CITY OF SAN BERNARDINO - REQUEST FOR COUNCil: ACTION
From:
~EC'D -ADM''' OF~
Roger G. Hardgrave . ,,,.. 'Subject:
. .. !SSG J,\N 23 :~: 3: :;2
PubllC Works/Englneerlng .
Approval of Contract Change Order
No. One -- Construction of Seccombe
Lake Storm Drain Lateral, per Plan
No. 6769 --Kershaw Construction
Dept:
Date:
1-17 -86
Synopsis of Previous Council action:
3-07-85
----Transfer of $7,125 to Account No. 48-510-673, "Seccombe Lake Storm
Drain Lateral," approved.
Plans approved and authorization granted to advertise for bids.
Resolution adopted awarding a contract to Kershaw Construction
Company, for the low bid price of $175,282.00.
7-15-85
9-09-85
Recommended motion:
That Change Order No. One to the contract with Kershaw Construction
Company, for the construction of Seccombe Lake Storm Drain Lateral,
in accordance with Plan No. 6769, be approved; to authorize payment
for removal of a concrete structure and for time lost due to
unmarked water lines, on a time and materials basis, for a cost not
to exceed $3,667.09, for an increase in the contract price from
$175,282.00 to $178,949.09.
cc: John Matzer, Jr., City Admin.
Warren Knudson, Dir. of Finance
{A;Zt~
Signature
Contact person:
Roger G. Hardgrave
Phone:
5025
Supportingdataattached:~.if Report & Resolution
Ward:
I
FUNDING REQUIREMENTS:
Amount: $3,667.09
Source: Storm Drain Construction
Finance: j.J ''-.- (?,A:~
Fund - Account No. <48-36e-5181o
Council Notes:
75-0262
Agenda Item No.
J~,
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
During excavation for the storm drain, the Contractor encountered an
abandoned reinforced concrete vault. This structure was not shown on the
plans, since it was not of record and its existence was unknown. Removal of
this abandoned vault was required in order for the storm drain and appurten-
ant facilities to be installed in accordance with the plans and specifications.
Two water mains were also broken by the Contractor during excavation. These
mains were not shown on the plans since the serving utility was not aware of
their existence. The Contractor was compelled to shut down his entire crew,
consisting of 6 personnel and 4 pieces of equipment, for a hour.
Payment to the Contractor will be made on a time and materials basis,
for removal of the vault and shut down time.
The total estimated project cost, based upon the actual low bid price,
contained an mount of $28,918 for contingencies, which will be used to finance
the cost of this change order.
We recommend Change Order No.1 be approved.
75.0264
yr")ject: Seccombe Lake Storm Drain'Lateral
f-lan No. 6769
Date: 1-17-86
File No. 4.424
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNAnDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO. ~
(Change necessitated because of field conditions)
Kershaw Construction Company
P. O. Box 9
iO: Montclair, CA 91763-0009
Gentlemen:
You are hereby authorized and directed to perform work as follows:
I. Remove a reinforced concrete structure and plug adjoining conduits.
2. Compensation for one hour time lost due to the breaking of two
unmarked water mains.
Work shall be done on a time and materials basis not to exceed $3,667.09.
Tota 1 extra work cost added to contract ............................. $ 3,667.09
. P . $ 175,282.00
Prevlous Contract rl ce .............................................
Amended Cost Price ..................................................$ 178,949.09
Additional time to complete contract due to change order
............
2 days
CONTRACTOR:
CITY OF SAN BERNARDINO:
By:
By:
ROGER G.' HARDG'RAVE
Director of Public Works/City Engr.
Title:
Accepted Date:
Approved Dote: