Dept: Pub1 ic Works/Engineering
Date: January 10, 1985
Subj~: Approval of P1 ans and Authori zati on
to Advertise for Bids --Construction
of Sewer Mains in Valley Truck Farm
Area on South Waterman Avenue, per
Pl an No. 6608
,From: Roger G. Hardgrave
Synopsis of Previous Council action:
4-16-84 -- Direction given to prepare plans.
5-07-84 -- Statement of Community Development Objectives and Use of Community
Development Block Grant Funds for FY 1984-85 adopted.
1-07-85 -- Supplemental funds allocated.
Racommended motion:
That the plans for construction of sewer mains in the Valley Truck
Farm Area on South Waterman Avenue, in accordance with Plan No. 6608,
be approved; and the Director of Public Works/City Engineer authorized
to advertise for bids.
cc: John Matzer, Jr., City Admin.
Herb Wessel, Gen. Mgr., Water Dept.
Manuel Moreno, Jr., Dir. of Public Services
c!Ju~ .~~
Signature
Contact person: Roger G. Hardgrave Phone: 5025
Supporting data attached: Staff Report Ward: 3
FUNDING REQUIREMENTS: Amount: Source: CDBG Funds
Finance: p- I? /I' A-
Council Notes:
75-0262
Agenda Item No.R.7
o 0
CITY OF SAN BBRNARDINO
o 0
- REQUEST FOR COUNCIL ACTION
STAFF REPORT
The plans for this project have been prepared by the Engineering Division, and
the project is ready to be advertised for bids.
Listed below is an eetimate of the total project cost:
Construction Contract: $ 501,305
Engineering & Inspection (W.O. #1373) 30,000
Sub-Total $ 531,305
79,695
TOTAL ESTIMATED PROJECT COST $ 611,000
An amount of $400,000 was provided in the 1984-1985 Comunity Development
Block Grant program for this project. Supplemental funds have been advanced
from the Sewer Line Construction Fund to cover the total estimated project,
with the understanding that they will be reimbursed from the 1985-1986 CDBG
program. In addition, approximately $109,000 in Jobs Bill funds will be made
available for this project.
The plans have been prepared to direct the inetallation of a sewer lateral to
the property line of each parcel with an inhabitable dwelling unit(s). This
is in accordance with our understanding of the intent of the Council actions.
There are approximately 200 parcels within this area. Sewer plant capacity
fees have been paid for about 64 parcels.
We recommend the plans be approved and staff be authorized to go out for bid.