HomeMy WebLinkAboutItem 1: Revised: 2023-06-26 Capital Improvement Projects Status Report- RevisedCAPITAL IMPROVEMENT PROGRAM STATUS REPORT Presented by City of San Bernardino Public Works Department June 26, 2023 1 Presentation Agenda •Project Delivery •Capital Improvement Program (CIP) Overview •CIP Projects •CIP Project Budget Status •Project Management Staffing Level 2 Project Delivery Phases 3 Project Delivery Workflow Process Project Planning (6 months to 1 year) Design (6 months to 1 year) Advertise and Award (3 months) Construction (6 months to 1.5 years) Project Close-out (3 months) PLANNING DESIGN CONSTRUCTION 2 years to 4 years 4 Capital Projects by Phase 5 16 27 12 17 38 34 0 5 10 15 20 25 30 35 40 Planning Design Advertise/Award Construction Close-Out Not-Activated Number of Projects Total 144 Capital Projects Capital Projects Funding by Phase 6 $117,695,128 $30,640,349 $21,259,490 $0 $20,000,000 $40,000,000 $60,000,000 $80,000,000 $100,000,000 $120,000,000 $140,000,000 Planning / Design / Construction Close-Out Not-Activated Total $169.6 million Capital Improvement Program. Not-activated include projects not assigned to staff or no approved funding. Capital Projects by Category 7 22 Building Projects, 15%, 13 Active Projects 31 Parks Projects, 22%, 12 Active Projects 9 Storm Drain Projects, 6%, 4 Active Projects 51 Streets Projects, 35%, 27 Active Projects 28 Traffic Controls Projects, 20%, 16 Active Projects 3 Other Projects, 2%, 0 Active Projects Buildings Parks Storm Drains Streets Traffic Controls Others Capital Projects Funding by Category 8 $21.7 M Building Projects, 13% $20M Active Projects $36.6M Parks Projects, 21% $28.6M Active Projects $14.9 M Storm Drains Projects, 9% $10.4M Active Projects $70.1M Streets Projects, 41% $43.1M Active Projects $16.6M Traffic Controls Projects, 10% $15.5M Active Projects $9.6M Other Projects, 6% $0M Activated Buildings Parks Storm Drains Streets Traffic Controls Others 9 Encanto Community Center Improvements CIP #2 Project Category: Building Ward: 1 Project Description: Estimated Total Project Cost:$3,394,315 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Construction Within Budget Budget: $3,394,315 Current Project Status and Timeline: Budget Status: Remodel and rehabilitate the Community Center. Estimated Project Completion: 6/30/2020Project Approval Date: 07/2024 10CIP #4 5th Street Senior Center Kitchen – Phase 2 11 California Theater Renovation CIP #6 Project Category:Building Ward: 1 Project Description: Estimated Total Project Cost:$4,870,431 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Design Construction Budget Status:Within Budget 08/2025 The improvements include pipe organ restoration, sound system upgrades, structural and safety improvements, lighting, HVAC, ADA compliance, and related improvements at California Theater. Project Approval Date: 6/30/2021 Budget: $4,870,431 Current Project Status and Timeline: Estimated Project Completion: Carousel Mall Demolition CIP #7 Project Category:Building Ward: 1 Project Description: Estimated Total Project Cost:$8,084,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction 02/2024 Budget Status:Within Budget The improvements include hazardous material abatement and demolishing the existing facilities at Carousel Mall. Project Approval Date: 6/30/2022 Budget: $8,084,000 Current Project Status and Timeline: Estimated Project Completion: 13 Paul Villaseñor Library Building Improvements CIP #8 14 New Animal Shelter CIP #10 Project Category:Building Ward: 3 Project Description: Estimated Total Project Cost:$219,046 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Planning Design Construction Construction Budget Status:Within Budget 03/2027 New animal shelter building, parking, walkways, and exercise yards. Project Approval Date: 6/30/2020 Budget: $378,675 Current Project Status and Timeline: Estimated Project Completion: 15 Installation of Automatic Entry Doors at Six Locations CIP #11 Project Category:Building Ward: 1 Project Description: Estimated Total Project Cost:$461,685 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Estimated Project Completion: Budget Status:Within Budget 07/2023 ADA compliant automatic doors replacement. Project Approval Date: 6/30/2020 Budget: $867,683 Current Project Status and Timeline: 16 Perris Hill Senior Center Roof Replacement CIP #13 Project Category:Building Ward: 2 Project Description: Estimated Total Project Cost:$205,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction 08/2023 Budget Status:Within Budget Project Site Map Rehabilitate existing roof structure and related improvements at Perril Hills Senior Center facility. Project Approval Date: 6/30/2020 Budget: $250,000 Current Project Status and Timeline: Estimated Project Completion: 17 Police Locker Room Renovation CIP #14 18CIP #17 City Hall Server Room HVAC Project Category:Building Ward: 1 Project Description: Estimated Total Project Cost:$221,375 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Budget Status:Within Budget 10/2023 Install new AC units. Project Approval Date: 12/7/2022 Budget: $221,375 Current Project Status and Timeline: Estimated Project Completion: 19CIP #18 Regal Theatre HVAC System Project Category:Building Ward: 1 Project Description: Estimated Total Project Cost:$389,693 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Budget Status:Within Budget 10/2023 Replace 8 new AC units. Project Approval Date: 12/7/2022 Budget: $389,693 Current Project Status and Timeline: Estimated Project Completion: 20CIP #19 One Stop Permitting Center 21 Jerry Lewis Swim Center Improvements CIP #24 Project Category:Parks Ward: 7 Project Description: Estimated Total Project Cost:$174,352 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Project Completion: Budget Status:Within Budget 09/2023 The Jerry Lewis Swim Center was last remodeled in 1993. This is the most utilized aquatic facilities. The scope of work is to install pool heaters. Project Approval Date: 6/30/2020 Budget: $190,000 Current Project Status and Timeline: 22CIP #27 Pioneer Memorial Cemetery & Seccombe Lake Improvements: Fence Installation Project Category:Parks Ward: 1 Project Description: Estimated Total Project Cost:$590,829 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design / Construction Construction Project Completion: Budget Status:Within Budget 10/2023 Install 7'-high wrought iron security fencing and gates along the perimeter of Seccombe Lake Park and Pioneer Memorial Cemetery. Project Approval Date: 6/30/2021 Budget: $590,829 Current Project Status and Timeline: 23CIP #28 Wildwood Park & Encanto Park – Phase 1: Baseball / Softball Field Repair Roosevelt Bowl Rehabilitation CIP #34 Project Category:Parks Ward: 2 Project Description: Estimated Total Project Cost:$1,200,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Design Construction Estimated Project Completion: Seating, lighting, sound, and building upgrades (hall, interior lighting, bathrooms, changing/makeup rooms). This project will address deferred maintenance at this outdoor center, and provide a safer environment for community attendance at events. Project Approval Date: 6/30/2021 Budget: $1,200,000 Current Project Status and Timeline: Budget Status:Within Budget 12/2024 Speicher Park – East Side Skate Park CIP #36 Nicholson Park Improvements CIP #37 Seccombe Lake Park Improvements CIP #38 Project Category:Parks Ward: 1 Project Description: Estimated Total Project Cost:$9,998,970 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Construction Estimated Project Completion: Upgrade the site furnishings, parking lot rehabilitation, new landscaping, lake improvements, ADA upgrades and irrigation improvements. Project Approval Date: 6/30/2022 Budget: $9,998,970 Current Project Status and Timeline: Budget Status:Within Budget 11/2024 28 Lytle Creek Park Improvements CIP #39 Project Category:Parks Ward: 3 Project Description: Estimated Total Project Cost:$600,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Estimated Project Completion: Project Site Map Installation of futsal fields and other improvements. Project Approval Date: Prior to 6/30/2018 Budget: $600,000 Current Project Status and Timeline: Budget Status:Within Budget 05/2024 Speicher Park – Ball Field Improvements CIP #40 Project Category:Parks Ward: 2 Project Description: Estimated Total Project Cost:$1,950,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Design Construction Estimated Project Completion: Budget Status:Within Budget 02/2025 Install new artificial turf system with drainage at Huchabaa Field, and replace infill material on other baseball fields at Speicher Park, lighting improvements, electrical repairs and all related improvements. Project Approval Date: 6/30/2021 Budget: $1,950,000 Current Project Status and Timeline: Sal Saavedra Park – Field Improvements CIP #41 Parks Master Plan Study CIP #46 32 CIP #48 Newmark Ball Field(s) Lighting System Installation Project Category:Parks Ward: 4 Project Description: Estimated Total Project Cost:$1,675,464 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Budget Status:Within Budget 05/2024 Project Site Map New lighting (box, contactors, breakers, conduit, wire, poles, fixtures, security lights) for T- Ball and Softball Fields (2ea.) The field currently has obsolete lighting that is not longer serviceable as parts are not available. This is a highly used field and replacement of these lights will significantly improve safety at the park. Project Approval Date: 6/30/2021 Budget: $1,705,052 Current Project Status and Timeline: Estimated Project Completion: 33 CIP #49 Speicher Park Multipurpose Field New Lighting Installation Project Category:Parks Ward: 7 Project Description: Estimated Total Project Cost:$1,083,394 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Budget Status:Within Budget 05/2024 Project Site Map The City has only one lighted multipurpose field (football, soccer, field hockey, ultimate frisbee) used by a dozen resident youth sports groups The installation of a lighting system will improve safety and expand the use of fields to meet the growing needs of community sports play, especially soccer, for all ages. Project Approval Date: 6/30/2021 Budget: $1,099,135 Current Project Status and Timeline: Estimated Project Completion: 34 CIP #55 Meyers Creek Focused Drainage Study Project Category:Storm Drain Ward: 5 Project Description: Estimated Total Project Cost:$266,771 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Planning Estimated Project Completion: Provide focused drainage study of the Meyers Creek, identify drainage structure deficiencies and capital improvement requirements and costs. Project Approval Date: 6/30/2022 Budget: $266,771 Current Project Status and Timeline: Budget Status:Within Budget 06/2024 35 CIP #58 Sierra Way Storm Drain Improvements Project Category:Storm Drain Ward: 7 Project Description: Estimated Total Project Cost:$3,965,209 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Design Construction Estimated Project Completion: Installation of drainage system on Sierra Way between 31st Street and 40th Street. Project Approval Date: 6/30/2019 Budget: $3,965,209 Current Project Status and Timeline: Budget Status:Within Budget 01/2025 36 CIP #60 Mt. Vernon Storm Drain Project Category:Storm Drain Ward: 6 Project Description: Estimated Total Project Cost:$6,156,522 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Estimated Project Completion: Street and Storm Drain Improvement for Mt. Vernon Ave. from 16th Street to Cajon Blvd. Project Approval Date: 6/30/2019 Budget: $6,156,522 Current Project Status and Timeline: Budget Status:Within Budget 06/2024 37 CIP #61 Storm Drain Catch Basin Screen Installation Project Category:Storm Drain Ward: All Project Description: Estimated Total Project Cost:$376,020 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Planning / Design Construction Estimated Project Completion: Yearly project for 5 years. Install connector pipe screen at various storm drain catch basin locations per MS4 Permit requirements. Project Approval Date: 6/30/2021 Budget: $376,020 Current Project Status and Timeline: Budget Status:Within Budget 11/2024 38 CIP #65 Construct Median on Kendall Curve 39 CIP #75 Street Sweeping Signage Program Project Category:Streets Ward: All Project Description: Estimate Total Project Cost:$0 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Design Construction Estimated Project Completion: Project Site Map Signs to be installed to restrict parking during a 3 to 4 hour window for street sweeping. Project Approval Date: 6/30/2020 Budget: $2,000,000 Current Project Status and Timeline: Budget Status:Surplus 06/2025 40 CIP #77 Street Rehabilitation – 21 Locations Project Category:Streets Ward: All Project Description: Total Project Cost (Estimate):$10,897,950 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Construction Estimated Project Completion: Project Site Map Project Approval Date: Budget: Current Project Status and Timeline: Budget Status:Shortfall 09/2024 Grinding, overlay and concrete improvements at select segments of Alameda Ave; H Street; Oak Street; Sonora St; 36th Street; 6th Street; Guthrie St; Oak St; 16th St; Business Center Dr; 35th St; Garfield St; Tamarisk Ave; 18th St; 2nd St; 13th St; Vanderbilt Way; 43rd Ave; Ohio St; Dallas Ave; 33rd St 6/30/2021 $6,080,695 Street Rehabilitation – 3 Locations CIP #82 Project Category:Streets Ward: 1; 4; 3 Project Description: Estimated Total Project Cost:$2,091,962 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Estimated Project Completion: Grinding, overlay and concrete improvements at 10th St between F St and G St; 49th St between Sepulveda Ave to end San Bernardino; and Rialto Avenue between Mt. Vernon to Bridge Project Approval Date: 6/30/2021 Budget: $2,091,962 Current Project Status and Timeline: Budgt Status:Within Budget 04/2024 Alley Rehabilitation – Clean California Grant CIP #86 Project