From: Roger G. Hardgrave
Dept: Public Works/Engineering
Date: 7-24-86
REC'D.-ADMllluaiNl: Approval of Change Order No. SEVEN -
Irrigation & Landscaping in Park Centre,
1986 JUL 2 Ii PM 12: 11 per Pl an No. 6760 --ARTHUR SHOOTER
ASSOCIATES, INC.
Synopsi$ of Previous Council action:
03-19-85 Final Action taken to establish Assessment District No. 961.
05-20-85 Plans approved and authorization granted to advertise for bids.
08-05-85 RES. No. 85-300 adopted awarding a contract for $528,063.00 to Arthur
Shooter Associates, Inc. for construction of irrigation and landscaping
in Park Centre Assessment District No. 961.
10-07-85 Change Order No. One approved to authorize payment for various items
of extra work at a net increase in the contract price of $102,456.00,
from $528,063.00 to $630,519.00.
(Continued on 2nd page)
Recommended moti.on:
That Change Order No. Seven to the contract with Arthur Shooter
Associates, Inc. for construction of irrigation and landscaping
at Park Centre, in accordance with Plan No. 6760, be approved;
to authorize the Contractor to repair wash-outs, remove silt and
re-seed lawn areas damaged by excessive rain runoff, at an
increase in the contract price of $2,569.15 from $651,129.70 to
$653,698.85.
cc: Ray Schweitzer, City Administrator
Warren Knudson, Director of Finance
JJA..6.f4
Con~tpenon: ~oger G HarQ9raVe
Supporting data attached: 5hff ~"PQrt & ("("0 r~o 7
Phone:
50?5
1
Ward:
FUNDING REQUIREMENTS:
Amount: $7 ,lifiq 1 Ii
Source: Prnr.ppd~ from A~~p~~mPnt
Finance: tJ:::. C' / A
District #961 --Account No. 251-633-53925
Cou ncil Notes:
75.0262
Agenda Item No.
7
,
Jl
Wi
u
-
CI~ OF SAN BERNARDQo - REQUQr FOR COUNCIL AC~N
STAFF REPORT
The Contractor, Arthur Shooter Associates, repaired the rain caused washouts
on three different occasions. This work was beyond the scope of the contract,
but essential to the functional requirements of Park Centre. The Contractor
failed to bill the City pending discussion of the situation and approval of a
Change Order to the contract. Daily work reports and equipment charges were
not submitted until after the Mayor and Council acted on Contract Change Order
Six and authorized final payment.
SYNOPSIS OF PREVIOUS COUNCIL ACTION Cont.
10-07-85 -- Change Order No. Two approved to authorize payment for various
items of work and deletions at a net increase in contract price
of $77.00 from $630,519.00 to $630,596.00.
12-02-85 Change Order No. Three approved to authorize payment for various
items of work and deletions, at a net increase in contract price
of $10,249.87, from $630,596.00 to $640,845.87.
04-07-86 -- Change Order No. Four approved to authorize payment for various
items of work and deletions, at a net increase in contract price
of $2,817.00 from $640,845.87 to $643,662.87.
05-19-86 Change Order No. Five was approved to authorize the contractor
to landscape and irrigate the extended portion of the island in
Hospitality Lane, at an increase in the contract price of $7,120.00
from $643,662.87 to $650,782.87.
06-07-86 -- Change Order No. Six was approved to authorize the purchase of
Val con Hi-Flo remote control valves at a net increase cost to
the contract of $346.83 from $650,782.87 to $651,129.70. The
work performed by the contractor, in accordance with specification
No. 6760 was approved and accepted; and final payment was authorized
at the expiration of the lien period.
75.0264
.I..
-
-
-
4 ~
c
o
o
o
Project: Landscape Improvements
for Park Centre
Plan No. 6760
Da te: 7-24-86
File No. 2.114
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO. 7
(Change necessitated because of field conditions)
To:
Arthur Shooter Associates
5703 Oberlin Drive, Suite 101
San Diego, CA 92121
Gentlemen:
You are hereby authorized and directed to perform the items of work
as follows:
1. Repair Wash-outs
2. Remove silt
3. Re-seed lawn area
The above items will be accomplished at a cost not to exceed $2,569.15.
Total extra work cost added to contract.................$
2.569.15
'Previous Contract Price..................................$
Additional time to complete contract due to change order
651.129.70
653.698.85
NONE
Amended Cost Price......................................$
CONTRACTOR
CITY OF SAN BERNARDINO
By:
Title:
By:
ROGER G. HARDGRAVE
Director of Public Works
Accepted Date: