Approval of Plans & Authorization to
Advertise for Bids -- Construction of
Addition to Restroom Building for
Elk's Field at Wildwood Park, per Plan
No. 6949
Dept: Public Works/Engineering
Date: March 12, 1986
Synopsis .of Previaus Cauncil actian:
Allocation of $42,000 to finance the cost for this addition.
Recommended mation:
That the plans for construction of an addition to the restroom for
Elk's Field, at Wildwood Park, in accordance with Plan No. 6949,
be approved; and the Director of Public Works/City Engineer authorized
to advertise for bids.
cc: Ray Schweitzer
Wa rren Knu dson
Annie Ramos
~ 1,[:~
Contact person:
Roger G. Hardgrave
Phane:
5025
4
Supporting data attached: Sta ff REport
Ward:
FUNDING REQUIREMENTS:
Amaunt: $51.000
saurce:n ~~rk Construction Fund -- Ace
Finance:; A'(J S'11l-H\~I:-' JI _
No. 243-363-57525
Council Nates:
7:;~262
Agenda Item No.
5-1{-
CIT . OF SAN BERNARDI"~O - ReQUI:~T FOR COUNCIL AC-~ON
.. .
1s.-~64
STAFF REPORT
Plans for this addition have been prepared by the Engineering Division, and
the project is ready to be advertised for bids. The project consists, in
general, of constructing a 15' x 18' addition to the existing concession
building in order to provide 2 restrooms.
Listed below is an estimate of the total project cost.
Construction Contract -
$40,968
3,400
$44,368
6,632
$51,000
Engineering & Inspection (W.O. #1469)
Sub-tota 1
Contingencies (15%) 1
TOTAL ESTIMATED PROJECT COST
An amount of $31,500 has been allocated from Roberti-Z'berg Funds, and $10,500 in
City Funds, under Account No. 243-363-57525, to finance the costs ~ncurred for
this addition. Supplemental funds may need to be provided, prior to award of a
contract, to fully finance this project.
We recommend that the plans be approved and authorization granted to advertise
for bids.
URGENCY CLAUSE:
It is essential that authorization to advertise be granted as soon as possible,
in order to comply with the schedule established for this project.