HomeMy WebLinkAbout2019-019Resolution No. 2019-19
RESOLUTION NO. 2019-19
RESOLUTION OF THE MAYOR AND CITY COUNCIL OF
THE CITY OF SAN BERNARDINO, CALIFORNIA,
APPROVING AMENDMENT NO.2 TO THE AGREEMENT
FOR SERVICES WITH TETRA TECH FOR DESIGN OF
THE 2' STREET BRIDGE REPLACEMENT AT WARM
CREEK (SS13-001)
WHEREAS, on June 16, 2014, an Agreement with Tetra Tech in the amount of
$470,790 for the design and environmental work for the 2nd Street Bridge replacement at Warm
Creek (SS13-001) was approved; and
WHEREAS, on December 5, 2016, a mitigated negative declaration under the California
Environmental Quality Act was adopted and on April 4, 2017 Caltrans approved a Categorical
Exclusion under the National Environment Policy Act; and
WHEREAS, on May 16, 2018, the Mayor and City Council adopted Resolution No.
2018-139 approving Amendment No. 1 to the Agreement for Services with Tetra Tech for design
of the 2nd Street Bridge replacement at Warm Creek (SS13-001);and
WHEREAS, consultant services are needed to completed work on the design of the 2nd
Street Bridge replacement at Warm Creek (SS13-001); and
WHEREAS, consultant has submitted a proposal dated December 20, 2018 to provide
the necessary services to complete project.
BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF THE CITY OF
SAN BERNARDINO AS FOLLOWS:
SECTION 1. The above recitals are true and correct and are incorporated herein by this
reference.
SECTION 2. The City Manager or designee is hereby authorized and directed to execute
Amendment No. 2 to the Agreement for Services with Tetra Tech for design of 2nd Street Bridge
replacement at Warm Creek, Federal Aid Project No. BRLS-5033(052), Capital Improvement
Project No. SS 13-001, Bridge No. 54C-0411, a copy of which is attached as Exhibit "A" and
incorporated herein.
SECTION 3. This Amendment shall not take effect until it is fully signed and executed
by the parties, and no party shall be obligated hereunder until the time of such full execution. No
oral contracts, amendments, modifications or waivers are intended or authorized and shall not be
implied from any act or course of conduct of any party.
SECTION 4. The authorization to execute this Amendment No. 2 is rescinded if the
parties to the Agreement fail to execute it and return it to the office of the City Clerk within
ninety (90) days of the passage of this Resolution.
Resolution No. 2019-19
SECTION 5. That the City Council finds a mitigated negative declaration under the
California Environmental Quality Act was adopted for this project on April 4, 2017 and Caltrans
approved a Categorical Exclusion under the National Environment Policy Act.
SECTION 6. Severability. If any provision of this Resolution or the application thereof
to any person or circumstance is held invalid, such invalidity shall not affect other provisions or
applications, and to this end the provisions of this Resolution are declared to be severable.
SECTION 7. Effective Date. This Resolution shall b ome effective immediately.
APPROVED and ADOPTED by theCity un ' nd igned by the Mayor and attested
by the City Clerk this 6 h day of February 2019.
John Valivia, Mayor
City of San Bernardino
Attest:
i
Georgeann Uanna, MMC, City Clerk
Approved as to form:
Gary D. Saenz, City Attorney
Resolution No. 2019-19
CERTIFICATION
STATE OF CALIFORNIA)
COUNTY OF SAN BERNARDINO) ss
CITY OF SAN BERNARDINO)
I, Georgeann Hanna, MMC, City Clerk, hereby certify that the attached is a true copy of
Resolution No. 2019-19 adopted at a regular meeting held at the 6a` day of February 2019 by the
following vote:
Council Members: AYES NAYS ABSTAIN ABSENT
SANCHEZ
VACANT
SHORETT x
NICKEL �(
RICHARD x
MULVIHILL X
WITNESS my hand and official seal of the City of San Bernardino this 6h day of February 2019.
Georgeai�janna,1 M,City Clerk
EXHIBIT "A"
AMENDMENT NO.2 TO THE AGREEMENT FOR SERVICES WITH TETRA
TECH FOR DESIGN OF THE 2ND STREET BRIDGE REPLACEMENT AT
WARM CREEK.
This AMENDMENT is made and entered into this 6th day of February 2019
by and between the CITY OF SAN BERNARDINO, California, a municipal
corporation, hereinafter referred to as the "City" and TETRA TECH, hereinafter referred
to as "Consultant."
WITNESSETH:
A. WHEREAS, on June 16, 2014 the Mayor and City Council adopted
Resolution No. 2014-234 awarding an Agreement to Tetra Tech for the design of bridge
replacement at 2nd Street and Warm Creek Federal Aid Project No. BRLS-5033(052),
Capital Improvement Project No. SS 13-001, Bridge No. 54C-0411 (Project); and
B. WHEREAS, on December 5, 2016 the Mayor and City Council approved
Resolution No. 2016-247 adopting a Mitigated Negative Declaration (MND), approving a
Mitigation Monitoring and Reporting Program(N&W) and authorizing the Director of
Community Development or Designee to file a Notice of Determination (NOD) with the
Clerk of the Board of Supervisors of San Bernardino County for the Second Street Bridge
Replacement Project, Bridge #54C-0411; and
C. WHEREAS, on May 16, 2018, the Mayor and City Council adopted
Resolution No. 2018-139 approving Amendment No. 1 to the Agreement for Services
with Tetra Tech for design of the 2nd Street Bridge replacement at Warm Creek (SS13-
001);and
D. WHEREAS, based on the Amendment No. 1, the expiration date of the
Agreement for Services was established as December 31, 2018; and
E. WHEREAS, the Project is continuing and the services of the Consultant
will be needed through December 31, 2020; and
F. WHEREAS, the Consultant has submitted a proposal by letter dated
December 20, 2018, attached hereto as Attachment A, concurring with extending the
expiration date of the Agreement to December 31, 2020 and requesting additional fees.
NOW THEREFORE, the parties hereto agree as follows:
1. Section 4.1 "Term" of said Agreement for Services is hereby amended to extend the
term of this Agreement to December 31, 2020, unless terminated sooner as provided
herein.
M!
Amendment No. 2 to Agreement for Services with Tetra Tech.
2. Section 2.6 "Compensation" of Agreement for Professional Services is hereby
amended as follows:
Original Contract Amount $470,790.00
Amendment No. 1 $0.00
Amendment No. 2 `97,239.00
Revised Contract Amount $568,029.00
3. All other terms and conditions of said Agreement for Services, as amended, � 3 p Elroved
by Resolution Nos. 2014-234, 2016-247 and 2018-139 shat I remain unchanged.
-2-
Amendment No. 2 to Agreement for Services with Tetra Tech.
AMENDMENT NO.2 TO THE AGREEMENT FOR SERVICES WITH TETRA
TECH FOR DESIGN OF THE 2ND STREET BRIDGE REPLACEMENT AT
WARM CREEK (SS13-001).
IN WITNESS WHEREOF, the parties hereto have executed this Amendment on the
date first shown above.
CITY OF S.Ai 13ERNARDINO TETRA TECH
By: By.
Andrea M. Miller, City Manager Signature
ATTEST:
-Georgeann Jdanna, M 1 City Clerk
Approved as to form:
Gary D. Saenz
City Attorney
N
-3-
Print Name/Title
TETRA T CAH ATTACHMENT "A"
December 20, 2018
Michael Grubbs, MS, PE
PwJedM=W
City of San Bernardino Public Wodm Department
201 N. E St., 2nd Floor
San Bernardino, CA 92401
Reference: Design Support Services During Construction for 2°d Street Bridge Replacement
Dear Mr. Grubbs:
Tetra Tech hereby submits Amendment Request No. l to continue providing design support services
for the 2°d Street Bridge Replacement Project. The additional work includes the following:
Task 1: Schedule Extension $4,060
Tetra Tech has been requested to provide professional services, including project management and
subconsultant coordination, well beyond the initial schedule. We estimate that the project is
approximately two years past the initial contract schedule. Periodically, our team has had to
continue providing services to assist the City to obtain approvals from various agencies and
stakeholders. This effort equates to approximately one hour of project management for an
additional six months.
Task 2: Additional Biological Services
$11,611
As part of the environmental permits required for the project, The Army Corps has requested a
biological memorandum. Tetra Tech subconsultant GPA has provided a scope and fee for the
biological memorandum and continued regulatory permitting services of the project, which is
attached to this proposal.
Task 3: Final PS&E Revisions
$6,641
The City has previously stated that there aro comments on the Final PS&E package submitted to
the City in August 2018. Once the comments are received, the Tetra Tech team will review and
respond to the comments in writing. Revisions to the plans, if necessary, will be made with a total
of 56 labor hours budgeted for this task.
Task 4: Design Support during Bid and Award
$5,240
During Bid and Award phase, the Tetra Tech team will provide support to the City to answer
Requests for Information (RFIs) from potential bidders. It is anticipated there will be five (5) RFIs
with a total of 15 labor hours.
Tetra Tech Inc.
350 South Grand Avenue, Suite 3310, los Angeles, CA 90071
Tel 213-279-3283 www.tetratechxom
Michael Grubbs
December 20, 2018
Page 2
Task 5; Design Support During Construction $69,697
Tetra Tech will provide engineering support during construction activities. Construction
management, construction contract administration, inspection, and testing will be performed by
others. Services will be provided to support the plans and specifications prepared by the Tetra Tech
team.
Project Management
The Tetra Tech team will provide a Design Support during Construction Technical Task Leader who
will coordinate with the Project Manager to insure he is up to date on all construction activities.
Monthly progress reports, including Expenditure Report, will be prepared for the duration of
construction. A total of 52 labor hours are budgeted for this task.
Attend Construction Meeting
Tetra Tech will attend a one -day pre -construction conference to be held with the successful
construction contractor, City personnel, and other relevant personnel. The Tetra Tech team,
comprising the Project Manager and Construction Observer will take notes and produce meeting
minutes, as appropriate, to be provided to the City for distribution. Weekly construction progress
meetings will be attended via teleconference.
Shop Drawing Submittal Review
Tetra Tech will review shop and work drawings of fabricated and manufactured equipment
forwarded by the City, for substantial conformity with the intent of the contract documents. Twenty
(20) calendar days are scheduled from receipt by the team to date of return of the reviewed submittal
copies. The level of effort required for this task depends on the number of submittals to be reviewed,
the quality of those submittals, and the number of resubmittals required.
The level of effort for this task is based on an assumption of 20 submittals and 10 resubmittals, with
an average level of effort of three hours per submittal for the initial submittal and one hour for the
resubmittals. The total allowance for reviewing submittals is 70 labor hours. Our team will target a
maximum of one week elapsed time to complete reviews, with the understanding that some reviews
may take longer depending on the circumstances.
Assist with Chani -,e Orders and Plan Clarifications
The team will assist the City with the preparation of change orders and plan clarifications. A total
of 15 labor hours for project management support and 21 engineering design hours are budgeted.
Assist with RFIs
Contractor -generated RFIs will be submitted to the City. The Tetra Tech team will review and
respond to RFIs submitted to it by the City. Although the time required to respond to a particular
request for clarification varies greatly, the estimated level of effort for this task assumes 20 RFIs at
3 hours each with 4 site visits at 6 hours each for a total of 84 labors hours. Our team will target a
maximum of two (2) business days elapsed time to answer RFPs, with the understanding that some
BFI's may take longer depending on the circumstances.
TETRA TECH
Michael Grubbs
December 20, 2018
Page 3
Contractor Site Meetines
The Tetra Tech team will meet with the construction field team and Contractor as requested by the
City. A total of six (6) meetings, each attended by the Construction Observer and one attended by
the Project Manager, are budgeted for a total of 42 labor hours, including travel time.
Prepare As -Built Drawinus
Following receipt by the Tetra Tech team of the City -approved marked set of drawings from the
Contractor affix construction is complete, the team will incorporate all changes noted on the
Contractor's marked set within 60 days following receipt. The budget is based on changes to 12
drawings at 1.5 hours per sheet for preparation of the As -Built Drawings, 18 labor hours plus review
of plans.
Participate in Final Acceptance Inspections
Following completion of construction and as part of the process of establishing and verifying
completion of the punch list, the Tetra Tech team, upon City request, will participate in two (2)
inspections of the completed or nearly completed site. The team will advise the City as to the
acceptability of the work To ensure that the hydraulic elements, roadway features, and drainage
structures are constructed per the plans and specifications, two Tetra Tech team members are
budgeted for a total of 32 labor hours including travel time and office time to summarize inspection
observations in memorandum form.
Subconsultant Design Support During Construction Services
Tetra Tech subconsultant CNS has provided a scope and flee for the Design Support During
Construction services and continued consultation support services of the project, which is attached
to this lor000sal.
The total additional compensation requested for this task order revision is $97,239.
Please let me know if you have any questions regarding the Fee Proposal.
Sincerely.
1
:t
Mr. MSU[lclo ArgeIIte, ltLA
Vice President
MA/kg
Attachment—Fee Proposal
GPA Proposal
CNS Proposal
TETRA TECH
f9 Price Proposal
2nd Street Bridge
Design Support for Environmental Studies, Bic>i/Aword, and Construction.
PMJArm
)u-mltaed to: Gty of San Bemardino Attn: MGM Grubbs)
Contract Type: Fixed Price
Project Pham / Tasim
Schedule
Fmm Thm Months ;
Total
Labor Hrs
F
4i
$35
Task 1 Schedule Extension
Project Management-Six Monde (1 hour per week)
26
26
ask 2 Additional Biological Services
Biolo" Services
-
Task 3 Final FS&E Revhions
Revisions to Final PS&E -
-
-
56
T 56
4
4 M
task 4 Design Support during Bid/Avrard - 6 Months
Project Management ( PM - 05 hr/wk, CM - 5 Fr/wk- A_ pprox. 52 wla)
AssistwM RFI (5 RFI's 0 3 his each)
41
-
26
15
Task 5 Design Support During Construction -12 Mont hs-
Project Management ( PM - 05 hr/wk, CM - S hr/wk- Approx. 52 wks)
Attend Codon Weddy Meetings via teleconference (52 Weeks @ 1 br/mtg)
- -
— 412
52
6s
-
Review Shop Drawing submittal Review (20 Submit @ 3 hrs/ea610 Re-submit @ 1hr/ea)
!Assist with Charge Orders (6 We*)
Ass[st with RR (20 RR's @ 3 hrs each, plus 4 site visits IF 6 hrs/a) _
Meet wkh the Contractor (6 Meetings @ 6 hrs each)
Prepare As-Built Drawings (12 Sheets @ 15 ha/sheet plus review, No Sheets)
70
36
— 84
42
31
Foal Ameptance Inspections (2 Inspections)
SubconwRant
32
-
Totals
53S
I_
Tetra Tedi - Confidential and Proprietary Peg
CONSULTING
2112E1
December 13, 2018
Joe Conroy, Project Manager
Tetra Tech
350 S. Grand Avenue, Suite 3310
Los Angeles, CA 90071
SUBJECT: BIOLOGICAL SERVICES FOR THE 2ND STREET BRIDGE REPLACEMENT PROJECT,
CITY OF SAN BERNARDINO
Dear Mr. Conroy:
GPA Consulting is pleased to submit this proposed scope of work to provide a biological
memorandum and continued regulatory permitting services for the above -reference project.
The scope of work and fee to complete the additional services has been provided as an
attachment to this letter. GPA is available to commence work on these tasks immediately, once
approved by the Tetra Tech and the City. If you have any questions, do not hesitate to contact
me at (310) 792-2690.
Sincerely,
Richard Galvin, Vice President
GPA Consulting
Attachment: 2nd Street Bridge Replacement Project Scope of Work and Budget
231 colifornio street, el segundo co 90245 t. 310.792.2690 {.310.792.2696
1
CONSULTING,
1
GPA Scope of Work
December 13, 2018
PROJECT UNDERSTANDING
The City of San Bernardino (City) proposes to replace the existing 2nd Street Bridge (Bridge #54G-0411)
over Warm Creek (Creek) between Arrowhead Avenue and Mt. View Avenue in the city of San
Bernardino (San Bernardino) (project). The 2nd Street Bridge is founded on timber piles that have been
driven into the earth, and extend approximately 10 feet above the natural invert of the Creek. The Creek
is a well-defined, unimproved, natural channel between the outlet of Town Creek Tunnel and the 21
Street Bridge. Downstream of the 2"d Street Bridge, the Creek is a rectangular concrete channel.
A Natural Environment Study and Jurisdictional Delineation were completed by GPA and signed by
Caltrans on May 16, 2016. A Clean Water Act (CWA) Section 401 Water Quality Certification application
and CWA Section 404 Pre -Construction Notification were submitted to the Regional Water Quality
Control Board (RWQCB) and United States Army Corps of Engineers (USACE), on October 4, 2018. The
California Fish and Game Code Section 1602 Streambed Alteration Notification is anticipated to be
submitted to the California Department of Fish and Wildlife (CDFW) by the end of December 2018.
SCOPE OF WORK
Task 1: Biological Memorandum
The Natural Environment Study was completed in 2016 and signed by Caltrans on May 16, 2016. In an
email dated November 15, 2017 the USAGE requested that a Biological Memorandum (Memorandum)
be prepared to provide current information regarding biological resources existing on-site, due to the
amount of time that has elapsed since the original study was prepared.
In order to complete the Memorandum, GPA will conduct records searches in the California Natural
Diversity Database and the United States Fish and Wildlife Service Information for Planning and
Conservation database. A field survey would also be required to complete the Memorandum; however,
GPA biologists Sheri Mayta and Hannah Hart conducted a field survey in the same area for the Warm
Creek Maintenance Project on November 8, 2018; the information obtained during the survey on
November 8 is sufficient to complete the Memorandum, and a separate survey would not be required.
GPA will document the results of the recent field visit and describe the current site conditions in a
Memorandum, including revised mapping, as appropriate. The memorandum will be prepared in a
format acceptable to the permitting agencies. GPA will perform a thorough and accurate technical
review of the Memorandum prior to submittal to the City and the USACE. Once the technical review is
completed by GPA, the Memorandum will be submitted to the City for review prior to submittal to the
USACE.
231 colifoinio el segundo 90245 1. 310.792.2690 1.310.792.2696
2
Task 2: Agency Coordination
The environmental and permitting processes have extended approximately 24 months beyond what was
anticipated in the existing contract and project schedule. The permitting agencies have requested
additional efforts as part of the regulatory process, including information and consultation beyond what
was originally anticipated. GPA will coordinate with the USACE, RWQCB, CDFW, and the City to provide
the information and consultation that has been requested by permitting agencies in order to obtain
permit approvals.
Task 3: Project Management
Throughout the permitting process, GPA will maintain a clear line of communication with the City, and
will conduct regular status checks to ensure all tasks are on schedule and within budget. The GPA
Project Manager (PM) will prepare a monthly progress report that includes the progress of each task,
new and ongoing issues, proposed resolutions, and estimated impact on the schedule. GPA will also
maintain electronic copies of the complete environmental record of the project, and will provide the
City with a copy of all documentation.
ASSUMPTIONS
• No technical studies other than the Memorandum will need to be revised in order to complete
the permitting processes.
• The permitting process would be complete in May 2013.
• Permitting fees have not been included in the fee; if any additional permitting fees are required
by the regulatory agencies, GPA assumes they would be paid directly by the City.
• On-51te or off-site mitigation required by the regulatory agencies would be implemented by the
City.
• A ten percent contingency has been included in our fee. if the contingency is required to
complete unanticipated activities related to the regulatory permits, GPA will submit a request to
the City to release the contingency funds.
231 colifnrnin street, el segundo ca 90245 t. 310.792 2690 f 310.792,2696
3
Project Budget:
2nd Street Bridge Project Regulatory Permits and Biological Memorandum
December 13, 2018
Task 1: Biological Memorandum
Hannah Hart -BioloW
24.00
$100.00
$2,400.00
Shed Mayta - Senior BloIoW
6.00
$110.00
$660.00
Jennifer Johnson - Associate BiokgM
16.00
$110Ai1
$1,760.x1
MadekaSchrader-Senior Associate
4-00
$150.00
$600.00
Marlin Rose - Senior GIS Analyst
4.10
$150.00
$600.00
Task Subtotal _
514.00
56.020.00
Task 2: Agency Coordination
Jennifer Johnson- Associate Bio ist
16-00
$110-00
$1,760.00
E dnn Ova - Senior Environmental Planner
6.00
$150.00
$400.00
Task Subtotal
2200
$266QA0
Task 3: Project Management
Erin Sava - Senior Environmental Planner
6.00
$150.00
$900.00
Task SubtoW
6A0
Mom)
Total Services
82.00
$9,5110.00
MIS
Amt Mkup
10% Coniinpency
1.00
$958.00
5858.00
Mal Delivery - project expense
2.00
$8.50
$17.00
Total Expenses
$975.00
Total Service:
$9,580.00
Total Expense:
X5,00
Second Street Bridge Replacement
Bridge Construction Supports
Company: CNS Engineers, Inc.
-
Date:
12113@01
TOTAL
- - - -
LABOR
STAFF TITLE
STAFF NAME
HOURS
Hourly Rate
COSTS
Principal BridQe En •r
TL -U-
11
$89.50 $98E
Senior Brid a Engineer
Q Nwau en - _............
50
-
$60 50
$3.025
Bridge Pro'eat Engineer
J. No en -
24
$43.50
$1,044
CADD Designer
N Li
4038.50
$1,547
Administrator
H Huano
2
$58.50
_.... _
$117
$C
DIRECT LABOR SUBTOTALS 127 $52.84 $6,711
(ave' rate)
DIRECT LABOR TOTAL
ESCALATION a 0'A LABOR TOTAL
OVERHEAD @ 141.93%
TOTAL LABOR & OVERHEAD
OTHER DIRECT COSTS (ODC'S):
s Mileage 300 $0.545 per mile
Reproduction
Postage/Deliveries
TOTAL OTHER DIRECT COSTS
PROFIT (10% OF LABOR & OVERHEAD.:
TOTAL CNS COSTS
SUBCONSULTANTS:
None
SUBTOTAL SUBCONSULTANT COSTS $0
.. _.
TOTAL SUBCONSULTANT COSTS
TOTAL COSTS
$9,524
$164
$200
$100
$0
$18,322
jmrmwT: DATE ?7!13118
NS ENGINEERS, INC. Task BRIDGE CONSTRUCTION SUPPORTS
tOJECT: Second Street Bridge REVI M -
Task Na Task Name BtWge Senior Mip Mige R ajert (ADD peqbq CWHOURS
Err¢ Eng mw 6gireer
J Lu Q Nguyen J. N�uvrn N Li H Hwnu 5000
$238.18 $761A0 1 $115.76 $102A6 $155.68 $0.00
13.0
mufumnu
Nape re Addenda and Change Orders
tl 1
1
8
2
8
10
19
Review Shop, Dra n s and RFPs
2
24
22
qg
site vrsfts
10
10
Pre. are As-BuR Plans
g
40
SublM • Ham
11
64
14
ere
Q
127
5u6fo6ef -
$20
050
2 ii$
088
5311 so
WAN
ODC
Total
1484
I 5is=
Structure Scope of Work
Task 13: Construction Support Services
CNS shall answer bidders' questions regarding the structural contract bid documents, and
prepare bid addenda if required. CNS will review structure shop drawings and submittals for
conformance with the contract plans and specifications and make recommendations for
acceptance, denial or re -submittal.
CNS shall provide response to contractor's requests for information (BFI's) about the contract
plans and specifications forwarded to the Consultant by the City. Upon written authorization
from the City, we will provide engineering design services for revisions to construction
documents resulting from changed field or unforeseen conditions or other change order work.
CNS will perform up to three (3) site visits during the construction as requested by the City.
Following the completion and acceptance of the project, we will furnish the City a complete set
of revised contract drawings showing as -built conditions. Revisions will be solely based on as -
built redline information provided by the Contractor and the City.