- REQUEST FOR COUNCIl!' ACTION
CITY OF SAN BERNARDINO
From: ROGER G. HARDGRAVE
Dept: Pub 1 i cWo r k s / En gin e e r i n g
Date: 10-19-87
~EC~A~MINp~6val of Plans & Authorization
1'; orr "'> ,l;.p )l.dvertise for Bids--Construction
.n ~ 1..... 0 f .:s e1ri 0 r C it i zen s C e n t e r i n Per r i s
Hill Park, per Plan No. 7298
Synopsis of Previous Council action:
08-26-85 --- Resolution No. 85-338 adopted approving application for
$350,000 from Senior Citizens Bond Act.
June, 1986 --Allocation of $60,000, from 1986/87 CDBG Program, approved
for architectural services.
Resolution No. 86-499 adopted authorizing execution of
an Agreement with Kurt Meyer Partners for architectural
services.
June, 1987-- Allocation of $300,000 from Park Construction Fee Fund,
and $100,000 from 1987/88 CDBG Program, approved.
07-20-87 -- Finding made that construction of Senior Citizen Center in
Perris Hill Park needed for health and safety reasons.
12-08-86
Recommended motion:
That the plans for construction of a Senior Citizens Center
in Perris Hill Park, in accordance with Plan No. 7298, be
approved, and the Director of Public Works/City Engineer
authorized to advertise for bids.
cc: Ray Schweitzer
Harren Knudson
Ken Henderson
Annie Ramos
J}J1 vf;$pf!~
Contact parson:
Rngpr r, HArngrAvP
Phone:
~n?~
Supporting dete attached: Staff Reoort
Ward:
2
FUNDING REQUIREMENTS:
Amount: i Rnn Ann
Source:
(ACCT.
(ACCT.
NO.) 121-544-57551
DESCRIPTION) Senior Citizens Center -
Finance: C~\ Xl~. ,~_._
f,r 1..1 ""v"., t1 \-.-
Perris Hill Park
Council Notes:
9.
-
-
-
. CI"( .. OF SAN BERNARDI~"1) - REQUF~T FOR COUNCIL AC..,ON
STAFF REPORT
Page 1 of 2
Plans for the construction of this center have been prepared
by the Architect, and the project is ready to be advertised for
bids. The project consists, in general, of constructing a 5,600
square foot building, with a full service kitchen, meeting room,
activity rooms, lobby and restrooms.
The original site was south of the parking lot for
Fiscalini Field. Since the existing parking lot was to be used
for the center, no site development costs were included in the
original estimate. The parking lot off of 21st Street will now
be used to meet the parking requirements for the center. Widening
and resurfacing of this lot is included in the contract documents
as an additive alternate. This alternate will be included in the
contract award if sufficient funds are available, or if supplemental
funds can be secured.
Listed below is an estimate .of the total project cost:
Construction Contract
Architect's Fee (Lump Sum)
Topo Map & Preliminary Soils Test
(W.O. 1792)
Construction Inspection & Testing
Sub-Total
Contingencies (15%)t
TOTAL ESTIMATED PROJECT COST
Estimated Cost for Additive Alternate
$ 590,000
46,000
10,000
50,000
$ 696,000
104,400
$ 800,400
$ 56,000
Funds allocated to finance the cost incurred for this
project are:
1986/87 CDBG Program $ 60,000
1987/88 CDBG Program $ 100,000
1987/88 Park Construction Fee Budget $ 300,000
Senior Citizens Bond Act $ 350,000
TOTAL FUNDS AVAILABLE $ 810,000
An amendment to the Municipal Code is being processed, to
allow construction of buildings, such as a Senior Citizens' Center,
within an "0" Zone. This amendment is scheduled to become effec-
tive on 12-16-87. This amendment requires a Conditional Use
Permit for a building within an "0" Zone. An application for a
C.U.P. has been submitted, and is scheduled to be heard by the
Planning Commission on 12-15-87.
10-19-87
75-0264
-
. CI-L: OF SAN BERNARDIa> -
REQU~T FOR COUNCIL AC...."ON
~~ . .
Page 2 of 2
Approval of the grant from the Senior Citizen Bond Act was
conditioned upon the project being substantially under construc-
tion by April, 1988. In order to ensure adherence to this dead-
line, it will be necessary to advertise for bids concurrently
with the Code revision and C.U.P. processing. Bids are scheduled
to be received on 12-22-87, which is after the effective date of
the Code amendment and public hearing by the Planning Commission
on the C.U.P.
STAFF REPORT
We recommend that the plans be approved and authorization
granted to advertise for bids.
10-19-87
75-0264
CITY OF SAN BEp-'l/jARDINO
,-
MEMORANDU~. I
Subject
Approved
To
RAY SCHWEITZER
City Administrator
S c.h e d u 1 e for Act ion I t ems 0 n S e n i 0 r
Citizens Center -- Item No.8,
Aqenda of 11-2-87
From
ROGER HARDGRAVE, Dir. of
Public Works/City Engr.
November 2, 1987
File No. 7.3724
Date
Date
gfq
,
At the Agenda Briefing of 10-30-87, a question arose as to the
schedule for the amendment to the Municipal Code, processing
the Conditional Use Permit, and advertising for bids. It is
planned to prosecute these items concurrently, in order to meet
the deadline imposed for Senior Citizens Bond Act Funds.
Code Amendment --
First Reading
Second Reading
Effecti ve Date
11-02-87
11-16-87
12-16-87
Conditional Use Permit
Accept Application
Planning Commission
Hearing
Appeal to Mayor and
Council (if any)
11-02-87
12-15-87
01-04-88
Advertising for Bids & Award of Contract
Approval of Plans and 11-02-87
Authorization to Ad-
vertise
Receive Bids 12-22-87
Award Contract 01-04-87*
*Could be extended to second meeting of January, if appeal filed
on C.U.P.
I trust this information on dates will be sufficient to advise
the Mayor and Council on the schedule established for this proj-
ect. ase advise if yo ve any questions.
HARDGRAVE
of Public Works/City Engineer
RGH:rs