Category:Streets Ward: 1 Project Description: Estimated Total Project Cost:$722,722 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Estimated Project Completion: Rehabilitate 4th street Alley including asphalt rehabilitation, installing trash bins, bike racks, new plants/trees; new artwork or paint on the walls. Project Approval Date: 6/30/2022 Budget: $722,722 Current Project Status and Timeline: Budget Status:Within Budget 06/2024 43 CIP #87 State HWY I-215 & University Parkway Interchange Improvements Project Category:Streets Ward: 5 & 6 Project Description: Estimated Total Project Cost:$2,962,055 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Budget Status:Shortfall 03/2025Estimated Project Completion: Project Site Map Construct a new Diamond Diversion interchange System. This new interchange will reduce congestion at this high volume ramp system. Project Approval Date: 6/30/2021 Budget: $2,002,055 Current Project Status and Timeline: 44 CIP #88 Citywide Pavement Rehabilitation Project Category:Streets Ward: 2, 4, 5 & 7 Project Description: Estimated Total Project Cost:$1,687,641 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Project Completion: Project Site Map This is a citywide initiative to improve the overall condition of streets. The scope of work includes crack filling and slurry sealing at various locations. Project Approval Date: 9/21/2022 Budget: $2,040,842 Current Project Status and Timeline: Budget Status:Surplus 08/2023 45 CIP #90 City of Highland Joint Projects: Pacific Ave Pavement Rehabilitation 46 CIP #91 City of Highland Joint Projects: CA-210 & Victoria Interchange Project Category:Streets Ward: 2 & 4 Project Description: Estimated Total Project Cost:$0 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Planning Design Design Construction Budget Status:Within Budget 01/2029Estimated Project Completion: Project Site Map Planning stages for Contruction of On/Off Ramps on the CA-210 Freeway at Victoria Ave. Project is funded by the Tribe and City of Highland. Project Approval Date: 6/30/2021 Budget: $0 Current Project Status and Timeline: N Victoria Ave Pepper Ave Rehabilitation CIP #92 Project Category:Streets Ward: 3 & 6 Project Description: Estimated Total Project Cost:$8,515,506 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Estimated Project Completion: Asphalt rehabilitation and concrete improvements from Baseline Road to Mill street. Project Approval Date: 7/20/2022 Budget: $8,515,506 Current Project Status and Timeline: Budget Status:Within Budget 01/2024 48 CIP #94 Sierra Way from 9th St. to 30th St. Project Category:Streets Ward: 1, 2 & 7 Project Description: Estimated Total Project Cost:$2,322,287 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Project Completion: Street pavement grinding, overlay and concrete work improvements. Project Approval Date: 5/4/2022 Budget: $2,493,946 Current Project Status and Timeline: Budget Status:Surplus 08/2023 49 CIP #95 SB County Joint St. Rehabilitation Projects: Lynwood Dr. & Other Roads Project Category:Streets Ward: 4 & 7 Project Description: Estimated Total Project Cost:$1,863,750 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Construction Estimated Project Completion: Project Site Map Surface Seal Treatment Project Approval Date: 10/26/2021 Budget: $1,371,000 Current Project Status and Timeline: Budget Status:Shortfall 9/2024 50 CIP #96 SB County Joint Street Rehabilitation Projects: Citrus St. & Other Roads Project Category:Streets Ward: 1, 2, 4, 7 Project Description: Estimated Total Project Cost:$686,250 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Design Construction Budget Status:Shortfall 06/2025Estimated Project Completion: Project Site Map Resurface Road Project Approval Date: 6/30/2021 Budget: $0 Current Project Status and Timeline: 51 CIP #97 SB County Joint Street Rehabilitation Projects: Blake St. & Other Roads Project Category:Streets Ward: 6 Project Description: Estimated Total Project Cost:$47,500 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Design Construction Estimated Project Completion: Project Site Map Resurface Road and ADA curb ramp update Project Approval Date: 10/26/2021 Budget: $0 Current Project Status and Timeline: Budget Status:Shortfall 06/2025 52 CIP #98 SB County Joint Street Rehabilitation Projects: Third St. & Other Roads Project Category:Streets Ward: 1 & 2 Project Description: Estimated Total Project Cost:$1,601,250 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Design Construction Estimated Project Completion: Project Site Map Resurface Road and ADA curb Ramp update. Project Approval Date: 10/26/2021 Budget: $0 Current Project Status and Timeline: Budget Status:Shortfall 06/2025 53 CIP #99 SB County Joint Street Rehabilitation Projects: North San Bernardino Area Curb Ramps Project Category:Streets Ward: 2 & 7 Project Description: Estimated Total Project Cost:$37,500 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Design Construction Estimated Project Completion: Project Site Map ADA Curb Ramp Update. Project Approval Date: 10/26/2021 Budget: $0 Current Project Status and Timeline: Budget Status:Shortfall 06/2025 54 CIP #100 SB County Joint Street Rehabilitation Projects: Arden Ave & Other Roads Project Category:Streets Ward: 1, 2, 4, 7 Project Description: Estimated Total Project Cost:$2,396,250 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Design Construction Budget Status:Shortfall 06/2025Estimated Project Completion: Project Site Map Pavement Reconstruction, Mill and Overlay, Americans with Disabilities Act (ADA) curb ramp update, and sewer manhole adjustment. Project Approval Date: 6/30/2021 Budget: $0 Current Project Status and Timeline: 55CIP #103 State Highway CA-210 at Waterman Avenue Project Category:Streets Ward: 7 Project Description: Estimated Total Project Cost:$1,398,270 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Construction Budget Status:Shortfall 09/2024Estimated Project Completion: The purpose of the project is to alleviate existing congestion and queues at the interchange by increasing capacity and the additions of turning lanes. Project Approval Date: 6/30/2021 Budget: $400,000 Current Project Status and Timeline: Pavement Management Program CIP #104 Project Category:Streets Ward: All Project Description: Estimated Total Project Cost:$996,173 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Planning Estimated Project Completion: The project includes preparation of Citywide pavement management program. Project Approval Date: 6/30/2022 Budget: $1,000,000 Current Project Status and Timeline: Budget Status:Within Budget 09/2024 Mount Vernon Ave Bridge Replacement CIP #108 Project Category:Streets Ward: 1 Project Description: Estimated Total Project Cost:$3,802,188 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Design / Construction Construction Construction Budget Status:Shortfall 08/2025Estimated Project Completion: This is a joint project led by SBCTA that includes replacement of existing bridge on Mt. Vernon Avenue, and related improvements. Project Approval Date: 6/30/2020 Budget: $3,579,531 Current Project Status and Timeline: State St. Extension Phase 1 – 16 St. to Baseline Rd. CIP #110 Project Category:Streets Ward: 6 Project Description: Estimated Total Project Cost:$8,472,943 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Budget Status:Within Budget 12/2023Estimated Project Completion: Phase 1 improvements includes construction of new asphalt roadway, concrete sidewalk, curb and gutter, curb ramps, concrete raised medians, traffic signal improvements, and striping. Project Approval Date: 6/30/2021 Budget: $8,480,960 Current Project Status and Timeline: Cross Street Bridge CIP #112 60 SB County Joint Project – 4th Avenue & Mountain Dr. CIP #113 Project Category:Streets Ward: 5 Project Description: Estimated Total Project Cost:$756,250 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Design Construction Estimated Project Completion: Project Site Map Culvert construction and roadway reconstruction, pavement reconstruction, ADA curb curb improvements. Project Approval Date: Not Approved BY CC yet. Budget: $0 Current Project Status and Timeline: Budget Status:Shortfall 09/2025 61 SB County Joint Project – 5th St & Pedley Road CIP #114 Project Category:Streets Ward: 1 Project Description: Estimated Total Project Cost:$355,500 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Estimated Project Completion: Project Site Map Hawk system installation, ADA ramps upgrade/construction, intersection widening, Installation of High Intensity Activated Crosswalk Beacon for a school crosswalk including intersection street civil improvements. Project Approval Date: Not Approved BY CC yet. Budget: -$ Current Project Status and Timeline: Budget Status:Shortfall 10/2023 62 SB County Joint Project – 40th St. & Other Roads CIP #115 Project Category:Streets Ward: 4 Project Description: Estimated Total Project Cost:$1,143,750 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Construction Estimated Project Completion: Project Site Map Mill and overlay, overlay, and ADA ramp updates, roadway Resurfacing of 40th streets and other roads, which will include adjustment of 25 manholes covers, and intersection pavment improvements with ADA compliant Ramps. Project Approval Date: 9/29/2020 Budget: -$ Current Project Status and Timeline: Budget Status:Shortfall 06/2024 Streetlight Knocked -Down Poles Replacement CIP #116 Project Category:Traffic Controls Ward: All Project Description: Estimated Total Project Cost:$38,709 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Estimated Project Completion: As street lights get knocked down they will be removed and replaced. This happens on a per incident basis. Project Approval Date: Prior to 6/30/2018 Budget: $54,889 Current Project Status and Timeline: Budget Status:Within Budget 11/2023 64 Solar Powered Street Lights on E St between Baseline St. & Highland Ave. CIP #117 Project Category:Traffic Controls Ward: 2 Project Description: Estimated Total Project Cost:$285,722 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Estimated Project Completion: Project Site Map The restoration of lighting services on this segment is needed to improve pedestrian safety and motorist visibility. The electrical system supporting the lighting system requires full reconstruction. This project will evaluate the use of solar lighting as an alternative to traditional wired street lights. Project Approval Date: Prior to 6/30/2018 Budget: $285,722 08/2023 Current Project Status and Timeline: Budget Status:Within Budget Genevieve Circuit Lighting CIP #118 Project Category: Traffic Controls Ward: 7 Project Description: Estimated Total Project Cost:$1,040,258 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Construction Construction Budget Status:Shortfall 09/2024Estimated Project Completion: Marshall Blvd on the south, 34th St. on the north, Mountain View Ave. on the West and Sierra Way on the east. Major electrical circuit repairs are required to restore lighting in this area. The project would repair these circuits and upgrade the lighting fixtures to LED. Project Approval Date: 6/30/2021 Budget: $381,825 Current Project Status and Timeline: Ralston Circuit Lighting CIP #119 Project Category: Traffic Controls Ward: 7 Project Description: Estimated Total Project Cost:$1,243,294 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Construction Construction Budget Status:Shortfall 09/2024Estimated Project Completion: Waterman Ave on the east, Sierra Way on the west, Palmyra on the south, Sonora Dr. on the north. Major electrical circuit repairs are required to restore lighting in this area. The project would repair these circuits and upgrade the lighting fixtures to LED. Project Approval Date: 6/30/2021 Budget: $382,167 Current Project Status and Timeline: 67 CIP #120 Citywide Street Lighting Upgrades Project Category:Traffic Controls Ward: All Project Description: Estimated Total Project Cost:$901,282 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Budget Status:Within Budget 02/2024 Project Site Map Retrofitting all city-owned streetlights to LED fixtures. Better quality, more energy efficient lighting and better safety for pedestrians and motorists. Phase 2 Project Approval Date: 6/30/2021 Budget: $1,000,000 Current Project Status and Timeline: Estimated Project Completion: 68 CIP #121 Upgrade Various Signal Hardware on 224 Signalized Intersections on Various Arterials Project Category:Traffic Controls Ward: All Project Description: Estimated Total Project Cost:$4,069,479 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Construction Budget Status:Within Budget 09/2023Estimated Project Completion: Project Site Map Upgrade various signal hardware components, including traffic signal heads, push buttons, and pedestrian signal heads on two hundred twenty-four (224) signalized intersections on various arterial in the City of San Bernardino. Project Approval Date: 6/30/2020 Budget: $6,436,296 Current Project Status and Timeline: 69 CIP #122 Implement Advanced Dilemma Zone Detection at 49 Signalized Intersections Project Category:Traffic Controls Ward: 1,2,3,6,7 Project Description: Estimated Total Project Cost:$3,978,574 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Construction Budget Status:Within Budget 09/2024Estimated Project Completion: Project Site Map Implement advance dilemma zone detection at 49 signalized intersections within three roadway corridors. Mt. Vernon Ave. from Highland Ave. to Johnston St., Baseline St. from Del Rosa Ave. to California St. and Highland Ave. from Medical Center Dr. to Victoria Ave. Project Approval Date: 6/30/2020 Budget: $7,022,566 Current Project Status and Timeline: 70 CIP #126 Traffic Management Center (TMC) – (Annual) Project Category:Traffic Controls Ward: All Project Description: Estimated Total Project Cost:$37,826 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Planning Construction Project Completion: Project Site Map Traffic Engineering maintains and improves the traffic management center. Improvements to this software and hardware will improve driving conditions throughout the city. Project Approval Date: 6/30/2020 Budget: $44,420 Current Project Status and Timeline: Budget Status:Surplus Ongoing 71 CIP #127 9th St. & Medical Center Traffic Signal Upgrade Project Category:Traffic Controls Ward: 6 Project Description: Total Project Cost:$428,448 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Budget Status:Within Budget 06/2023Project Completion: Project Site Map This project will upgrade the existing traffic signal at the intersection of 9th St and Medical Center Drive. Project Approval Date: 6/30/2020 Budget: $428,448 Current Project Status and Timeline: 72 CIP #128 Del Rosa Signal Upgrade Project Category:Traffic Controls Ward: 2 & 7 Project Description: Total Project Cost:$376,290 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Construction Budget Status:Within Budget 06/2023Project Completion: Project Site Map This project will upgrade the existing traffic signal at the intersection of Del Rosa Ave with Date St/Date Pl. Project Approval Date: 6/30/2020 Budget: $376,290 Current Project Status and Timeline: 73 CIP #138 Mt. Vernon Ave & Rialto Ave Traffic Signal Upgrade Project Category:Traffic Controls Ward: 1 & 3 Project Description: Estimated Total Project Cost:$20,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Budget Status:Within Budget 12/2023Estimated Project Completion: This signal equipment is at its end of useful life and is experiencing failures. This upgrade will include the poles and cameras. (Selected based on KOA assessment) Project Approval Date: Prior to 6/30/2018 Budget: $60,000 Current Project Status and Timeline: 74 CIP #139 Mt. Vernon Ave & Walnut Ave Traffic Signal Upgrade Project Category:Traffic Controls Ward: 3 Project Description: Estimated Total Project Cost:$20,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Budget Status:Within Budget 12/2023Estimated Project Completion: This signal equipment is at its end of useful life and is experiencing failures. This upgrade will include the poles and cameras. Project Approval Date: Prior to 6/30/2018 Budget: $35,000 Current Project Status and Timeline: 75 CIP #141 Rancho Rd. & Rialto Ave. Traffic Signal Upgrade Project Category:Traffic Controls Ward: 3 Project Description: Estimated Total Project Cost:$20,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Estimated Project Completion: Budget Status:Within Budget 12/2023 This signal equipment is at its end of useful life and is experiencing failures. This upgrade will include the poles and cameras. (Selected based on KOA assessment) Project Approval Date: Prior to 6/30/2018 Budget: $25,000 Current Project Status and Timeline: 76 CIP #142 Waterman / 21st Traffic Upgrade Project Category:Traffic Controls Ward: 2 Project Description: Estimated Total Project Cost:$20,000 FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Design Estimated Project Completion: Budget Status:Within Budget 12/2023 This signal equipment is at its end of useful life and is experiencing failures. This upgrade will include the poles and cameras. Project Approval Date: Prior to 6/30/2018 Budget: $25,000 Current Project Status and Timeline: 77 Project Category Project Title Project Category Project Title Building Emergency BU Generator for Compressed Natural Gas Station Parks Seccombe Park: Fencing Project Building Paul Villasenor Library Improvements Parks Blair Park: Fitness Court, 3 fields Building Anne Shirrells Park & Community Center Streets Street Rehabilitation- 7 Locations Program #8886 Part 1 Parks Wildwood Park Parking Lot Improvements Streets Street Rehabilitation- Congress Street from Mt. Vernon Avenue to K Street Parks Perris Hill YMCA Parking Lot Improvements Streets Street Rehabilitation- Virginia St from E St to F St and From G St to H St Parks Playground Equipment Replacement Streets Street Rehabilitation- Hillside and Fairfax Parks Jerry Lewis Swim Center Improvements (Swimming Pool & Shade Structure) Closed-Out Projects Closed -Out Projects Project Category Project Title Project Category Project Title Project Category Project Title Streets Street Rehabilitation- Niles from San Gabriel to Crestview Streets Street Rehabilitation- 9 Locations Streets 2nd Street Bridge Replacement Streets Street Rehabilitation- Trenton from Crestview to Valencia, Valencia from Trenton to Niles Paving Streets State HWY I -10 CO-OP at Waterman Interchange Improvement Traffic Controls Mill and K Street Traffic Signal Upgrade Streets Street Rehabilitation- Cedar Street from Highland to 29th Street Streets ATP Cycle 2 Safe Route to School Traffic Controls Mill Street and Arrowhead Traffic Signal Upgrade Streets Street Rehabilitation- Arden Street (by soccer field) Streets City Wide Bus Stop Improvements Traffic Controls Traffic Signal Battery Backup Systems (Annual) Streets Street Rehabilitation- Country Club Lane from Waterman to Fremotia Drive Streets City of Redlands Co-Op Project Traffic Controls Highland and Patton Traffic Signal Upgrade Streets Street Rehabilitation- Arden Street from Highland Avenue to Highland Creek Streets Barton Road Rehabilitation Project Traffic Controls Highland/SB Bi -City Bikeway/Walk Streets Street Rehabilitation- 7 Locations Streets Kendall Dr. Slope Stabilization H St Traffic Controls Local Roadway Safety Plan Not-Activated Projects Project Category Project Title Project Category Project Title Building Delmann Heights Community Center Upgrade Parks Ball Field Accessory Building Upgrade Building Police Building Management System Parks Hernandez Community Center: Security Fencing Building Feldheym Library Improvement Parks Citywide Irrigation System Upgrade Building Inland Empire 66ers / San Manuel Stadium Parks Park Restrooms Program Building Train Depot Parks Perris Hills Senior Center Renovation Building SCE Charge Reddy Program at City Yard, Police & City Hall Parks Norton Gym: Facility Upgrades; Public Service Academy Building City Hall Rehabilitation Project Parks Bobby Vega Park Improvements Parks Ruben Campos Community Center Parks Norton Park Not-Activated Projects Project Category Project Title Project Category Project Title Project Category Project Title Parks Jerry Lewis Swim Center Street H St. Widening from Kendall Dr. to 40th St.Traffic Controls Tippecanoe Ave Interconnect Parks Anne Shirrells Park Street Alabama Street Rehab Project Traffic Controls 9th Street Interconnect Parks Ball Field Lighting Assessment Street Arrowhead Farm Area Steet Rehab Traffic Controls 6th Street Interconnect Storm Drain Waterman / Baseline Culvert Street Street Rehabilitation : Belleview St., 27 th St., Temple St. Traffic Controls Hunts Lane & Redlands Blvd Traffic Storm Drain Storm Drain Upgrade Street 40th Street Widening from Electric Ave to Johnson St Others Waterman Landfill Vapor Extraction Storm Drain Conejo & 39th Storm Drain Traffic Controls Highland Ave Interconnect Others MWSC Soil Extraction Storm Drain Sierra Way Storm Drain Traffic Controls Baseline Interconnect Others Water Infrastructure Improvement Storm Drain Drainage Channel improvement at Cajon Blvd & Shenandoah Way Traffic Controls Waterman Ave Interconnect Capital Projects with Budget Shortfalls 81 Project Title Budget Total Project Cost Budget Shortfall Funding Source Cross Street Bridge $0.00 $1,000,000 (estimated)$1,000,000 Capital Contingency Reserve Fund University Parkway & I-215 Improvements*$2,040,000 $3,000,000 $960,000 Measure I * Staff intends to return to the City Council on 7/19/23 to amendment to Co-Op Agreement with SBCTA. Capital Projects with Budget Shortfalls 82 Project Title Budget Total Project Cost Budget Shortfall Budget Surplus Funding Source Genevieve Circuit Lighting $381,825 $1,422,083 $1,040,258 Measure S Ralston Circuit Lighting $382,167 $1,625,461 $1,243,294 Measure S Congress Street from Mt. Vernon Avenue to K Street; 14 locations $325,000 Measure S Arden Street (by soccer field)$325,000 Measure S Citywide Pavement Rehabilitation $1,350,000 Measure S Street Sweeping Signage Program $2,000,000 Measure S Total $2,283,552 $4,000,000 Measure S City Council approved 130 CIP Projects in the amount of $169.6M Plus 14 non-funded projects CIP Management Progression 83 Comparison with Other Cities 84 5 3 14 2 47 2 2 10 10 10 7 0 5 10 15 20 25 30 35 40 45 50 Huntington Beach Oxnard Fontana Moreno Valley San Bernardino Fremont Chula Vista Santa Clarita Irvine Santa Ana Average (excluding SB) Projects per Project Manager Nearly 7x the average Industry standard is 7 to 10 projects per project manager. Recommendations It is recommended that the Mayor and City Council of the City of San Bernardino, California: 1.Receive and file an update regarding the City of San Bernardino’s Capital Improvement Program; and 2.Resolution No. 2023 -XXX authorizing the Agency Director of Finance to amend the FY 2023/24 Capital Improvement Plan, recording supplemental appropriations in the amount of $1,000,000 from the Capital Contingency Reserve Fund for the Cross Street Bridge Project; and $1,040,258 from Measure S for the Genevieve Circuit Lighting Project; and $1,243,294 from Measure S for the Ralston Circuit Lighting Project. Questions? 86