'cn:; OF SAN BERNARDIC~
File No. 6.1444-3
- REQUr:jT FOR COUNCIL AC~ON
From: Roger G. Hardgrave
Dept: Publ ic Works/Engineering
Date: 11-12-86
Subject: Approva 1 of Change Order No. ONE --
Contract with Valley Crest Landscaping,
Inc., for construction of Phase I-A,
Zone B, of See combe Lake State Urban
Recreation Area, per Plan No. 6878
Synopsis of Previous Council action:
02-17-86 -- Work on Phase I-A, Zone A, in accordance with Plan No. 6667, approved
and accepted and final payment authorized at expiration of the lien
period.
Resolution No. 86-76 adopted authorizing execution of Agreement for
development of the Seccombe Lake State Urban Recreation Area.
Plans approved and authorization granted to advertise for bids.
Resolution No. 86-328 adopted, awarding contract to Valley Crest
Landscaping, Inc. for the low bid price of $915,000.00.
03-04-86
05-19-86
08-04-86
Recommemled motion:
That Change Order No. One to the contract with Valley Crest
Landscaping, Inc., for the construction of Phase I-A, Zone B,
of See combe Lake State Urban Recreation Area, per Plan No.
6878, be approved; to authorize the Contractor to delete the
Adobe Building re-construction, at a net decrease to the
contract price of $56,266.00, from $915,000.00 to $858,734.00.
cc: Ray Schweitzer
Warren Knudson
Annie Ramos
Signature
Contact person:
,Jon Rohprt,
Phone:
~??~
Supporting data attached: Staff Rpport P. rhangp Ornpr #1 Ward:
FUNDING REQUIREMENTS:
Amount: ($~fi, ?fifi on)
Source: D&c."....c..I'L .1.... f"""'~#.""""'''1
Finance: IJ,,:
C'~
.
Council Notes:
75.0262
Agenda Item No.
5-1
~
Cll::~ OF SAN BERNARDI::~ - REQUr:;T FOR COUNCIL Ac'2oN
STAFF REPORT
During removal of the northerly addition to the old Adobe Building,
portions of the North and East walls collapsed. All work within the adobe
construction area was discontinued and a security fence was erected to secure
the area and reduce liability exposure. Work on, or adjacent to the structure,
has been suspended pending a review by the City and State, of the acceptable
methods for reconstruction of the Adobe Building as a historical landmark.
Change Order No. One will direct Valley Crest Landscaping, Inc. to
continue with the removal of the remaining portions of the roof and brick gables,
removal of the newer southerly addition, shoring of the remaining portions of
the adobe walls, removal of debris, and salvaging the adobe bricks.
It has been determined that the adobe structure will be reconstructed
under a future contract, utilizing as much of the existing structure and
materials as possible. The credit amount of $56,266 will be available for
this reconstruction.
In order to allow the completion of the Seccombe Lake Project, and
obtain an acceptable restored adobe facility, it is recommended that the
restoration of the Adobe Building and its related site work be deleted from
the contract requirements with Valley Crest Landscaping.
The total deductive cost for deletion of the adobe structure and
amenities, not including $8,000 for demol ition, is $56,266.00, redu cing the
contract price from $915,000.00 to $858,734.00. This is based upon a detailed
breakdown of the Contractor's Bid Estimate.
We recommend that Change Order No. One be approved.
URGENCY CLAUSE:
A potential liability is created by the partially demolished adobe house.
Authority needs to be given to the Contractor to proceed with the demolition
in order to abate any possible liability exposure.
75-0264
. r
Pr<:lJ_.:t:
Seccombe Lake, Phase I-A, ~e B
.....
....,;
Date:
11-12-36
-
...J
Plan No. 6878
File No. 6.1444-3
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO. -1---
(Change necessitated because of field conditions)
Valley Crest Landscaping, Inc.
1920 So. Yale Street
TO: Santa Ana, CA 92704
Gentlemen:
You are hereby authorized and directed to delete the reconstruction of the
Adobe Building, (excepting demolition of the abutting structure,($8,000), and
construction of associated amenities, as follows:
Adobe House, Retaining Walls, Block/Stucco Wall, Teak Park Benches, Trash
Receptacles, Adobe Trellis, Decomposed Granite, Concrete Flatwork, Irrigation,
Landscaping and Electrical, at a lump sum credit of $56,266.00.
(Demolition of existing structure shall proceed in accordance with section 13015
of the contract specifications. All adobe bricks shall be salvaged).
$ ( 56,266.00)
Total extra work cost added to contract .............................
$ 915,000.00
Previ ous Contract Pri ce .............................................
$ 858,734.00
Amended Cost Pri ce ..................................................
Additional time to complete contract due to change order ............ -0-
CONTRACTOR:
CITY OF SAN BERNARDINO:
By:
By:
ROGER G. HARDGRAVE
Director of Public Works/City Engr.
Title:
Accepted Date:
Approvert Date: