CITY OF SAN BERNARDINO -
FiONO. 1.630 :>
REQUEST FOR COUNCIL ACTION
From: M. Moreno & R. Hardgrave
Subject: Recommendations for Reconstruction/
Resurfacing Major Arterials -- Second
Apportionment of SB 300 Funds in
1985-86
Dept: Publ ic Services & Publ ic Works
Date: 12-20-85
Synopsis of Previous Council action:
11-04-85 -- "Additional allocation of $460,000 from SB 300 Funds, if and when
available, be restricted to major arterial projects within the City
on a priority basis as established by the City Engineer and Director
of Public Services, irrespective of wards."
Recommended motion:
That the joint recommendation for reconstruction/resurfacing of
major arterials, from the second apportionment of SB 300 Funds,
be approved,
/l1l~ f /771flU/YV'~ X
Signature
~z~~
Contact person: M. Moreno & R. Hardgrave
Supporting data attached: Sta ff Report
Phone:
5045 and 5025
Ward: 1,2,3,4,5,6 & 7
FUNDING REOUIREMENTS: Amount:
Sou rce:
Finance:
Council Notes:
75-0262
Agenda Item No,
J~,
.
c 0
CITY OF SAN BERNARDINO -
-
o ;;
REQUEST FOR COUNCIL ACTION
STAFF REPORT
Recommended reconstruction/resurfacing projects for the second
apportionment of SB 300 funds are set forth below:
No.
Street
Limits
Estimated
Cost
$ 226,700
$ 12,825
$ 17,228
$ 54,586
$ 35,684
$ 51,2Ql
$ 47,182
$ 25,028
$ 470,434
The total is slightly over the anticipated second apportionment of
$460,000. However, it is very likely that enou9h cost savings could be
realized on other projects to finance the total amount,
1.
2,
3,
4.
Kendall Dr, to Electric Ave.
Randall Ave. to Mill St.
Waterman Avenue to Steel St,
Santa Ana River to Central
The estimate for 40th Street is based upon the work being done by
contract, under a cooperative agreement with the County. The total estimated
cost is $320,200, with $93,500 (29.2%) being financed by the County. This
estimate is based upon the "worst case" situation, and includes removal of all
existing pavement. If it is determined that all, or a portion, of the existing
pavement will match the grade of the future widening and can be retained, the
cost will decrease accordingly.
40th Street
Pepper Avenue
Wi er Road
Waterman Avenue
(Southbound only)
Highland Avenue
Arrowhead Avenue
Arrowhead Avenue
"H" Street
Sierra Way to Waterman Ave,
Sixth St, to Baseline St.
Highland Ave. to 29th St.
16th St. to Highland Avenue
TOTAL
The estimates for the other streets were prepared by the Public
Services Department on the basis of heating and remixing, and applying I inch
asphalt concrete resurfacing.
5,
6.
7,
8.
We recommend that this priority list be approved,
URGENCY CLAUSE:
All SB 300 funds are to be spent or expended by June, 1986. Therefore, it is
essential that an early decision be made on which streets are to be reconstructed/
resurfaced with these funds.
75-0264