HomeMy WebLinkAboutS03-Public Works ._- ----- CiT\f OF SAN BERNARDlko - REQUbJyNOFOF:9 COUNCIL AC'o~ON From: Roger G. Hard9rave Dept: Publ ic l~orks/Engineering Subject: Approval of Change Order No. One -- Contract for Grading, Irrigation and Hydrospraying of Lawn at Al Guhin Park, per Plan No. 6626 --Bob Britton,Inc. Date: 10-I-B5 Synopsis of Previous Council action: 1983/84 Budget Allocation of $106,000.00 for improvement of Al Guhin Park 6-17-85 _________ Authorization to advertise for bids on Phase I construction, per Plan No. 6626 6-22-85 _________ Adoption of Tentative Budget for Parks Department including an additional $94.000.00 for Al Guhin Park, Phase I con- struction. 8-05-85 ________ RES. 85-314 adopted awarding a contract to Bob Britton, Inc. for the low bid price of $143,853.82. Recommended motion: , That Change Order No. One to the contract with Bob Britton, .Inc., for the Grading, Irrigation and Hydrospraying of Al Guhin Park, in accordance with Plan No. 6626, be approved; to authorize payment for changing the electrical service from single phase to three-phase at an increase in the con- tract price of $450.00, from $143,853.82 to $144,303.B2. cc: John Matzer, Jr" City Administrator Warren Knudson, Dir. of Finance Annie Ramos, Dir. of Parks, Rec. & Community Services (A, /'~ Signature Contact penon: Gene R. Klatt Supporting data attached: Staff Report & C. C. O. tlo. 1 FUNDING REOUIREMENTS: Amount: $450.00 Account 243-361-57506 Phone: 5125 Ward: 5 Source: Park Construction Fund - Finance: , , /J- Council Notes: S~3 CI1( / OF SAN BERNARDK'D - REQU~"jT FOR COUNCIL AC .ION 75-0264 STAFF REPORT The plans and specifications were designed to provide single phase electrical service for the irrigation controller. Three phase power will be required when the park is fully developed with the planned facilities. Southern California Edison has recommended that 3-phase power be provided at this time. since it will be less costly than converting when further development occurs. The Contractor has quoted a price of $450.00 for providing 3-phase power, in lieu.of single phase. We feel. this is a fair and reasonable price, and much cheaper than providing 3 phase power in the future. The total estimated project cost, based upon the actual low bid price, included an amount of $16,546.18 for contingencies, which can be used to finance' the cost of this change order. We recommend Change Order No.1 be approved. URGENCY CLAUSE It is essential that approval of this change order be obtained as soon as possible in order to. avoid delaying completion of the project. , I.....n No. G~G IRRIGATION AND HYDROSEEDING AT AL GUHIN PARK 6626 ,-~j Dilte: 10/2/85 File No. 6.1459 .. Project: ENGINEERING DIVISION DEI'Arnr4CNT OF PUBLIC WO({K..~)- CITY OF SAN BERNARDINO', CALIFORNIA CONTRACT C!lANGE ORDER NO. ONE (Change necessitated because of field conditions) TO: BOB BRITTON, INC. Gentlemen: You are hereby authorized and directed to change the electrical service from single phase to three-phase at a lump sum increase of contract price of $450.00. .. ~ Total extra work cost added to contract .............................$ 450.00 P . C t t P '. $ 143 853.82 reVlOUS on rac r1ce ............................................. , Amended Cost Pl'"'ice ........:.............................................~$144303 8? . : . . Additional tifue to complete contract due to change order ..~......... 2 days CONTRACTOR: CITY OF SAN BERNARDINO: By: Title: .. ROGER G. 1IJ\110GIM"VE Director. ,of Publ ic Works/City Engr. ,By: Accepted Date: Approved Date: .