CI~Y OF SAN BERNARDINO - REQUES~ FOR' COUNC.(I'"'gON
From: Roger Hardgrave REC'D. - ADMIN. Qttlect:
Dept: Public \-Jorks/EngineeriW~ fEB -6 PH 3: 1,6
Date: 2-6-86
Approval of Change Order No, One
--Extension of Hospitality Lane
and Construction of Bridge on
San Timoteo Creek, per Plan No,
6653 -- BONADIMAN-McCAIN, INC.
Synopsis of Previous Council action:
November, 1984 Authorization granted to submit project profile to
EDA
March, 1985 Resolution No, 85-111 adopted authorizing filing
of an application for 8rant with EDA
September, 1985 - Plans approved and authorization granted to ad-
vertise for bids,
SePtember, 1985 - Allocation of $293,000 approved in the Street
Construction Fund, under Account No, 242-362-57366
to finance the Local Agency share,
(Continued on 2nd Page)
Recommewled motion:
That Change Order No. One to the contract with
Bonadiman-McCain, Inc, for construction of a bridge
on San Timoteo Creek at Hospitality Lane, in
accordance with Plan No. 6653, be approved, to
authorize the contractor to furnish steel piling
material and weld to each side of steel pipe web,at
an increase in the contract price of $689,09, from
$490,777,60 to $491,466,69,
cc: Ray Schweitzer, City Admin,
,(arren Knudson, Dir, of Fiil:mce
;) ) .-d:
Ik1 4-; v~~/'--
SignalUre
Contact person: __. _.. . . Gene. R,..Kla t.L.
Phone:
5111
1
Supporting data attached: _S taff Rpt... & Cl1ang",,_ Or:.der--".o :.~ Ward:
FUNDING REQUIREMENTS:
Amount: $639,09
Source: Street Construction Fund,
Acct,#242-362-57366-Hospitality Lane Extension
\ -t
Finance:.i- -;~J!
( .! . .
"'; / ----.It' 1- Vvt4...c,/\ (]
r.., ~
i
Council Notes:
Agenda Item No,L ~~.
n.,.0262
_._----._..._-_._._-_.--._----_._~~._-_.
- ~ . - -
CI'l.,_' OF SAN BERNARDI~ ,0 - REQUEr-T FOR COUNCIL ACT 'N
STAFF REPORT
The specifications state that the steel piles be driven
at a minimum bearing resistance, However, during the driving of
4 piles, it was discovered that the minimum bearing resistance
was not being achieved,
Our Resident Bridge Engineer directed the Contractor to
\.Jeld "lugs" on each side of these 4 piles, in order to increase
the cross sectional area and, thereby, increase the bearing
resistance, This extra work was done on a time and materials
basis for an estimated cost of $689,09,
The total estimated project cost included an amount of
$81,822,40 for contingencies, which can be used to finance the
cost of the change order,
We recommend that Change Order No, 1 be approved,
SYNOPSIS OF PREVIOUS COUNCIL ACTION Continued
11-18-85 - Resolution No, 85-492 adopted awarding a contract
for the low bid price of $490,777,60,
75-0264
Projcct:
,
San Timotco Creck Bridge
(Hospitality Lanc)
Plan No. 6653
D ate: J an u a r y 31, 1 986
File No.
1.366
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO.-1-
(Change necessitated because of field conditions)
TO; Bonadiman-McCain, Inc.
P.O. Box 6444
San Bernardino, CA. 92412
Gentlemen:
You are hereby authorized and directed to perform work at force account
as follows:
1. Furnish steel piling material and weld to each side of steel pile
web, four feet from tip of each pile as directed by the Engineer.
.
Total extra work cost added to contract..............,.........$
689,09
Previous Contract Price........................................$ 490,777,6L
Amended Cost Price.............................................$ 491,466.69
Additional time to complete contract due to change order....... 0
CONTRACTOR:
ByL)~, k LQ,\ (\='
Title: ~f7
CITY OF SAN BERNARDINO
By:
ROGER G. HARDGRAVE
Director of Public Works/City Eng.
^ccepted Date:
Appr-oved Date: