. C.-It' OF SAN BERNARD.tto - REQU"T F~~e ~~~~~IL ACtiON
t[:
Roger G. Hardgrave
Public Works/Engineering
Subject: Approval of Plans and Authorization to
Advertise for Bids -- Upgrade Lighting
for Richardson Jr. High School Ballfield,
per Plan No. 6892
Date:
February 6, 1986
Synopsis of Previous Council action:
10-07-85 --- Expenditure of $38,000 from CDBG funds, for repair of ballfield
lighting at Richardson Field, approved.
Recommended moti,on:
~
That the plans for upgrading the lighting for the Richardson Jr.
High School Ballfield, in accordance with Plan No. 6892, be approved;
and the Director of Public Works/City Engineer authorized to advertise
for bids.
cc:
Ray Schwe i tzer
Annie Ramos
cA c!:dl:~
Contact person:
Roger G. HardQrave
Phone:
5025
3
Supporting data attached: Staff Report
Ward:
FUNDING REOUIREMENTS:
Amount: $44,850
Source: Account No, 240-360
~71~n. Richardson Ballfield LiQhtinQ
.Cil Notes:
F;~f'~ r~(}
75-0262
Agenda Item No. R 5 - -3
CIA:' OF SAN BERNARDlo - REQUAT FOR COUNCIL AC"ON
.
STAFF REPORT
The Plans, specifications and estimate for these improvements have
been prepared by the Engineering Division, and the project is ready to be
advertised for bids,
Listed below is an estimate of the total project cost.
Construction Contract --------------------- $34,000
Engineering & Inspection (W.O. #1469)
Sub-Total
5,000
Contingencies (15%)
TOTAL ESTIMATED PROJECT COST
$39,000
5,850
$44,850
~
The project consists, in general, of removing the existing
lighting system and installing a new system, that will be more energy
efficient and provide a higher level of lighting on the playing field.
At the Council Meeting of 10-07-85, an amount of $38,000 was
allocated from CDBG Funds to Account No, 240-360-57150, to finance the
costs incurred for upgrading the lighting system for this ballfield.
We recommend that the plans be approved and authorization
granted to advertise for bids.
URGENCY CLAUSE
The plans for this project will have to be approved by the State Architect,
since the site is school property. It is vital that advertising be
started immediately upon approval by the State Architect, in order to
have the new lighting system in operation by the start of the softball
season.
.