HomeMy WebLinkAbout18- Public Works CITY OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
File No. 3 . 14-23
From: ROGER G. HARDGRAVE Subject: Approval of Change Order No. 3 -
Phase IV of Northwest Inter-
Dept: Public Works ceptor Sewer, per Plan No. 9195 -
ORIGINAL --UTAH PACIFIC CONSTRUCTION
Date: 10-28-96
Synopsis of Previous Council action:
June, 1986 - Allocation of $409 , 000 in 1986/87 Sewer Line Construc-
tion Fund budget approved.
04--04-94 - Resolution No. 94-84 adopted authorizing execution of
an agreement with Holmes and Narver for professional
design services.
06-05-95 •- Transfer of $497 , 000 from Acct. No. 245--365-5504-1526 ,
Phase I , to Account No. 245--365-5504-1529 , Phase IV
Northwest Interceptor Sewer, approved.
06-05-95 - Plans approved; authorization to advertise for bids .
01-22---96 -- Resolution No. 96--17 adopted awarding a contract for
low bid price of $616 , 176 .
07-01-96 - Change Order #1 approved, to authorize Contractor to
install larger casing, at a not to exceed cost of
$25 , 000 .
Recommended motion:
That Change Order .No. 3 to the contract with Utah Pacific Construc-
tion for construction of Phase IV of the Northwest Interceptor
Sewer from Medical Center Drive and 16th St. to California St. and
Porter St. , in accordance with Plan No. 9195 , be approved; to
authorize payment of $31 , 023 . 60 as settlement of all claims filed
by the Contractor.
cc: S .. Cl-r'31-1
ii. 'achon
J. Penr,'tan
Signature
Contact person: Steve Enna Phone: 5225
Staff Report,
Supporting data attached: Memo & CCO #3 Ward: 6
FUNDING REQUIREMENTS: Amount: $31 , 023 . 60 (Sewer Line Construction Fund)
Source: (Acct. No.) 245•-365-5504-1529
Acct. Description)Phase IV - Nopthwest Interceptor
Sewer Financ
Council Notes:
1I IS' q
IR
Agenda Item No.
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT Page 1 of 2
The following five (5) claims for additional costs were
submitted by Utah Pacific Construction, in connection with Phase
IV of the Northwest Interceptor Sewer.
1 . Conflict with Caltrans ' Traffic Signal Conduits --
Even though Caltrans is exempted, by Section 4216 of the
California Government Code , from the requirement to be a
member of Underground Service Alert (the regional utility
notification organization) their personnel marked the
location of their traffic signal conduits at California
Street and Highland Avenue.
However, Caltrans ' personnel failed to mark all of their
conduits . This omission resulted in delays to the Contractor
while repairs were being made. The Contractor submitted a
claim for the additional work incurred in the amount of
$10 , 571 . 37 .
Our office did not approve this claim, since the owner is
normally responsible for failure to adequately mark their
facilities .
2 . Conflicts with Abandoned Muscoy Water District Lines - -
Five (5) abandoned Muscoy Water District lines were
encountered by the Contractor. These lines were not shown on
the plans, since the Water District did not advise us of
their existence. The Contractor submitted a claim in the
amount of $1 , 776 . 68 for the extra work involved in removing
these lines .
This claim was not approved by our office, since conflicts
with unmarked utility facilities are normally the responsi-
bility of the owner.
3 . Conflict with San Bernardino Municipal Water District Line --
The Contractor broke a 6-inch water main at the intersection
of California Street and Highland Avenue. This water line
was not shown on the plans, since we were not aware of its
existence. The Contractor submitted a claim in the amount of
$1 , 168 . 83 for the extra costs incurred by this conflict.
Since the owner is normally responsible for conflicts with
unmarked utilities, this claim was not approved by our
office.
4 . Additional Costs for Boring the 48-inch Steel _Casing under
Highland Avenue --
Change Order No. One was approved to authorize payment to the
Contractor for the actual costs incurred by increasing the
steel casing from 36-inch to 48-inch, up to a net increase of
10-28-96
75-0264
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Page 2 of 2
$25 , 000 . The Contractor submitted a claim in the amount of
$42 , 506 . 72 , due to the unforeseen costs incurred by encoun-
tering large rocks. The soil borings for this project did
not reveal any large rocks, so the auger delivered to the
project site was for soil only, and had to be replaced.
This cost was not approved, since Contract Change Order No.
One was for a not-to-exceed cost of $25 , 000 .
