HomeMy WebLinkAboutItem No. 22 - Award of a Construction Contract for City Yard Roof Replacement
Consent Calendar
City of San Bernardino
Request for Council Action
Date: June 17, 2020
To: Honorable Mayor and City Council Members
From: Teri Ledoux, City Manager
By:Kris Jensen, Director of Public Works
Subject: Award of a Construction Contract for the CityYards Roof
Replacement
Recommendation
It is recommended that the Mayor and City Council of the City of San Bernardino,
California, adopt Resolution No. 2020-122:
1. Amending the FY 2019/20 Capital Improvement Plan (CIP) to include City Yard
2. Approving a total project budget in the amount of $308,017 for the construction
contract in the amount of $279,517 and project contingencies in the amount of
$28,500; and
3. Approving the award of a Construction Contract with Bligh Roof Co. DBA Bligh
Pacific of Santa Fe Springs, California in the amount of $279,517; and
4. Authorizing the Director of Finance to amend the FY 2019/20 adopted budget to
transfer a total of $308,017 from Public Works Building Maintenance accounts
001-400-0037-5172 (Equipment Maintenance) and 001-400-0037-5502
(Professional Contractual services) to Capital Improvement Project Fund 001-
160-8774 in support of the Project; and
5. Authorizing the City Manager or designee to expend the contingency fund, if
necessary, to complete the project.
Background
The Public Works Department Fleet and Building Maintenance Division is responsible
for maintaining the City Yard located at 187 S. Pershing Avenue, San Bernardino. The
existing roof of the vehicle maintenance Shop at City Yard is about 30 years old and
has exceeded its useful life and is no longer serviceable. The facility roof has been
patched numerous times over the last few decades, and the facility has incurred water
damage due to this over the years. Additional roof leaks could further damage the
replaced.
Page 1
6743
Staff prepared plans and specifications for the roof replacement project. Theproposed
scope of work includes removing and disposing of the existing roof, installation of
adhered thermoplastic (PVC) feltback membrane roof system, installation of
polysocyanurate roof insulation, gypsum cover boards, PVC fascia, and other
components to comprise a water tight roof system as a base bid. Staff included
replacement of existing gutters and downspouts as an alternate bid item. Determination
of the lowest responsible bid was based on the total base bid. The alternate bid item
was not considered in determining the lowest responsible bidder.
This project is proposed to be funded with savings realized in FY 2019/20 Public Works
Building Maintenance Division operating budgets.
Discussion
City Yard Roof Replacement (Project No 13395) to provide roof repairs, was advertised
for public bidding on April 17, 2020 and April 24, 2020 in the San Bernardino County
Sun Newspaper, F. W. Dodge, Construction Bid Board, High Desert Plan Room, San
Diego Daily Transcript, Sub-Hub Online Plan Room, Reed Construction Data, Bid
Bernardino Area Chamber of Commerce.
Sealed bids were received and opened on May 14, 2020. The City received five bids as
follows:
BIDDER CITY BASE BID ALTERNATE TOTAL
BID BID
Bligh Roof Co. DBA Santa Fe $227,810 $51,707 $279,517
Bligh Pacific Springs
Best Contracting Gardena $285,850 $42,200 $328,050
Services, Inc.
San Marino Roof Co., Orange $304,981 $43,438 $348,419
Inc.
Danny Letner Inc. DBA Orange $349,200 $37,550 $386,750
Letner Roofing Co.
Courtney, Inc. Irvine $378,680 $46,840 $425,520
The City has reviewed the bid package and confirmed that Bligh Roof Co. DBA Bligh
Pacific of Santa Fe Springs, California, is the lowest responsible and responsive bidder,
with a base bid amount of $227,810 and a total bid amount of $279,517. Based on
available funding, staff is recommending award of the total bid amount of $279,517
(base bid plus alternate).
In addition to construction costs, staff anticipates the need for a construction
contingency to provide for any unforeseen work that is related to the project and
estimated staff costs required to support engineering inspections of the project. At this
Page 2
6743
time, the estimated full project cost is at $308,017 which includes the lowest responsive
construction bid, project contingencies, and engineering inspections. The breakdown of
the total project costs are as follows:
Cost Items Amount
Bid (Including Alternate Bid) $ 279,517
Construction Contingency $ 28,500
Estimated Total Project Cost $ 308,017
If awarded by the Mayor and City Council, construction work on the City Yard Roof
Replacement is anticipated to begin in August 2020 and be completed by October 2020.
2020-2025 Key Strategic Targets and Goals
This project aligns with Key Target No. 1e: Create an asset management plan as it will
address a long deferred maintenance item for a City owned facility and will help
preserve the facility asset for use continued use by the Public Works Department for
many years into the future.
Fiscal Impact
Funding in the total amount of $308,017 is available for this project through General
Fund savings realized in FY 2019/20 Public Works Building Maintenance Operating
Budgets in account 001-400-0037. Savings in an amount of $93,017 is available in
001-400-0037-5172 (Building Equipment Maintenance) and $215,000 in savings is
available through 001-400-0037-5502 (Professional Contractual Services). A budget
adjustment is required to transfer the total Project budget of $308,017 to City Yard
Replacement Project. No 001-160-8774 as shown in the table below.
From Account To Account Amount Cost Item
001-400-0037-5172 001-160-8774-5504 $ 93,017 Construction
Professional Services CIP Construction
001-16 0-8774-5504
001-400-0037-5502 $ 215,000 Construction
Equipment Maint. CIP Construction
TOTAL $ 308,017
The Building Maintenance Division operating budgets include budgets for emergency
maintenance of equipment such as elevators, fire sprinkler systems, and roll up doors.
During FY19/20 fewer than expected equipment maintenance expenditures were
incurred, resulting in a savings in this budget category. Additionally, the Division
budgets annually for Professional Contractual Services to assist with major construction
repair requests. Because staff was able to address the bulk of these types of repair
requests in-house, savings were realized in this budget category in FY2019/20, as well.
Page 3
6743
Conclusion
It is recommended that the Mayor and City Council of the City of San Bernardino,
California, adopt Resolution No. 2020-122:
1. Amending the FY 2019/20 Capital Improvement Plan (CIP) to include City Yard
2. Approving a total project budget in the amount of $308,017 for the construction
contract in the amount of $279,517 and project contingencies in the amount of
$28,500; and
3. Approving the award of a Construction Contract with Bligh Roof Co. DBA Bligh
Pacific of Santa Fe Springs, California in the amount of $279,517; and
4. Authorizing the Director of Finance to amend the FY 2019/20 adopted budget to
transfer a total of $308,017 from Public Works Building Maintenance accounts
001-400-0037-5172 (Equipment Maintenance) and 001-400-0037-5502
(Professional Contractual services) to Capital Improvement Project Fund 001-
160-8774 in support of the Project; and
5. Authorizing the City Manager or designee to expend the contingency fund, if
necessary, to complete the project.
Attachments
Attachment 1 Resolution No. 2020-122; Exhi
Attachment 2 Bid Tabulation for City Yard Roof Replacement
Attachment 3 Lowest Bid Form for City Yard Roof Replacement
Attachment 4 Location Map
Ward: Ћ
Synopsis of Previous Council Actions: bƚƓĻ
Page 4
RESOLUTION NO. 2020-122
RESOLUTION OF THE MAYOR AND CITY COUNCIL OF
THE CITY OF SAN BERNARDINO, CALIFORNIA,
AMENDING THE FY 2019/20 CAPITAL IMPROVEMENT
PLAN (CIP) TO INCLUDE CITY YARD ROOF
REPLACEMENT PROJECT 13395
APPROVING A TOTAL PROJECT BUDGET IN THE
AMOUNT OF $308,017 FOR THE CONSTRUCTION
CONTRACT IN THE AMOUNT OF $279,517 AND
PROJECT CONTINGENCIES IN THE AMOUNT OF
$28,500; AND APPROVING THE AWARD OF A
CONSTRUCTION CONTRACT WITH BLIGH ROOF CO.
DBA BLIGH PACIFIC OF SANTA FE SPRINGS,
CALIFORNIA IN THE AMOUNT OF $279,517; AND
AUTHORIZING THE DIRECTOR OF FINANCE TO
AMEND THE FY 2019/20 ADOPTED BUDGET TO
TRANSFER A TOTAL OF $308,017 FROM PUBLIC
WORKS BUILDING MAINTENANCE ACCOUNTS 001-400-
0037-5172 (EQUIPMENT MAINTENANCE) AND 001-400-
0037-5502 (PROFESSIONAL CONTRACTUAL SERVICES)
TO CAPITAL IMPROVEMENT PROJECT FUND 001-160-
8774 IN SUPPORT OF THE PROJECT; AND
AUTHORIZING THE CITY MANAGER OR DESIGNEE TO
EXPEND THE CONTINGENCY FUND, IF NECESSARY,
TO COMPLETE THE PROJECT
WHEREAS, the City of San Bernardino Public Works Department is responsible to
maintain facilities at the City Yard located at 187 S. Pershing Avenue, San Bernardino; and
WHEREAS, staff has administered a competitive bid process to secure a construction
contract to perform the City Yard Roof Replacemen; and
WHEREAS, the City received five bids on May 14, 2020, and Bligh Roof Co. DBA
Bligh Pacific of Santa Fe Springs, California, has been determined to be the lowest responsive,
responsible bidder; and
WHEREAS, the total Project budget is estimated at $308,017 including construction
costs and contingencies; and
WHEREAS, the City now wishes to enter into a construction agreement with Bligh Roof
Co. DBA Bligh Pacific to perform the Project work; and
WHEREAS, the funding for the project is available through savings realized in
previously approved FY 2019/20 Building Maintenance Operating Budgets.
Resolution No. 2020-122
BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF THE CITY OF
SAN BERNARDINO AS FOLLOWS:
SECTION 1. The above recitals are true and correct and are incorporated herein by this
reference.
SECTION 2. The Director of Finance is authorized to amend the FY 2019/20 CIP to
include the City Yard roof Replacement Project 13395 in a total project amount of $308,017.
SECTION 3. The City Manager is authorized and directed to execute a construction
agreement followiAttorney with Bligh Roof
Co. DBA Bligh Pacific in the amount of $279,517 with a contingency in the amount of $28,500
for the City Yard Roof Replacement, attached hereto and incorporated as Exhibit A.
SECTION 4. The City Manager or designee is hereby authorized to execute all
documents in support of the City Yard Roof Replacement Project 13395 on behalf of the City.
SECTION 5. The Director of Finance is authorized to amend the FY 2019/20 adopted
budget to transfer funds from General Fund Building Maintenance Account No. 001-400-0037-
5172 ($93,017) and 001-400-0037-5502 ($215,000) to CIP Account No. 001-160-8774.
SECTION 6. The City Council finds this Resolution is not subject to the California
Environmental Quality Act (CEQA) in that the activity is covered by the general rule that CEQA
applies only to projects which have the potential for causing a significant effect on the
environment. Where it can be seen with certainty, as in this case, that there is no possibility that
the activity in question may have a significant effect on the environment, the activity is not
subject to CEQA.
SECTION 7. Severability. If any provision of this Resolution or the application thereof
to any person or circumstance is held invalid, such invalidity shall not affect other provisions or
applications, and to this end the provisions of this Resolution are declared to be severable.
SECTION 8. Effective Date. This Resolution shall become effective immediately.
APPROVED and ADOPTED by the City Council and signed by the Mayor and attested
by the Acting City Clerk this ___ day of __________, 2020.
John Valdivia, Mayor
City of San Bernardino
Attest:
__________________________________
Genoveva Rocha, CMC, Acting City Clerk
Approved as to form:
_________________________________
Sonia Carvalho, City Attorney
Resolution No. 2020-122
CERTIFICATION
STATE OF CALIFORNIA )
COUNTY OF SAN BERNARDINO) ss
CITY OF SAN BERNARDINO )
I, Genoveva Rocha, CMC, Acting City Clerk, hereby certify that the attached is a true copy of
Resolution No. _____, adopted at a regular meeting held at the ___ day of _______, 2020 by the
following vote:
Council Members: AYES NAYS ABSTAIN ABSENT
SANCHEZ _____ _____ _______ _______
IBARRA _____ _____ _______ _______
FIGUEROA _____ _____ _______ _______
SHORETT _____ _____ _______ _______
NICKEL _____ _____ _______ _______
RICHARD _____ _____ _______ _______
MULVIHILL _____ _____ _______ _______
WITNESS my hand and official seal of the City of San Bernardino this ___ day of
____________ 2020.
______________________________
Genoveva Rocha, CMC, Acting City Clerk
A G R E E M E N T
CITY OF SAN BERNARDINO
THIS AGREEMENT is made and concluded this _____ day of _______________, 20___, between the
City of San Bernardino (owner and hereinafter "CITY"), and Bligh Roof Co. DBA Bligh Pacific
(hereinafter "CONTRACTOR").
1. For and in consideration of the payments and agreements hereinafter mentioned, to be made and
performed by the CITY, and under the conditions expressed in the bond as deposited with the CITY, receipt of
which is hereby acknowledged, the CONTRACTOR agrees with the CITY, at the CONTRACTOR's own proper
cost and expense in the Special Provisions to be furnished by the CITY, to furnish all materials, tools and
equipment and perform all the work necessary to complete in good workmanlike and substantial manner the
CITY YARD ROOF REPLACEMENT
Project No. 13395
in strict conformity with Plans and Special Provisions No. 13395 , and also in accordance with Standard
Specifications for Public Works/Construction, latest edition in effect on the first
on file in the Office of the City Engineer, Public Works Department, City
of San Bernardino, which said Plans and Special Provisions and Standard Specifications are hereby especially
referred to and by such reference made a part hereof.
2. The CONTRACTOR agrees to receive and accept the prices as set forth in the Bid Schedule as
full compensation for furnishing all materials and doing all the work contemplated and embraced in this
agreement; also for all loss or damage arising out of the nature of the work aforesaid or from any unforeseen
difficulties or obstructions which may arise or be encountered in the prosecution of the work and for all risks of
every description connected with the work; also for all expenses incurred by or in consequence of the suspension
or discontinuance of work, and for well and faithfully completing the work and the whole thereof, in the manner
and according to the Plans and Special Provisions, and requirements of the Engineer under them.
3. The CONTRACTOR herein covenants by and for himself or herself, his or her heirs, executors,
administrators, and assigns, and all persons claiming under or through them, that there shall be no discrimination
against or segregation of, any person or group of persons on the basis of race, color, national origin, religion, sex,
marital status, or ancestry in the performance of this contract, nor shall the CONTRACTOR or any person
claiming under or through him or her, establish or permit any such practice or practices of discrimination or
segregation with reference to the selection of subcontractors, vendees, or employees in the performance of this
contract. Failure by the CONTRACTOR to carry out these requirements is a material breach of this contract,
which may result in the termination of this contract or such other remedy, as recipient deems appropriate.
A-1
AGREEMENT: CITY YARD ROOF REPLACEMENTProject No. 13395
4. CITY hereby promises and agrees with the said CONTRACTOR to employ, and does hereby
employ the said CONTRACTOR to provide the materials and to do the work according to the terms and
conditions herein contained and referred to, for the prices aforesaid, and hereby contracts to pay the same at the
time, in the manner, and upon the conditions above set forth; and the same parties for themselves, their heirs,
executors, administrators, and assigns, do hereby agree to the full performance of the covenants herein contained.
5. It is further expressly agreed by and between the parties hereto that should there be any conflict
between the terms of this instrument and the bid of said CONTRACTOR, then this instrument shall control and
nothing herein shall be considered as an acceptance of said terms of said bid conflicting herewith.
IN WITNESS WHEREOF, the parties of these presents have executed this contract in four (4)
counterparts, each of which shall be deemed an original in the year and day first above mentioned.
CONTRACTOR CITY OF SAN BERNARDINO
NAME OF FIRM:
Bligh Roof Co. DBA Bligh Pacific BY: ___________________________________
TERI LEDOUX
City Manager
BY: _______________________________
Robert Bligh
TITLE: President ATTEST:
MAILING ADDRESS:
11043 Forest Place _______________________________
Genoveva Rocha, CMC
_____Santa Fe Springs, Ca 90670_______ Acting City Clerk
PHONE NO.: (562) 944-9753______________ APPROVED AS TO FORM:
ATTEST:
_______________________________
SONIA CARVALHO, City Attorney
____________________________________
Secretary
NOTE: Secretary of the Owner should attest.
If Contractor is a corporation, Secretary should attest.
A-2
ATTACHMENT NO. 4
LOCATION MAP
187 S Pershing Avenue