WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017
(Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor
in April 2017 to address the significant multi -modal transportation funding shortfalls statewide;
and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure
the residents of our City of San Bernardino are aware of the projects proposed for funding in our
community and which projects have been completed each fiscal year; and
WHEREAS, WHEREAS, the City must adopt by resolution a list of projects proposed to
receive fiscal year funding from the Road Maintenance and Rehabilitation Account WMRA),
created by SB 1, which must include a description and the location of each proposed project, a
proposed schedule for the project's completion, and the estimated useful life of the improvement;
and
WHEREAS, the City/County, will receive an estimated $3,700,000 in RMRA funding in
Fiscal Year 2019-20 from SB 1; and
WHEREAS, this is the third year in which the City is receiving SB 1 funding and will
enable the City to continue essential road maintenance and rehabilitation projects, safety
improvements, repairing and replacing aging bridges, and increasing access and mobility options
for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City of San Bernardino has undergone a robust public process to ensure
revenues are being used on the most high-priority and cost-effective projects that also meet the
communities priorities for transportation investment; and
WHEREAS, the 2016 California Statewide Local Streets and Roads Needs Assessment
found that the City of San Bernardino's streets and roads are in fair condition. This revenue will
help us increase the overall quality of our road system and, over the next decade, help us
improve the condition of our streets and roads; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate ten (10)
street pavement rehabilitation segments, add active transportation infrastructure throughout the
City this year and about ten (10) of similar projects into the future; and
WHEREAS, the 2018 California Statewide Local Streets and Roads Needs Assessment
found that the City streets and roads are in an "excellent/good/at-risk/poor" condition and this
Resolution No. 2019-63
revenue will help us increase the overall quality of our road system and over the next decade will
bring our streets and roads into a good condition; and
WHEREAS, the SB 1 project list and overall investment in our local streets and roads
infrastructure with a focus on basic maintenance and safety, investing in complete streets
infrastructure, and using cutting-edge technology, materials and practices, will have significant
positive co -benefits statewide.
BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF THE CITY OF
SAN BERNARDINO AS FOLLOWS:
SECTION 1. The above recitals are true and correct and are incorporated herein by this
reference.
SECTION 2. The following list of proposed projects will be funded in -part or solely
with fiscal year 2019-20 Road Maintenance and Rehabilitation Account revenues:
Crestview Avenue Rehabilitation from East Baseline Street to 20th Street to provide
pavement rehabilitation. Accessibility improvement will be installed or upgraded as part of the
project. This will increase estimated useful life of 20 years to the street. Project is anticipated to
start July 2019 and completed by June 2020.
Electric Avenue Rehabilitation from 48th Street to Cul -De -Sac & Bartlett Drive to provide
pavement rehabilitation. Accessibility improvement will be installed or upgraded as part of the
project. This will increase estimated useful life of 15 years to the street. Project is anticipated to
start July 2019 and completed by June 2020.
5' Street from E Street to F Street to provide pavement rehabilitation. Accessibility
improvement will be installed or upgraded as part of the project. This will increase estimated
useful life of 20 years to the street. Project is anticipated to start July 2019 and completed by
June 2020.
Victoria Ave. Rehabilitation from 800 FT. East of Tippecanoe Ave. to Richardson St. to
provide pavement rehabilitation. Accessibility improvement will be installed or upgraded as part
of the project. This will increase estimated useful life of 15 years to the street. Project is
anticipated to start July 2019 and completed by June 2020.
7th Street Rehabilitation from Waterman Ave to Sierra Way to provide pavement
rehabilitation. Accessibility improvement will be installed or upgraded as part of the project.
This will increase estimated useful life of 15 years to the street. Project is anticipated to start July
2019 and completed by June 2020.
Mt. Vernon Avenue Rehabilitation from 17TH Street to Reece Street to provide pavement
rehabilitation. Accessibility improvement will be installed or upgraded as part of the project.
This will increase estimated useful life of 15 years to the street. Project is anticipated to start July
2019 and completed by June 2020.
Resolution No. 2019-63
Commercenter Drive West from Hospitality Lane to the North Cul-de-Sec;from
Hospitality Lane to Business Center Drive; from East Airport Drive to Commercenter
Drive East to provide pavement rehabilitation. Accessibility improvement will be installed or
upgraded as part of the project. This will increase estimated useful life of 15 years to the street.
Project is anticipated to start July 2019 and completed by June 2020.
Highland Avenue from Valencia Avenue to Cedar Street to provide pavement rehabilitation.
Accessibility improvement will be installed or upgraded as part of the project. This will increase
estimated useful life of 15 years to the street. Project is anticipated to start July 2019 and
completed by June 2020.
Little Mountain Drive Rehabilitation from Valencia Avenue to Cedar Street to provide
pavement rehabilitation. Accessibility improvement will be installed or upgraded as part of the
project. This will increase estimated useful life of 15 years to the street. Project is anticipated to
start July 2019 and completed by June 2020.
Arden Avenue Rehabilitation From Pacific Street to Highland Creek to provide pavement
rehabilitation. Accessibility improvement will be installed or upgraded as part of the project.
This will increase estimated useful life of 15 years to the street. Project is anticipated to start July
2019 and completed by June 2020.
SECTION 3. That the City Council finds this Resolution is not subject to the California
Environmental Quality Act (CEQA) in that the activity is covered by the general rule that CEQA
applies only to projects which have the potential for causing a significant effect on the
environment. Where it can be seen with certainty, as in this case, that there is no possibility that
the activity in question may have a significant effect on the environment, the activity is not
subject to CEQA.
SECTION 4. Severability. If any provision of this Resolution or the application thereof
to any person or circumstance is held invalid, such invalidity shall not affect other provisions or
applications, and to this end the provisions of this Resolution are declared to be severable.
SECTION 5. Effective Date. This
APPROVED and ADOPTED by the City
by the City Clerk this 1st day of May 2019.
Attest:
Georgeann F f anna, MMC, City Clerk
become effective immediately.
" n 1 an .1 ed by the Mayor and attested
T� s
John Valdivia, Mayor
City of San Bernardino
Resolution No. 2019-63
Approved as to form:
��� -t.-
Gary
Z� Gary D. Saenz, City Attorney
Resolution No. 2019-63
CERTIFICATION
STATE OF CALIFORNIA)
COUNTY OF SAN BERNARDINO) ss
CITY OF SAN BERNARDINO)
I, Georgeann Hanna, MMC, City Clerk, hereby certify that the attached is a true copy of
Resolution No. 2019-63 adopted at a regular meeting held at the I" day of May 2019 by the
following vote:
Council Members: AYES NAYS ABSTAIN ABSENT
SANCHEZ X
IBARRA x
VACANT
SHORETT X
NICKEL X
RICHARD -)C
MULVIHILL
WITNESS my hand and official seal of the City of San Bernardino this I " day of May ? 019.
Georgeann Wanna, MMC, City Clerk