HomeMy WebLinkAboutRES 2020-068 Execute Contract Change Order (CCo) No. 1 to Project No. 1332 with Noble E&C, Inc.RESOLUTION NO.2020-68
RESOLUTION OF THE MAYOR AND CITY COUNCIL OF THE CITY
OF SAN BERNARDINO, CALIFORNIA, AUTHORIZING THE CITY
MANAGER TO EXECUTE CONTRACT CHANGE ORDER (CCO) NO. 1
TO PROJECT NO. 1332 WITH NOBLE E&C, INC. IN THE AMOUNT OF
$27,998, FOR A FULL CONTRACT NOT -TO -EXCEED AMOUNT OF
$101,998; AND AUTHORIZING THE DIRECTOR OF FINANCE TO
RECORD A BUDGET ADJUSTMENT IN ANIMAL SHELTER
IMPROVEMENT FUND 124 AND UPDATE THE PROJECT PURCHASE
ORDER TO REFLECT THE FULL, APPROVED PROJECT COST
WHEREAS, staff previously identified repairs needed at the Animal Shelter that address
the most immediate health and safety issues to include electrical panel design and upgrade, roof
replacement, and mold abatement and reconstruction; and
WHEREAS, on December 4, 2019, the Mayor and City Council awarded a Construction
Contract (Project No. 1332) to Noble E&C, Inc. in the amount of $74,000 with a contingency in
the amount of $8,000 to perform mold abatement and reconstruction portion of the repairs; and
WHEREAS, upon beginning mold abatement work, it was discovered that additional
materials must be removed and replaced in the facility, and temporary office and restrooms will
be required for staff displaced by the construction work performed; and
WHEREAS, Noble E&C has provided Contractor Change Order No. 1 in the amount of
$27,998 to include the provision of labor, equipment, and materials required to replace
insulation, repaint the interior of the entire facility and provide temporary office and restroom
facilities for staff displaced during the completion of mold abatement and reconstruction in the
office areas; and
WHEREAS, the change order amount exceeds the contingency amount previously
established for the project.
BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF THE CITY OF
SAN BERNARDINO AS FOLLOWS:
SECTION 1. The above recitals are true and correct and are incorporated herein by this
reference.
SECTION 2. The City Manager is hereby direct to execute Contract Change Order No. 1
to Project No. 1332 with Noble E&C, Inc., in the amount of $27,998 for a full contract not -to -
exceed amount of $101,998, and attached hereto as Exhibit A,
SECTION 3. The Director of Finance is hereby directed to record a budget adjustment
in the amount of $19,998 from Animal Shelter Improvement Fund 124 to support costs of
Resolution No. 2020-68
April 15, 2020
Pagel of 3
Contract Change Order No. 1 for Project 1332 in excess of the approved contingency for the
project, and update the contract purchase order to reflect the full, approved project costs.
SECTION 4. The City Council finds this Resolution is not subject to the California
Environmental Quality Act (CEQA) in that the activity is covered by the general rule that CEQA
applies only to projects which have the potential for causing a significant effect on the
environment. Where it can be seen with certainty, as in this case, that there is no possibility that
the activity in question may have a significant effect on the environment, the activity is not
subject to CEQA.
SECTION 5. Severability. If any provision of this Resolution or the application thereof
to any person or circumstance is held invalid, such invalidity shall not affect other provisions or
applications, and to this end the provisions of this Resolution are declared to be severable.
SECTION 6. Effective Date. This Resolution shall becom effective immediately.
APPROVED and ADOPTED by the kCity
igi .d by the Mayor and attested
by the Acting City Clerk this 15�t day of April
divia, Mayor
an Bernardino
Attest
Genoveva Rocha, CMC, Acting City Clerk
Approved as to form:
Sonia Carvalho, Ci Attorney
Resolution No. 2020-68
April 15, 2020
Page 2 of 3
CERTIFICATION
STATE OF CALIFORNIA)
COUNTY OF SAN BERNARDINO) ss
CITY OF SAN BERNARDINO )
I, Genoveva Rocha, CMC, Acting City Clerk, hereby certify that the attached is a true
copy of Resolution No. 2020-68, adopted at a regular meeting held on the 15t' day of April 2020
by the following vote:
Council Members: AYES NAYS ABSTAIN ABSENT
SANCHEZ X
IBARRA X
FIGUEROA X
SHORETT X
NICKEL x
RICHARD X
MULVIHILL X
WITNESS my hand and official seal of the City o3enoveva
ernardino this 16'' day )f April 2020.
Rocha, CMC, Acting City Clerk
Resolution No. 2020-68
April 15, 2020
Page 3 of 3
Change Order_ #001
Project Name
Animal Shelter Mold Remediation
Change Order No.
Contractor:
Noble E&C, Inc.
Date: 3/30/20
by:
:_::mparry ems
David Ylm
("MY—WASubmitted
Job Order Number:
—i- 6«
A. Description of Change
Provide all labor, materials, equipment and coordination required to modify and/or provide the Items or
systems listed below. Contracto,
accepts the amount paid under this Change Order as payment in full for Contractor and Its subcontractor with no increase
to the projo7
schedules except where specifically noted.
Duration required for this task: N/A
1 Insulation (11-30) & Comer Molding on the ceiling (Phase I & Phase 111)
- Material: $ 2,500 (Insulation & Comer Molding)
$
2,250 00
- Labor: 2 MD x 4 Days
$
3,584.00
2 Drywall Ceiling Painting (Phase I & Phase 111)
- Material : $ 1,500 based on 2,000 SF (Primer & 2 Coatings)
$
1,500.00
- Labor: 2 MD x 4 Days
$
3,594 00
3 Primer Painting at Phase 11 (Exposed wood joist and rafter)
Material : $ 1,000
$
11000 00
Labor: 2 MD x 2 Days
$
1,792.00
4 Wall Patching & Painting at Phase I & Phase III
Material : $ 2,000 (Phase I & III)
$
2,000.00
Labor: 2 MD x 5 Days
$
4,490 00
6 interior/ Exterior Door (12 Ea) Painting
- Material & Labor
$
2,000.00
7 Office & Bathroom Trailer
- Delivery, Set-up & Pick-up (1 Month)
$
2,156.00
Sub Total $ 24,346.00
O&P (15%) $ 3,651.90
Grand Total S 27,997.90
1. Review & Comment
Noble E&C Inc/Name & Title David Vim, PM
N�mq �yBs -
Comments
Architect's Approval
Comments
Project Owner's Approval
Comments
C. Change Order Certificate
Original Contract Amount
Previously Approved Change Amount
This Change Amount
Revised Total Contract Amount
(Name)
5 _
$ 27,997.90
$ 27,997.90