5 . Additional Asphalt Concrete Paving for Trench in California
Street
The Contractor submitted a claim in the amount of $14 , 395 . 25
for the extra cost incurred in paving the trench. A trench
width of 9 . 15 feet was used in preparing the bid, but the
actual width was more than 14 feet, due to unstable soil and
existing utilities .
This claim was not approved, since soil conditions are
normally factors that the Contractor must deal with in the
course of the project.
An informal arbitration board was established to review these
claims and make a recommendation. This panel was comprised
of the following persons:
1 . Ray Salvador - Assistant to the Mayor.
2 . Brian Gengler - Civil Enginering Associate for the City
of Loma Linda.
3 . Chris Dean - Eastland Construction
The recommendation of this board, as set forth in the memo dated
10-22-96 , is that Claims No. 1 - 4 be approved. A copy of this
memo is attached for reference.
Utah Pacific Construction has agreed to accept payment of
$31 , 023 . 60 , for claims No. 1 - 4 , as settlement in full .
The Board also recommended that the City seek reimbursement from
Caltrans, Muscoy Water District and San Bernardino Municipal
Water Department. Billing advices have been prepared for these
agencies and forwarded to our Finance Department for preparation
of the actual bills .
Change Order No. 3 will authorize payment to the Contractor of
$31 , 023 . 60 , for Claims Nos. 1 - 4 . We recommend that Change
Order No. 3 be approved as a settlement of all claims submitted
by the Contractor.
Attach.
75-0264
CITY OF SAN BERNARDINO
INTEROFFICE MEMORANDUM
TO : Steve Enna, Construction Engineer
FROM: Ray Salvador, Assistant to the Mayor
SUBJECT: Informal Arbitration, Spec . No. 9195, 16th Street and
California Street .
DATE : October 22 , 1996
COPIES : Roger Hardgrave, Director of Public Works; File .
-------------------------------------------------------------------
Per Informal Administrative Arbitration held on October 17, 1996,
the Arbitration Board recommends as follows in the above referenced
matter:
1 . Claims for Caltrans delays be approved for subcontractors T &
M and markup only.
2 . Claim for delays due to Muscoy Water District be approved.
3 . Claims for delays due to San Bernardino Water District be
approved.
4 . Claim for additional costs for bore casing size increase be
approved.
5 . Change order No. 3 , additional AC paving on California Street
due to soil conditions and existing utilities be disapproved.
The Board recommends that the City seek reimbursement from
Caltrans, Muscoy Water District and San Bernardino Water District .
Please do not hesitate to contact me at X5210 if you have any
questions or require further information.
Ray Salvador
Assistant to the Mayor
For Boardmembers Brian Gengler and Chris Dean
C I T Y O F S A N B E R N A R D I N O
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
Project: INSTALLATION OF SEWER MAIN LINE IN 16TH STREET AND
CALIFORNIA STREET BETWEEN MEDICAL CENTER DRIVE AND PORTER
STREET.
File No. : 3 . 14-26
Plan No. : 9195
Date: 10/28/96
CONTRACT CHANGE ORDER NO. THREE
TO: UTAH PACIFIC CONSTRUCTION
40940 Eleanora Way
Murrieta, CA 92562
Gentlemen:
You are hereby compensated for performing the extra work as
directed by the Resident Engineer, as follows:
(1) Delay and relocation costs due to a conflict with the existing
unidentified Caltrans facilities, at the intersection of
Highland Avenue and California Street, at a total cost of
$ 10, 571. 37.
(2) Delay due to a conflict with the existing Muscoy Water
facilities, north of the intersection of Highland Avenue and
California Street, which were not indicated on the plans, at a
total cost of $ 1,776. 68.
(3) Delay due to a conflict with the existing 6-inch San Bernardino
Waterline, at the intersection of Highland Avenue and
California Street, which was not indicated on the plans, at a
total cost of $ 1, 168.83 .
(4) Additional work performed by the contractor while installing
the steel casing across Highland Avenue @ California Street,
when large rocks were encountered during the jacking operation,
at a total cost of $ 17,506.72 .
Total Extra Work Cost added to the Contract . . . . .$ 31,023. 60
Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . .$ 642,881.00
Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 673,904. 60
Additional time to complete Contract due to Change Order -O-Working
Days
Contract Change Order No. 3
File No. 3. 14-26
Page 2
CONTRACTOR CITY OF SAN BERNARDINO
Accepted Recommended
By: By:
ROGER G. HARDGRAVE DATE
Director of Public Works/City Engr
Title:
Date: