CITY OF SAN BERNARDINO
Q No. 1.3660)
- REQUEST FOR COUNCIL ACTION
From: Roger G. Hardgrave 11t'1.. AI ",I. ....,ject:
Dept: Publ ic Works/Engineering 1986 JUN -5 PM 3: 58
Date: June 5, 1986
Approval of Change Order No. FOUR &
Approval & Acceptance of Work --Extension
of Hospitality Lane & Construction of
Bridge over San Timoteo Creek, per Plan
No. 6653 --BONAD1MAN-McCAIN, INO .
Synopsis of Previous Council action:
11/84 -- Authorization granted to submit project profile to EDA.
03/85 Resolution No. 85-111 adopted authorizing filing of an application for
Gran t with EDA.
09/85 Plans approved and authorization granted to advertise for bids.
09/85 -- Allocation of $293,000 approved in the Street Construction Fund, under
Account No. 242-362-57366 to finance the Local Agency share.
11/18/85 -- Resolution No. 85-492 adopted awarding a contract for the low bid price
of $490,777.60.
02/17/86
Change Order No. One approved to authorize the Contractor to furnish
steel piling material and weld to each side of steel pipe web, at an
(continued on 2nd Page)
Recommended motion:
1. That Change Order No. Four to the contract with Bonadiman-McCain, Inc.,
for the construction of a bridge on San Timoteo Creek, at Hospitality
Lane, in accordance with Pl an No. 6653 and EDA requi rements, be approved;
to authorize changes in final quantities from that estimated, change
orders on a time & material basis and particularly Bid Items 6, 15 & 22
and Contract Change Order No. Three that varied by more than 15%, at a
net increase in contract price of $13,804.84, from $517,929.29 to
$531,734.13.
2. That the work performed by the Contractor, in accordance with Specifi-
cation No. 6653, be approved and accepted and that final payment be
authorized at the expiration of the lien period.
John Matzer, Jr., City Administrator
. Warren Knudson, Director of Finance
cc:
OA ,K]~.
Signature
Contact person:
Gene Klatt
Phone:
~111
Supporting data attached: Staff Report & C. C. O. No 4
FUNDING REQUIREMENTS: Amound$13.804.84)
Account #242-362-57366 - Hospitality Lane Extension
Ward:
Source: Strppt rnnc:trllrtinn I='lInn
Finance: p... I'? J!'..~
Council Notes:
75-0262
Agenda Item NO'~
r
'-
03/17/86 --
05/03/06 --
05/03/86 --
.1"'"'-
~
o
)
increase in the contract price of $689.09, from $490,777.60
to $491,466.69.
Change Order No. Two approved to authorize the Contractor
to perform all work necessary to construct grouted rip rap
protection at an estimated increase in the contract price of
$44,212.60, from $491,466.69 to $535,679.29
Supplement to Change Order No. Two approved to authorize the
elimination of grout to the rip rap protection and reduction
of the estimated increase to the contract by change order
No. Two by approximately $20,000, from $535,679.29 to
$515,679.29.
Change Order No. Three approved to authorize Contractor to
furnish and install chain link fences and gates on a time and
material basis and as directed by the Engineer, at an estimated
increase in contract price of $2,250.00, from $515,679.29 to
$517,929.29.
CI~ OF SAN BERNARDlhb - REQUM- FOR COUNCIL AC~N
STAFF REPORT
Final bid quantities for Bid Items and contract Change Orders that
have increased or decreased by 15% must be approved by a balancing change
order. This is a requirement of the Economic Development Administration,
the funding agency for the San Timoteo Bridge Project.
Bid Item No.6, Aggregate Base, increased by 20% (550 tons) due to
unsuitable soils being discovered during construction. The Soils Engineer
changed the structural section of the street by increasing the aggregate
base from II inches to 16 inches in depth between stations 5+00 and 8+17,
at an increase in contract cost of $4,312.00.
Bid Item No. 12, Reinforcing Steel Bars, was underestimated by the
design engineer. Actual steel quantities exceeded the estimate by 20%
(13,661 lbs) at an increase in contract cost of $6,830.50.
Bid Item No. 22, Concrete Block Wall, was deleted from the contract.
During construction it was discovered that the wall was unnecessary as the
fill to be placed could be sloped safely without utilizing the retaining wall.
Contract Change Order No. Three approved chain link fencing and two
drive gates, as required by the San Bernardino County Flood Control District.
This work was done on a time and material basis at an estimated amount of
$2,250.00. The actual cost of this work was $3,177.39.
The extension of Hospitality Lane and construction of the bridge over
San Timoteo Creek was satisfactorily completed May 23, 1986.
The contract was awarded for the low bid price of $490,777.60. The
actual final contract price is $531,734.13, due to the requirements by the
San Bernardino County Flood Control District for slope protection and chain
link fencing and increased quantities in aggregate base and reinforcing steel.
The total increase of 8% is within the 10% contingencies of the low bid cost
of the contract.
We recommend that the work be approved and accepted and that final
payment be authorized.
7'io.0:)';4
Project: San Timoteo Bridge
Date:
6-5-86
File No. 1.366
,
"
Pl an No. 6653
r
l~"
,J
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO. -L
(Change necessitated because of field conditions)
Bonadiman - McCain, Inc.
280 So. Lena Road
P. O. Box 6444.
San Bernardino, CA 92412
TO:
Gentlemen:
Authorization is hereby given for a balancing change order for bid items where quantities
changed by 15% and for change orders that were on a time and material basis. Tabulation
. is as follows:
Est. Final Contract
Bid Item Units Quan. Quan. Price Increase
6. Aggregate Base Ton 2,650 3,200 $ 7.84 $ 4,312.00
15. Reinforcing Bars Lbs. 67,000 80,661 0.50 $ 6,830.50
22. Cone. Blk. Wall L. F. 88.5 0.00 10.00
CCO
#3 Chain Link.Fencing T&~' $ 2,250 $3,177.39 T & M 927.39
Various Items & Change Orders 2,619.95
Decrease
$ 885.00
Total extra work cost added to contract .............................$
13,804.84
Previ ous Contract Pri ce .........................................................................................
$ 517,929.29
$ 531,734.13
Anlended Cost Pri ce ....................................................................................................
Additional time to complete contract due to change order ............
-0-
CONTRACTOR:
CITY OF SAN BERNARDINO:
By:
By:
ROGER G. HARDGRAVE
Director of Public Works/City Engr.
Title:
Accepted Date:
Approved Date: