- REQU.T FOR COUNCIL A~ON
, From:
.:
ROGER G. HARDGRAVE, Director
Subject: Approval of Change Order No. Four __
Construction of Two Racquetball
Courts at Boys Club per Plan No. 6684
SCC GENERAL CONTRACTOR
Public Works/Engineering
Date: 2/28/86
Synopsis of Previous Council action:
01-18-85
Plans approved and authorization granted to advertise for bids.
09-09-85
Report of Competitive Bid Opening accepted and filed; and matter of
required supplemental funding referred to RDA Committee
Supplemental funding in the amount of $40,000 approved.
Resolution No, 85-392 adopted awarding the contract to the low
bidder for the low bid price of $138,760.00,
(See page 2)
09-23-85
10-07-85
Recommended moti,on:
.
That Change Order No. Four to the contract with SCC General Contractors, for the
construction of two racquetball courts at the Boy's Club, in accordance with Plan
No. 6684 be approved; to authorize the contractor to reconstruct the existing air
conditioning system reinstall existing electrical lights, outlet fixtures,
thermostat and install 75 L,F. of gas line to the new air conditioning unit, at a
net increase in contract price of $2,154.58, from $142,392.63 to $144,547.21.
cc: Ray Schweitzer, Assistant City Administrator
(A~
Signature
Contact person: Rogl'r G. Hardgrave
Phone:
5025
Supporting data attached: Staff Report
Ward:
6
FUNDING REQUIREMENTS:
Amount: $?' Q~ ~R
Source: r.nRG Fllnd~
Finance:
WCil Notes:
75-0262
Agenda Item No. RS- 5
.
.
.
~~
.
02-17-86
03-03-86
03-03-86
.
.
.
Change Order No. One referred back to Staff for cost renegotiation
with contractor,
Change Order No, Two, on the agenda for approval to authorize the
contractor to construct windows into two doors at an increase in
contract price of $228.44, from $140,968,44 to $141,196.88.
Change Order No, Three, on the agenda for approval to authorize
the contractor to fur the court walls to meet the required dimension
necessary to install the courts at an increase in contract price of
$1,195.75, from $141,196.88 to $142,392.63.
-2-
-~
(
CI. OF SAN BERNARDeO - REQU.T FOR COUNCIL A~ON
.
.
.
15-0264
STAFF REPORT
The plans and specifications for the room adjoining the racquetball
courts do not direct relocation of the eight existing florescent light
fixtures; re-arrangement of the eight air-conditioning ducts and registers;
relocating existing electrical outlets (located in the concrete floor);
relocating the thermostat for the air-conditioning unit; and installing
about 75 lineal feet of a 3/4-inch gas line, from the crawl space. located
above the control section of the existing building, to supply the two new
air-conditioning units to be installed under this control.
A suspended ceiling with compatible light fixtures was installed
when the building was originally constructed. The plans for the two
racquetball courts direct the removal of this suspended ceiling and in-
stallation of a normal drywall ceiling. However, the plans do not direct
the installation of the necessary framing details to accommodate the lights
and air-conditioning registers, An interior wall has been removed to
provide a lobby for the courts, It will be necessary to install a conduit
in the floor to accommodate necessary revisions to the electrical circuit,
It will be necessary to saw cut the existing concrete floor, install a
conduit, and pull new conductors in order to maintain electrical power to
this circuit.
The plans also do not indicate how the eight existing A/C ducts
and registers, in the room to be remodeled as a lobby, will necessarily
be modified, The registers must be framed in and the A/C duct system
reconstructed to be compatible with the new drywall ceiling, The Archi-
tect has issued a verbal instruction on how the Contractor is to complete
this work, consisting of sealing off six of the existing ducts and
extending two ducts to the new registers. The existing thermostat also
had to be relocated, as it was on a wall that was removed.
The plans also do not direct installation of a gas line to provide
service to the two new A/C units. Seventy-five feet of 3/4" gas line
must be plumbed from a point near the existing kitchen and a connection
must be made at that point.
The Contractor has quoted a price of $2,154.58 to do these items
of work. We feel this is a fair and reasonable price for the amount and
type of work involved,
The total estimated project cost, based upon the actual low bid
price, contained an amount of $22,140 for contingencies, which can be used
to finance the cost of this extra work. We recommend this change order be
approved.
A copy of the Estimate for Change Order, by Michael Murphy, Archi-
tect, with a breakdown of this cost is attached for reference.
Change Order No, One was referred back to staff for renegotiation
with the Architect. The Architect has been contacted, and recommends that
negotiations be deferred until the end of the project when all change orders
can be done at one time.
-3-
-
-
-
.
Project:
Construction of Two R.etball
Courts at the Boy's Cl
.
,Da te:
2-28-86
.
6684
No.
File No. 6.1450
~ '.. ...
EN GIN EE R IN G 0 I V I S ION ...' ,
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO, Four
(thange necessitated because of field conditions)
To:
SCC General Contractor
22816 La Pa i x
Grand Terrace, CA 92324
Gentlemen:
You are hereby authorized and directed to reconstruct the existing
A/C system, reinstall existing electrical lights, outlet fixture,
thermostat and install 75 L,F. of gas line to the A/C unit at an
agreed price of $2,154.58.
~
Total extra work cost added to contract"...";..,,..,..$ 2,154.58
Previous Contract Price.................................$ 142,392.63
Am end e d Co s t P ri c e . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 144,547. 21
Additional time to complete contract due to change orderS 5 days
CONTRACTOR
,CITY OF SAN BERNARDINO
By:
Title:
'By:
ROGER G, HARDGRAVE
Director of Public Works
.
'.
Accepted Date:
Approved Date: