HomeMy WebLinkAbout11- Development Department Dt; VELOPMENT DEPARTMENT
OF THE CITY OF SAN BERNARDINO
REQUEST FOR COMMISSION/COUNCIL ACTION
FROM: KENNETH J. HENDERSON SUBJECT: CENTRAL POLICE STATION
Executive Director CONSTRUCTION CONTRACTS/
BIDDING
DATE: February 15, 1994
---------------------------------------------------------------------------------------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action(s):
December 7, 1992 - The Community Development Commission approved the site plan of"Scenario C" and
authorized staff and consultants to proceed with the development of plans and determination of costs and
methods of financing a new Central Police Station.
(Synopsis Continued to Next Page...)
---------------------------------------------------------------------------------------------------------------------------------------------
Recommended Motion(s):
(Community Development Commission)
MOTION: That the Community Development Commission authorize the execution of a Construction
Management contract with Millie and Severson, Incorporated, for general contracting and
construction management services in connection with the construction of the Central Police
Station; further, that the Commission authorize advertisement for Trade Contractor bids for
construction of the Station; further,that the Commission increase the Agency budget in an
amount of$369,714 for construction management services; and, further, that the Commission
direct staff to prepare financing documents for a Certificates of Participation issue to yield
approximately $5,000,000 in construction funds, and a Tax Allocation Bond issue in an amount
necessary to provide for completion of construction and furnishing of the Station.
&4,14
Administrator KENNET J. HEND SON
Executive Director
---------------------------------------------------------------------------------------------------------------------------------------------
Contact Person(s): Kenneth J. Henderson/John Hoeger Phone: 5081
Project Area(s): Central City North (CCN) Ward(s): One (1)
Supporting Data Attached: Staff Report;
FUNDING REQUIREMENTS: Amount: $369.714 Source: Bond Proceeds
Budget Authority: Requested
---------------------------------------------------------------------------------------------------------------------------------------------
Commission/Council Notes:
--------------------------------------------------------------------------------------------------------------------------
KJH:JBH:lag:cpsconst.cdc COMMISSION MEETING AGENDA
MEETING DATE: 02/2111994
Agenda Item Number: _
REQUEST FOR COMMISSION/COUNCIL ACTION
Central Police Station - Construction Contracts/Bidding
February 15, 1994
Page Number -2-
----------------------------------------------------------------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action(s) Continued:
April 5, 1993, The City Council adopted Resolution of Intention No. 93-106 regarding the
vacation of Seventh Street.
April 19, 1993, The Commission received and filed a report on site and orientation
alternatives and on the impact of the closure of Seventh Street.
May 24, 1993, The Commission approved $8,000,000 in tax allocation bond financing with
the balance to be determined at some future date. The Council adopted a resolution vacating
Seventh Street.
July 6, 1993, The Commission authorized solicitation of bids for general contracting services.
September 7, 1993, The Council authorized preparation of documents and resolutions for
Certificates of Participation financing for construction and furnishing of the facility. The
Commission designated the firm of Millie and Severson, Incorporated as the apparent lowest
responsible bidder and directed the negotiation of a contract for general contracting services.
November 15, 1993, Resolutions were adopted by the Council, the Commission, and the San
Bernardino Joint Powers Financing Authority providing for approximately $6,120,000 in
Certificates of Participation financing.
November 23, 1993, The Development Review Committee adopted a mitigated negative
declaration and approved Development Permit (Type III) No.93-09 to provide for construction
of the Station.
--------------------------------------------------------------------------------------------------------------------------
KJH:JBH:lag:cpsconst.cdc COMMISSION MEETING AGENDA
MEETING DATE: 02/21/1994
Agenda Item Number:
DEVELOPMENT DEPARTMENT
STAFF REPORT
---------------------------------------------------------------------------------------------------------------------
Central Police Station - Construction Contracts/Bidding
During the year of 1993, the Common Council, the Community Development Commission,
Joint Powers Financing Authority, and the City's Development Review Committee have all
taken various actions to enable completion of design for the new Central Police Station.
Completion of the design work now allows the Agency to proceed with competitive bidding
for the construction work of the Station. Based upon the results of this bidding process, staff
will return to the Commission and Council with recommendations for award of construction
contracts and for issuance of bonds in amounts determined from the bidding.
In accordance with Commission action on September 7, 1993, staff has negotiated a contract
with Millie and Severson, Incorporated, for general contracting and construction management
services. Based upon advice from the City Attorney's office regarding the most expeditious
format for the document, this contract is a now construction management contract in the
amount of $369,714.
The City Attorney's office is completing the final form of the contract and bid specification
documents. A final form of contract will be available for distribution on Friday, February 18,
1994, in replacement of the attached draft.
CONSTRUCTION MANAGEMENT CONTRACT
The attached construction management contract provides for both preconstruction and
construction services from Millie and Severson, Incorporated (Severson). The City Attorney's
office has consulted with staff on the most problem free approach to this contract within the
requirements of public works contracting law. The use of the construction manager approach
allows for consistency with the bid request authorized by the Commission and will provide
the most straight forward approach to the construction of the Station.
The contract is based upon:
$ 25,000 Preconstruction Period Manager's Fee
155,000 Construction Period Manager's Fee
6,811 Liability Insurance
150,829 Personnel Fee
32,074 General Conditions
$369,714 Total
--------------------------------------------------------------------------------------------------------------------------
KJH:JBH:lag:cpsconst.cdc COMMISSION MEETING AGENDA
MEETING DATE: 02/21/1994
Agenda Item Number: _
DEVELOPMENT DEPAI AENT STAFF REPORT
Central Police Station - Construction Contracts/Bidding
February 16, 1994
Page Number -4-
--------------------------------------------------------------------------------------------------------------------------
This represents a $66,540 reduction from the original low bid amount of $436,254. This
difference primarily results from the fact that individual prime trade contractors will provide
performance bonds for the construction. There has also been a reduction in the general
conditions section as a result of certain services no longer required from Severson.
In accordance with the specifications approved by the Commission in the Request for
Qualifications/Invitation to Bid, the contract is based upon earlier cost and schedule estimates
for construction of the Station. It provides for the pro rata adjustment of the Construction
Manager's fee based upon actual amounts under final contract. It also provides for an
adjustment in personnel costs and general conditions in the event of approved extensions in
the project schedule.
In accordance with the Commission's action of December 7, 1992, and in order to complete
the Station's design within the tightest possible schedule, Severson has begun the
constructability reviews and the drafting of bidding documents necessary to allow for the
trade contracting bidding process to be completed on a timely basis. Bids for the
construction of Station will be advertised upon Commission adoption of the form motion.
PRIME TRADE CONTRACT BIDDING
Upon approval of the Commission, bids will be requested for all prime trade contract
specialties. A copy of the bidding specifications and construction drawings is available for
public review and inspection at Agency offices and a second set has been placed in the
Council offices for the convenience of Commission members. To shorten the required time,
the first construction component will be demolition and site grading. The project schedule
calls for the grading bid request to be advertised on February 25, 1994 and for bids to be
opened on March 23, 1994. This will allow for recommendations to the Commission for
award of grading at its meeting of April 4, 1994. The balance of the trades will be bid
approximately three (3) weeks later.
The facility is a 79,961 square foot two-story tilt up concrete structure. It is designed as an
essential facility so that operations can be expected to continue even after an emergency
event, such as an earthquake on the San Andreas fault. It has been value engineered to
reduce costs. For example, reinforcement is placed in areas of the roof bearing heavy loads
(such as underneath air conditioning units) while other areas in the same roof are not
reinforced unnecessarily. The tilt up construction and value engineering have combined to
reduce costs substantially as compared to similar facilities recently completed elsewhere.
--------------------------------------------------------------------------------------------------------------------------
KJH:JBH:lag:cpsconst.cdc COMMISSION MEETING AGENDA
MEETING DATE: 02/21/1994
Agenda Item Number:
DEVELOPMENT DEPAI ✓LENT STAFF REPORT
Central Police Station - Construction Contracts/Bidding
February 16, 1994
Page Number -5-
--------------------------------------------------------------------------------------------------------------------------
The City Administrator's office, the City's Facilities Maintenance Division, and the Police
Department have reviewed the specifications as they have been developed by the design team.
Also, of course, the process has bee reviewed and checked by the Planning and Building
Services Department and by the Department of Public Works. Reductions in cost have been
made throughout the project to keep costs at a minimum, while continuing to meet the
program requirements for police operations. Some portions of the program, such as the short
term detention facility and the document imaging equipment, are expected to save substantial
amounts of operational costs for the City each year.
The actual amount for the cost of construction will not be known until after the completion of
bidding. Nevertheless, Severson has, as part of its constructability reviews and project cost
estimating services, recently completed informal bidding based upon the recently available
draft construction documents. The best estimates indicate that building construction will fall
between $100 to $105 per square foot (the design target has been $100) and that fixtures and
equipment installed as part of the construction process will equal approximately $6 per square
foot. The estimates are:
$ 7,699,401 Building Construction
2,381,004 Indirect (A&E, permits, construction
management, etc.)
$955,884 Site Costs
$ 11,036,289 TOTAL BUILDING CONSTRUCTION
$ 436,220 FF&E Prime Trade Contracts
$ 11,472,509 TOTAL UNDER CONTRACT
--------------------------------------------------------------------------------------------------------------------------
KJH:JBH:1ag:cpsconst.cdc COMMISSION MEETING AGENDA
MEETING DATE: 02/21/1994
Agenda Item Number: I-
DEVELOPMENT DEPAL ✓LENT STAFF REPORT
Central Police Station - Construction Contracts/Bidding
February 16, 1994
Page Number -6-
--------------------------------------------------------------------------------------------------------------------------
In addition there are fixtures, furnishings and equipment to be supplied by vendors based
upon bids obtained under the City and Agency's procurement procedures. The estimates for
vendor supplied items are:
$ 104,321 Fixtures
1,113,104 Furniture
595,000 Equipment
$ 1,812,425 TOTAL FF&E
These are estimates and the actual amount will be determined by competitive bidding in
accordance with adopted procedures. In addition to these costs there are the acquisition costs
the Agency has paid to obtain the site. A detailed cost estimate breakdown is available for
review but actual costs will be determined by bidding.
RECOMMENDATION
The plans and specifications have been reviewed by the appropriate City Departments and
Divisions. The proposed construction management contract has been approved by Agency
Counsel. Based upon the above, staff recommends adoption of the form motion.
k, �1
KENNETH J. ENDERSON, Executive Director
Development Department
--------------------------------------------------------------------------------------------------------------------------
KJH:JBH:1ag:cpsconst.cdc COMMISSION MEETING AGENDA
MEETING DATE: 02/21/1994
Agenda Item Number: _
City Attorney
DRAFT
AGREEMENT BETWEEN OWNER
AND CONSTRUCTION MANAGER
AGREE4ENT
Made this day of in the year Nineteen Hundred
and Ninety-Four ( 1994 ) .
BETWEEN The Redevelopment Agency of the City of
San Bernardino
THE OWNER, AND
Millie and Severson, Incorporated
THE CONSTRUCTION MANAGER.
For services in connection with the following described Project:
San Bernardino Police Facility
The Architect/Engineer for the Project is : Leach Mounce Architects
The Owner and the Construction Manager agree as set forth below:
FLR/aLCPDFaciL.Agr] 1
February 10, 1994
I �
uty Hnorney
DRAFT
ARTICLE 1
THE CONSTRUCTION TEAM AND EXTENT OF AGREEMENT
The CONSTRUCTION MANAGER accepts the relationship of trust and
confidence established between him and the Owner by this Agreement.
He covenants with the Owner to furnish his best skill and judgment
and to cooperate with the Architect/Engineer in furthering the
interests of the Owner. He agrees to furnish efficient business
administration and superintendence and to use his best efforts to
complete the Project in the best and soundest way and in the most
expeditious and economical manner consistent with the interest of
the Owner.
1. 1 THE CONSTRUCTION TEAM. The Construction Manager, the
Owner, and the Architect/Engineer called the "Construction Team"
shall work from the beginning of design through construction
completion. The Construction Manager shall provide leadership to
the Construction Team on all matters relating to construction.
1.2 EXTEND OF AGREEMENT. This Agreement represents the
entire agreement between the Owner and the Construction Manager and
supersedes all prior negotiations, representations or agreements .
When Drawings and Specifications are complete, they shall be
identified by amendment to this Agreement. This Agreement shall
not be superseded by any provisions of the documents for
construction and may be amended only by written instrument signed
by both Owner and Construction Manager.
1.3 DEFINITIONS
1 . 3 . 1 The Project is the total construction to be managed under
this Agreement .
1 . 3 .2 The Work is that part of the construction that a
particular Trade Contractor is to perform and such General
Condition Items that the Construction Manager performs with his own
forces .
1. 3 . 3 General Condition Items as used herein shall be deemed to
mean provision of facilities or performance of work by the
Construction manager for items which do not lend themselves readily
to inclusion in one of the separate trade contracts . General
condition items may include (but are not limited to) the following:
watchmen; scaffolding; hoists; signs; safety barricades; water
boys; cleaning; dirt chutes; cranes; shanties; preparation for
ceremonies including minor construction activity in connection
therewith; temporary toilets; fencing; sidewalk bridges; first aid
,station; trucking; temporary elevator; special equipment; winter
protection; temporary heat, water, and electricity; temporary
protective enclosures; field office and related costs thereof such
FLR/aLCPDFaciL.Agr1
February 10, 1994 2
l
Ulty Attorney
DRAFT
as equipment furnishings and office supplies; progress, final and
miscellaneous photographs; messengers; installation of Owner
furnished items; post and planking; general maintenance; subsoil
exploration; refuse disposal; field and laboratory tests of
concrete, steel and soils; surveys; bench marks and monuments;
storage on site and off site of long lead procurement items; and
miscellaneous minor construction work when it is not feasible for
the Owner to secure competitive bids or proposals thereon. General
Conditions may become part of Trade Contractors work as provided
elsewhere in the contract documents . Exhibit sets forth
items included.
ARTICLE 2
CONSTRUCTION MANAGER'S SERVICES
The Construction Manager will perform the following services
under this Agreement in each of the two phases described below.
2 . 1 DESIGN PHASE
2 . 1 . 1 CONSULTATION DURING PROJECT DEVELOPMENT. Schedule and
attend regular meetings with the Architect/Engineer during the
development of design to advise on selection of materials , building
systems and equipment . Provide recommendations on construction
feasibility, availability of materials and labor, time requirements
for installation and construction, and factors related to cost
including costs of alternative designs or materials, preliminary
budgets , and possible economies .
2 . 1.2 SCHEDULING. Develop a Project Schedule that coordinates
and integrates the Architect/Engineer' s design efforts and the
Owner' s activities with construction schedules . Update the Project
Schedule incorporating a detailed schedule for all activities of
the project, including realistic activity sequences and durations,
allocation of labor and materials, processing of shop drawings and
samples, and delivery of products requiring long lead-time
procurement . Include the Owner' s occupancy requirements showing
portions of the Project having occupancy priority.
2 . 1 .3 PROJECT CONSTRUCTION BUDGET. Update and refine the
project budget estimate prepared by the Koll Company for Owner' s
approval as the development of the Drawings and Specifications
proceeds, and advise the Owner and the Architect/Engineer if it
appears that the Project Construction Budget will not be met and
make recommendations for corrective action.
2 . 1.4 COORDINATION OF CONTRACT DOCUMENTS. Review the Drawings
and Specifications as they are being prepared, recommending
alternative solutions whenever design details affect construction
FLR/aL[PDFacil.Agr1 3
February 10, 1994
Il
Uly Attorney
DRAFT
feasibility or schedules without, however, assuming any of the
Architect/Engineer' s responsibilities for design.
2 . 1. 5 CONSTRUCTION PLANNING. Recommend for purchase by the
Owner and expedite the procurement of long-lead items to ensure
their delivery by the required dates .
2. 1.5. 1 Make recommendations to the Owner and the
Architect/Engineer regarding the division of Work in the Drawings
and Specifications to facilitate the bidding and awarding of Trade
Contracts, allowing for phased construction taking into
consideration such factors as time of performance, availability of
labor, overlapping trade jurisdictions, and provisions for
temporary facilities .
2 . 1 . 5.2 Review the Drawings and Specifications with the
Architect/Engineer to eliminate areas of conflict and overlapping
in the Work to be performed by the various Trade Contractors .
Develop bid specifications and review and advise on all bid
documents and procedures .
2 . 1 . 5. 3 Develop Trade Contractor interest in the Project and as
working Drawings and Specifications are completed, assist the Owner
in taking competitive bids on the Work of the various Trade
Contractors . After analyzing the bids, recommend to the Owner that
such contracts be awarded.
2 . 1.6 EQUAL EMPLOYMENT OPPORTUNITY. Determine applicable
requirements for equal employment opportunity programs for
inclusion in Project bidding documents, by coordinating with Owner
(City) personnel .
2 .2 CONSTRUCTION PHASE
2 .2 . 1 PROJECT CONTROL. Monitor the Work of the Trade
Contractors and coordinate the Work with the activities and
responsibilities of the Owner, Architect/Engineer and Construction
Manager to complete the Project in accordance with the Owner' s
objectives of cost, time and quality.
2 .2 . 1. 1 Maintain a competent full-time Superintendent at the
Project site to coordinate and provide general direction of the
Work and progress of the Trade Contractors on the Project.
2 .2 . 1.2 Establish on-site organization and lines of authority in
order to carry out the overall plans of the Construction Team.
2 .2 . 1 .3 Establish procedures for coordination among the Owner,
Architect/Engineer, Trade Contractors and Construction Manager with
respect to all aspects of the Project and implement such
procedures .
FLR/aLCPDFac L.Agr] 4
February 10, 1994
I �
Uty Attorney
DRAFT
2 .2 . 1 .4 Schedule and conduct progress meetings at which Trade
Contractors, Owner, Architect/Engineer and Construction Manager can
discuss jointly such matter- as procedures, progress, problems and
scheduling.
2 .2 . 1 . 5 Provide regular monitoring of the Project Schedule as
construction progresses . identify potential variances between
scheduled and probably completion dates . Review schedule for Work
not started or incomplete and recommend to the Owner and Trade
Contractors adjustments in the schedule to meet the probable
complete date. Provide summary reports of each monitoring and
document all changes in schedule .
2 .2 . 1 . 6 Determine the adequacy of t'-e Trade Contractors '
personnel and equipment and the availabi-ity of materials and
supplies to meet the schedule . Recommend courses of action to the
Owner when requirements of a Trade Contract are not being met .
2 .2 .2 PROVISIONS OF FACILITIES. Provide all supervision,
labor, materials, construction equipment, tool and subcontract
items which are necessary for the completion of the General
Condition items which are set forth in Exhibit "B" .
2 .2 . 3 COST CONTROL. Develop and monitor an effective system of
Project cost control . Revise and refine the initially approved
Project Construction Budget, incorporate approved changes as they
occur, develop cash flow reports and forecasts as needed, and
identify variances between actual and budgeted or estimated costs
and advise the Owner and Architect/Engineer whenever projected cost
exceeds budgets or estimates .
2 .2 .3 . 1 Maintain cost accounting records on authorized Work
performed under unit costs , actual costs for labor and materials ,
or other basis requiring accounting records . Afford the Owner
access to these records and preserve them for a period of three ( 3 )
years after final payment.
2 .2 .4 CHANGE ORDER. Develop and implement a system for the
preparation, review and processing of Change Orders . Recommend
necessary or desirable changes to the Owner and the
Architect/Engineer, receive requests for changes , assemble the
required information and documentation, submit recommendations to
the Owner and the Architect/Engineer, and assist in negotiating
Change Orders .
2 .2 . 5 PAYMENTS TO TRADE CONTRACTORS. Develop and implement a
procedure for the review, approval, processing and payment of
applications by Trade Contractors for progress and final payments .
FLR/aLCPDFaciL.Agr1 5
February 10, 1994
CITY Attorney
DRAFT
2.2 .6 PERMITS AND FEES. Assist the Owner and
Architect/Engineer in obtaining all building permits and special
permits for permanent improvements, excluding any permits required
to be obtained by the various Trade Contractors, such as permits
for inspection, temporary facilities, etc . Assist in obtaining
approvals from all the authorities having jurisdiction.
2.2.7 OWNER' S CONSULTANTS. If required, assist the Owner in
selecting and retaining professional services of a surveyor,
testing laboratories and special consultants, and coordinate these
services .
2 .2 .8 REVIEW OF WORK AND SAFETY. Review the Work of Trade
Contractors for defects and deficiencies in the Work without
assuming any of the Architect/Engineer' s legal responsibilities for
design and inspection. Review the safety programs of each of the
Trade Contractors and make appropriate recommendations . In making
such reviews, he shall not be required to make exhaustive or
continuous inspections to check quality of work, safety precautions
and programs in connection with the Project. The performance of
such services by the Construction Manager shall not relieve the
Trade Contractors of their responsibilities for performance of the
work and for the safety of persons and property, and for compliance
with all federal, state and local statutes, rules, regulations and
orders applicable to the conduct of the Work.
2 .2 .9 DOCUMENT INTERPRETATION. Refer all questions for
interpretation of the documents prepared by the Architect/Engineer
to the Architect/Engineer.
2 .2 . 10 SHOP DRAWINGS AND SAMPLES. In collaboration with the
Architect/Engineer, establish and implement procedures for
expediting the processing and approval of shop drawings and
samples .
2 .2 . 11 REPORTS AND PROJECT SITE DOCUMENTS. Record the progress
of the Project. Submit written progress reports to the Owner and
the Architect/Engineer including information on the Trade
Contractors ' Work, and the percentage of completion. Keep a daily
log available to the Owner and the Architect/Engineer.
2 .2 . 11. 1 Maintain at the Project site, on a current basis :
records of all necessary Contracts, Drawings, samples, purchases,
materials , equipment, maintenance and operating manuals and
instructions, and other construction related documents, including
all revisions . Obtain data from Trade Contractors and maintain a
current set of record Drawings, Specifications and operating
manuals . At the completion of the Project, deliver all such
records to the Owner.
FLR/aLCPDFaciL.Agr] 6
February 10, 1994
, I
DRAFT
2 .2 . 12 SUBSTANTIAL COMPLETION. Determine Substantial Completion
of Work or designated portions thereof and prepare for the
Architect/Engineer a list of incomplete or unsatisfactory items and
a schedule for their completion.
2 .2 . 13 START-UP. With the Owner' s maintenance personnel, direct
the check out of utilities, operations systems and equipment for
readiness and assist in their initial start-up and testing by the
Trade Contractors .
2 .2 . 14 FINAL COMPLETION. Determine final completion and provide
written notice to the Owner and Architect/Engineer that the Work is
ready for final inspection. Secure and transmit to the
Architect/Engineer required guarantees, affidavits, releases, bonds
and waivers . Turn over to the Owner all keys, manuals, record
drawings and maintenance stocks .
2 .2 . 15 WARRANTY. The Construction Manager shall collect and
deliver to the Owner any specific written warranties or guarantees
given by others , including all required Trade Contractor guarantees
and warranties .
2.3 ADDITIONAL SERVICES
At the request of the Owner, the Construction Manager will provide
the following additional services upon written agreement between
the Owner and Construction Manager defining the extent of such
additional services and the amount and manner in which the
Construction Manager will be compensated for such additional
services .
2 .3 . 1 Services related to investigation, appraisals or
valuations of existing conditions, facilities or equipment, or
verifying the accuracy of existing drawings or other Owner-
furnished information.
2 .3 .2 Services related to Owner-furnished equipment, furniture
and furnishings which are not a part of the Work.
2 .3 . 3 Services related to construction performed by the Owner.
2 . 3 .4 Consultation on replacement of Work damaged by fire or
other cause during construction, and furnishing services for the
replacement of such Work.
2 .3 . 5 Services made necessary by the default of a Trade
Contractor.
2 . 3 .6 Preparing to serve or serving as an expert witness in
connection with any public hearing, arbitration proceeding, or
legal proceeding.
FLR/aLCPDFaciL.Agr] 7
February 10, 1994
DRAFT
2 .3 .7 Services related to Work performed by the Construction
Manager other than General Conditions items as set forth in Exhibit
„B„ .
2 .3 .8 Inspections of and services related to the Project after
completion of the services under this Agreement.
2 .3 .9 Providing any other service not otherwise included in
this Agreement .
ARTICLE 3
OWNER'S RESPONSIBILITIES
3 . 1 The Owner shall provide full information regarding the
requirements for the Project .
3 .2 The Owner shall designate a representative who shall be
fully acquainted with the Project and has authority to approve
Project Construction Budgets, Changes in the Project, render
decisions promptly consistent with Project Schedule and furnish
information expeditiously.
3 . 3 The Owner shall retain an Architect/Engineer for design
and to prepare construction documents for the Project. The
Architect/Engineer' s services, duties and responsibilities are
described in the Agreement between the Owner and the
Architect/Engineer, a copy of which will be furnished to the
Construction Manger .
3 .4 The Owner shall furnish for the site of the Project all
necessary surveys describing the physical characteristics, soil
reports and subsurface investigations, legal limitations, utility
locations, and a legal description.
3 .5 The Owner shall secure and pay for necessary approvals,
easements , assessments and charges required for the construction,
use or occupancy of permanent structures or for permanent changes
in existing facilities .
3 . 6 The Owner shall furnish such legal services as may be
necessary for providing the items set forth in Paragraph 3 . 5, and
such auditing services as he may require.
3 .7 The Construction Manager will be furnished without charge
all copies of Drawings and Specifications reasonably necessary for
the execution of the Work.
3 .8 The Owner shall provide the insurance for the Project as
provided in Paragraph 10 . 4 , and shall bear the cost of any bonds
required.
S
�� �a
w�'. ��c. t:,t�,i t �c,•,, t � ..t c.tip.
FLR/aLCPDFaciL.Agr] 8
February 10, 1994
City Attorney
DRAFT
3 .9 The services, information, surveys and reports required
by the above paragraphs shall be furnished with reasonable
promptness at the Owner' s expense, and the Construction Manager
shall be entitled to --ply upon the accuracy and completeness
thereof .
3 . 10 If the Owner becomes aware of any fault or defect in the
Project or non-conformance with the Drawings and Specifications, he
shall give prompt written notice thereof to the Construction
Manager.
3 . 11 The Owner shall furnish reasonable evidence satisfactory
to the Construction Manager that sufficient funds are available and
committed for the entire cost of the Project. Unless such
reasonable evidence is furnished, the Construction Manager is not
required to commence any Work, or may, if such evidence is not
presented within a reasonable time, stop the Project upon fifteen
( 15 ) days notice to the Owner.
3 . 12 The Owner shall communicate with the Trade Contractors
only through the Construction Manager.
3 . 13 Owner shall make provision within its trade contracts
giving authority to Construction Manager to direct, coordinate, and
determine the sequence of the work of Trade Contractors, and
requiring the Trade Contractor to provide to the Construction
Manager all documentation, deemed necessary by the Construction
Manager for the proper management and administration of the work,
required by this agreement, or the Trade Contract.
ARTICLE 4
TRADE CONTRACTS
4. 1 All portions of the Project other than General Condition
Items ( set forth in Exhibit "B" ) shall be performed under Trade
Contracts including contracts for general construction work with
several construction trades . The Construction Manager shall
develop bid specifications and assist the Owner in requesting and
receiving bids from Trade Contractors and Trade Contracts will be
awarded by the Owner after the bids are reviewed by the
Architect/Engineer, Construction Manager and Owner. Contracts will
be awarded to the lowest responsible bidder in accordance with
Owner' s policies and procedures .
4 .2 Trade Contracts will be between the Owner and the Trade
Contractors . The form of the Trade Contracts including the General
and Supplementary Conditions shall be developed jointly with the
Owner and Construction Manager.
FLR/aLCPDFaciL.Agr1 9
February 10, 1994
City Attorney
DRAFT
ARTICLE 5
PROJECT SCHEDULE
5. 1 The services to be provided under this Contract shall be
in general accordance with the following schedule:
a. Pre-Construction (design) phase 2 month;
b. Construction phase 9 month;
c . To the extent that the date of Substantial Completion
is longer than nine months from the commencement of
construction phase, the Construction Manager is
entitled to additional compensation as set forth in
Article 3 .
5.2 At the time work commences, a Date of Substantial
Completion of the Project shall also be established.
5.3 The Date of Substantial Completion of the Project or a
designated portion thereof is the date when construction is
sufficiently complete in accordance with the Drawings and
S-ecifications so the Owner can occupy or utilize the Project or
designated portion thereof for the use for which it is intended.
Warranties called for by this Agreement or by the Drawings and
Specifications shall commence on the Date of Substantial Completion
of the Project or designated portion thereof .
5 .4 If the Construction manager is delayed at any time in the
progress of the Project by any neglect of the Owner or the
Architect/Engineer or by any employee of either, or by any separate
contractor employed by the Owner, or by changes ordered in the
project, or by labor disputes, fire, unusual delay in
transportation, adverse weather conditions not reasonably
anticipated, unavoidable casualties , or by delay authorized by the
Owner, the Construction Completion Date shall be extended by Change
Order for a reasonable length of time.
ARTICLE 6
CONSTRUCTION MANAGER'S FEE
6. 1 In consideration of the performance of the Contract, the
Owner agrees to pay the Construction Manager in current funds as
compensation for his services a Construction Manager' s Fee as set
forth in Subparagraphs 6 . 1 . 1 and 6 . 1 . 2 .
6. 1. 1 For the performance of the Pre-Construction Design
services, a fee of $25, 000 . 00 , which shall be paid monthly, in
equal proportions, based on the scheduled Design Phase time.
FLR/aLCPDFaciL.Agr] 1 0
February 10, 1994
l �
%,1&y PAciorney
DRAFT
6. 1 .2 For work or services performed during the Construction
Phase, a fee of $155, 000 ( see page 10A) which shall be paid
proportionately to the ratio the monthly payment for the Cost of
the Project bears to the estimated cost. Any balance of this fee
shall be paid at the time of final payment.
6.2 Adjustments in Fee shall be made as follows :
6.2 . 1 For changes in the Project as provided in Article 8, the
Construction Manager' s Fee shall be adjusted by two and one-half
percent (2 1/2% ) of the additional cost of the work for increases
in the scope of the Project .
6.3 Included in the Construction Manager' s Fee are the
following:
6. 3 . 1 Salaries or c- �_er compensation of the Construction
Manager' s employees at t.-,e principal office and branch offices,
except employees listed in Subparagraph 7 . 2 . 2 .
6.3 .2 General operating expenses of the Construction Manager' s
principal and branch offices other than the field office.
6 .3 .3 any part of the Construction Manager' s capital expenses,
including interest on the Construction Manager' s capital employed
for the Project .
6. 3 .4 Overhead or general expenses of any kind, except as may
be expressly included in Article 7 .
ARTICLE 7
REIMBURSABLE COSTS
7 . 1 The Owner agrees to pay the Construction Manager for the
reimbursable costs he incurs as defined in Paragraph 7 . 2 . Such
payment shall be in addition to the Construction Manager' s Fee
stipulated in Article 6 .
7 . 1 . 1 Reimbursable costs shall only include costs for General
Conditions , as more fully described in Exhibit "B" , Personnel Fee,
Insurance costs, or costs for work which has been added by Change
Order.
7 . 1 .2 The aggregate Reimbursable Costs shall not exceed
$201, 170 ( sum of costs for General Condition fee, Personnel Fee and
Insurance costs ) . The aggregate Reimbursable Cost may be adjusted
through prorata adjustments to the General Conditon Fee and
Personel Fee agreed to in writing pursuant to Article 8 .
FLR/aLCPDFaciL.Agr] l 1
February 10, 1994
! I
DRAFT
7 . 1.3 The cost items listed in Article 7 . 2 represent allowable
cost, and are not a representative listing of the items to be
provided by Construction Manager. Cost items provided by
Construction Manager are set forth in Exhibit Any other
items for which costs are incurred are to be added by Change Order.
7 .2 REIMBURSABLE COST ITEMS
7 .2. 1 Wages paid for labor in the direct employ of the
Construction Manager in the performance of General Condition Items
under applicable collective bargaining agreements, or under a
salary or wage schedule agreed upon by the Owner and Construction
Manager, and including such welfare or other benefits, if any, as
may be payable with respect thereto.
7 .2 .2 Salaries of the Construction Manager' s employees when
stationed at the field office, in whatever capacity employed,
employees engaged on the road in expediting the production or
transportation of materials and equipment, and employees in the
main or branch office performing the functions listed below:
Scheduling
Project Management/Administration
Document Preparation
Warehousing/Transportation
Expediting
Estimating/Plan Review/Budgeting
7 .2 .3 Costs of all employee benefits and taxes for such items
as unemployment compensation and social security, insofar as such
cost is based on wages, salaries, or other remuneration paid to
employees of the Construction Manager referred to in Subparagraphs
7 . 2 . 1 and 7 . 2 . 2 .
7 .2 .4 The proportion of reasonable transportation, traveling,
moving, and hotel expenses of the construction Manager or of his
officers or employees incurred in discharge of duties connected
with the Project .
7 .2 .5 Cost including rental of all materials, supplies and
equipment required to perform General Condition Items, including
costs of transportation, storage and maintenance thereof .
7 .2 .6 Cost of the premiums for all insurance which the
Construction Manager is required to procure by this Agreement or is
deemed necessary by the Construction Manager.
. 7 .2 .7 Sales , use, gross receipts or similar taxes related to
the Project imposed by any governmental authority, and for which
the Construction Manager is liable.
FLR/aLCPDFaciL.Agr1
February 10, 1994 12
I �
DRAFT
7 .2 .8 Permit fees , licenses, tests, royalties, damages for
infringement of patents and costs of defending suits therefor, and
deposits lost for causes other than the Construction Manager' s
negligence. If royalties or losses and damages, including costs of
defense, are incurred which arise from a particular design,
process , or the product of a particular manufacturer or
manufacturers specified by the Owner or Architect/Engineer, and the
Construction Manager has no reason to believe there will be
infringement of patent rights, such royalties, losses and damages
shall be paid by the Owner.
7 .2 .9 Losses, expenses or damages to the extent not compensated
by insurance otherwise ( including settlement made with the written
approval of the owner) .
7 .2 . 10 Minor expenses such as telegrams, long=distance telephone
calls, telephone service at the site, expressage, and similar petty
cash items in connection with the Project.
7 .2 . 11 Cost of removal of all debris .
7 .2 . 12 Cost incurred due to an emergency affecting the safety of
persons and property.
7 .2 . 13 Cost of data processing services required in the
performance of the services outlined in Article 2 .
7 .2 . 14 Legal costs reasonably and properly resulting from
prosecution of the Project for the Owner.
7 .2 . 15 All costs directly incurred in the performance of the
Project and not included in the Construction Manager' s Fee as set
forth in paragraph 6 . 3 .
ARTICLE 8
CHANGES IN THE PROJECT
8. 1 The Owner, without invalidating this Agreement, may order
Changes in the Project within the general scope of this Agreement
consisting of additions, deletions or other revisions, the
Construction Manager' s Fee and the Construction Completion Date or
amount of Reimbursable Costs being adjusted accordingly. All such
Changes in the Project shall be authorized by Change Order.
8.2 A Change Order is written order to the Construction
Manager signed by the Owner or his authorized agent issued after
the execution of this Agreement, authorizing a change in the scope
of the Project, services to be provided, or the Construction
Manager' s Fee or the construction Completion Date, and/or amount of
FLR/aLCPDFaciL.Agr1 1 3
February 10, 1994
ji
Vily
DRAFT
Reimbursable Costs . The construction Manager' s Fee shall be
adjusted as provided in Paragraph 6 . 2 .
8.3 Change Orders adjusting Construction Manager compensation
shall be made as follows :
In the event that the project construction phase duration
exceeds nine ( 9 ) months ( i . e. as measured from the date of
commencement to the date of Substantial Completion) , the
Construction Manager shall receive a Change Order for a prorata
share of increased General Conditions costs and Personnel Fees .
Further, in the event that the aggregate Trade Contracts exceed
$7 , 225, 000, the Construction Manager shall receive as an adjustment
to its fee, an amount of two and one-half percent (2 . 5% ) of such
excess .
PAYMENTS TO THE CONSTRUCTION MANAGER
9 . 1 The Construction Manager shall submit monthly to the
Owner a statement, sworn to, if required, showing in detail all
Reimbursable Costs incurred during the previous month, all amounts
due Trade Contractors, and the amount of the Construction Manager' s
Fee due as provided in Article 6 . Payment by the Owner to the
Construction Manager of his statement amount shall be made within
fifteen ( 15 ) days after it is received in writing.
9.2 Final payment constituting the unpaid balance of
Reimbursable Costs and the Construction Manager' s Fee shall be due
and payable when the Project is delivered to the Owner, ready for
beneficial occupancy, or when the Owner occupies the Project,
whichever event first occurs, provided that the project be then
substantially completed and this Agreement substantially performed.
9.3 If the Owner should fail to pay the Construction Manager
within ten ( 10 ) days after the time the payment of any amount
becomes due, then the Construction Manager may, upon seven (7 )
additional days ' written notice seek a hearing before the Owner' s
governing body (EDA Commission) to resolve the dispute. Should a
resolution not be reached, the disputed amount shall be placed in
an escrow account until such time the dispute is resolved, or upon
completion of the project, the Construction Manger may seek a
judicial remedy.
9.4 Payments due but unpaid shall bear interest at the rate
the Owner is paying on his construction loan or at the legal rate,
whichever is higher .
FLR/aL[PDFacil.Agr] 1 4
February 10, 1994
DRAFT
-
VJZ a ct-
ARTICLE 10 � ` U-
INSURANCE, INDEMNITY AND--WAIVER OF SUBROGATION {��w� <� ► M S
10. 1 INDEMNITY 1
10. 1. 1 The Construction Manager agrees to indemnify and hold the
Owner harmless from all claims for bodily injury and property
damage (other than the work itself and other prope--ty insured under
Paragraph 10 . 4 ) that may arise from the Construction Manager' s
operations under this Agreement .
i
10. 1.2 The Owner shall cause all Trade Contractors to agree to
indemnify the Owner and the Construction Manager and hold them
harmless from all claims for bodily injury and property damage
(other than property insured under Paragraph 10 . 4 ) that may arise
from that contractor' s operations Such provisions shall be in a
form satisfactory to the Construction Manager.
10.2 CONSTRUCTION MANAGER'S LIABILITY INSURANCE
10.2 . 1 The Construction Manager shall purchase and maintain such
insurance as will protect him from the claims set forth below which
may arise out of or result from the Construction Manager' s !
operations under this Agreement .
10.2. 1. 1 Claims under workers ' compensation, disability benefit
and othe- similar employee benefit acts which are applicable to the
work to be performed.
10.2 . 1.2 Claims for damages because of bodily injury, occupational
sickness or disease, or death of his employees under any applicable
employer' s liability law.
r
10.2 . 1.3 Claims for damages because of bodily injury, or death of ?
any person other than his employees .
10.2 . 1.4 Claims for damages insured by usual personal injury
liability coverage which are sustained ( 1 ) by any person as a
result of an offense directly or indirectly related to the
employment of such person by the Construction Manager or (2 ) by any
other person.
10.2 . 1.5 Claims for damages, other than to the work itself,
because of injury to or destruction of tangible property, including
loss of use therefrom.
10.2 . 1.6 Claims for damages of bodily injury or death of any
person or property damage arising out of the ownership, maintenance
or use of any motor vehicle .
FLR/aLCPDFaciL.Agr1
February 10, 1994 1 5
Uty Attorney
DRAFT
10.2 .2 The Construction Manager' s Comprehensive General
Liability Insurance shall include premises --operations ( including
explosion, collapse and underground coverage) elevators,
independent contractors , completed operations, and blanket
contractual liability on all written contracts, all including broad
form property damage coverage .
10.2 . 3 The Construction Manager' s Comprehensive General and
Automobile Liability Insurance, as required by Subparagraphs 10 . 2 . 1
and 10 . 2 . 2 shall be written for not less than limits of liability
k
as follows : x
a. Comprehensive General Liability
1 . Personal Injury $1 , 000, 000 Each Occurrence
$2 , 000, 000 Aggregate
(Completed Operations)
2 . Property Damage $1 , 000, 000 Each Occurrence
$2 , 000, 000 Aggregate
b. Comprehensive Automobile Liability
1 . Bodily Injury $1, 000 , 000 Each Person
$1, 000, 000 Each Occurrence
2 . Property Damage $1, 000 , 000 Each Occurrence
10.2 .4 Comprehensive General Liability Insurance may be arranged
under a single policy for the full limits required or by a
combination of underlying policies with the balance provided by an
Excess or Umbrella Liability policy.
10.2 . 5 The foregoing policies shall contain a provision that
coverages afforded under the policies will not be canceled or not
renewed until at least sixty ( 60 ) days ' prior written notice has
been given to the Owner. Certificates of Insurance showing such
coverages to be in Force shall be filed with the Owner prior to
commencement of the Work and shall name Owner as an additional
insured.
10.3 OWNER' S LIABILITY INSURANCE
10.3 . 1 The Owner shall be responsible for purchasing and
maintaining his own liability insurance and, at his option, may
purchase and maintain such insurance as will protect him against
claims which may arise from operations under this Agreement .
FLR/aLCPDFaciL.Agr1 16
February 10, 1994
City Attorney
DRAFT
10.4 INSURANCE TO PROTECT PROJECT
10.4. 1 The Owner shall purchase and maintain property insurance
in a form acceptable to the Construction Manager upon the entire
Project for the full cost of replacement as of the time of any
loss . This insurance shall include as named insureds the Owner,
the Construction Manager, Trade Contractors and their Trade
Subcontractors and shall insure against loss from the perils of
Fire, Extended Coverage . l and shall include "All Risk" insurance
for physical loss or damage including without duplication of
coverage at least theft, vandalism, malicious mischief, transit,
collapse, flood, earthquake, testing, and damage resulting from a
defective design, workmanship or material . The Owner will increase
limits of coverage, if necessary, to reflect estimated replacement
cost. The Owner will be responsible for any co-insurance penalties
or deductibles . If the Project covers an addition to or is
adjacent to an existing building, the Construction Manager, Trade
Contractors and their Trade Subcontractors shall be named as x
additional insureds under the Owner' s Property Insurance covering
such building and its contents .
10.4. 1. 1 If the Owner finds it necessary to occupy or use a portio
or portions of the Project prior to Substantial Completion thereof,
such occupancy shall not commence prior to a time mutually agreed
to by the Owner and Construction Manager and to which the insurance
company or companies providing the property insurance have
consented by endorsement to the policy or policies . This insurance
shall not be canceled or lapsed on account of such partial
occupancy. Consent of the Construction Manager and of the
insurance company or companies to such occupancy or use shall not
be unreasonably withheld.
j
J
10.4.2 The Owner shall purchase and maintain such boiler and
machinery insurance as may be required or necessary. This s
insurance shall include the interests of the Owner, the
Construction Manager, Trade Contractors and their Trade
Subcontractors in the Work.
i
10.4. 3 The Owner shall purchase and maintain such insurance as
wil protect the Owner and Construction Manager against loss of use j
of Owner' s property due to those perils insured pursuant to
Subparagraph 10 . 4 . 1 . Such policy will provide coverage for
expediting expenses of materials, continuing overhead of the Owner
and Construction Manager, necessary labor expense including
overtime, loss of income by the Owner and other determined
exposures . Exposures of the Owner and the Construction Manager
shall be determined by mutual agreement and separate limits of
,coverage fixed for each item.
FLR/aLCPDFaciL.Agr] 1 7
February 10, 1994
� I
City Attorney
DRAFT
10.4 .4 The Owner shall file a copy of all policies with the
Construction Manager before an exposure to loss may occur. Copies
of any subsequent endorsements will be furnished to the
Construction Manager. The Construction Manager will be give sixty
( 60 ) days notice of cancellation, non-renewal, or new endorsements
restricting or reducing coverage. If the Owner does not intend to
purchase such insurance, he shall inform the Construction Manager i
in writing prior to the commencement of the Work. The Construction
Manager may then effect insurance which will protect the interest
of himself, the Trade Contractors and their Trade Subcontractors in
the Project, the cost of which shall be reimbursable pursuant to
Article 7 . If the Construction Manager is damaged by failure of
the Owner to purchase or maintain such insurance or to so notify
the Construction Manager, the Owner shall bear all reasonable costs
properly attributable thereto.
10.5 PROPERTY INSURANCE LOSS ADJUSTMENT
z
t
c
10.5. 1 Any insured loss shall be adjusted with the Owner and the
Construction Manager and made payable to the owner and Construction
Manager as trustees for the insureds, as their interests may
appear, subject to any applicable mortgagee clause.
10.5.2 Upon the occurrence of an insured loss, monies received
will be deposited in a separate account and the trustees shall make
distribution in accordance with the agreement of the parties in
interest, or in the absence of such agreement, in accordance with
an arbitration award pursuant to Article 14 . If the trustees are
unable to agree on the settlement of the loss, such dispute shall
also be submitted to arbitration pursuant to Article 14 .
i
10.6 WAIVER OF SUBROGATION }
z
t
10.6. 1 The Owner and Construction Manager waive all rights
against each other, the Architect/Engineer, Trade Contractors, and ?
their Trade Subcontractors for damages caused by perils covered by
insurance provided under Paragraph 10 . 4, except such rights as they
may have to the proceeds of such insurance held by the Owner and
Construction Manager as trustees . The Owner shall require similar
waivers from all Trade Contractors and their Trade Subcontractors .
10.6.2 The Owner and Construction Manager waive all rights
against each other and the Architect/Engineer, Trade Contractors
and their Trade Subcontractors for loss or damage to any equipment I
used in connection with the Project and covered by any property
insurance. The Owner shall require similar waivers from all Trade t
Contractors and their Trade Subcontractors .
10. 6.3 The Owner waives subrogation against the Construction
Manager, Architect/Engineer, Trade Contractors, and their Trade
Subcontractors on all property and consequential loss policies
FLR/aLCP0FaciL.Agr3 1 8
February 10, 1994
I �
City of San Bernardino Economic Development Ager F 'FT", _C17 ' CLEPF
DEVELOPMENT DEPARTMENT r ;31
February 18, 1994
TO: COMMUNITY DEVELOPMENT COMMISSION MEMBERS
FROM: Kenneth J. Henderson, Executive Director
CC's: Agency Administrator; City Clerk; City Attorney; File
SUBJECT: CENTRAL POLICE STATION - Construction Management
Contract
Agenda Item No. 11 for the Commission meeting on Monday, February
21, 1993, includes the Construction Management Contract for the
Central Police Station. The draft contract attached to the staff
report was in the process of revision and the report indicated a
revised draft would be distributed for review.
The attached contract is a final draft for your review and
consideration. It is also receiving final review from the City
Attorney's office and from Risk Management. If the Commission
approves the contract on Monday it will be executed in this form
together with any final changes approved by Agency Counsel and by
the Director of Risk Management.
Please do not hesitate to contact me if you need any information
or have questions.
KE T J. HE r DERSON, EXECUTIVE DIRECTOR Administrator
0218NWPD.CDC -4 ( (
AGREEMENT BETWEEN OWNER
AND CONSTRUCTION MANAGER
AGREEMENT
Made this day of in the year Nineteen Hundred
and Ninety-Four (1994) .
BETWEEN The Redevelopment Agency of the City of
San Bernardino
THE OWNER, AND
Millie and Severson, Incorporated
THE CONSTRUCTION MANAGER.
For services in connection with the following described Project:
San Bernardino Police Facility
The Architect for the Project is: Leach Mounce Architects
The Owner and the Construction Manager agree as set forth below:
[PDFacil.Agr]
February 18, 1994 1
ARTICLE 1
THE CONSTRUCTION TEAM AND EXTENT OF AGREEMENT
The CONSTRUCTION MANAGER accepts the relationship of trust and
confidence established between him and the Owner by this Agreement.
He covenants with the Owner to furnish his best skill and judgment
and to cooperate with the Architect in furthering the interests of
the Owner. He agrees to furnish efficient business administration
and superintendence and to use his best efforts to complete the
Project in the best and soundest way and in the most expeditious
and economical manner consistent with the interest of the Owner.
1. 1 THE CONSTRUCTION TEAM. The Construction Manager, the
Owner, and the Architect called the "Construction Team" shall work
from design through construction completion. The Construction
Manager shall provide leadership to the Construction Team on all
matters relating to construction.
1.2 EXTEND OF AGREEMENT. This Agreement represents the
entire agreement between the Owner and the Construction Manager and
supersedes all prior negotiations, representations or agreements.
When Drawings and Specifications are complete, they shall be
identified by amendment to this Agreement. This Agreement shall
not be superseded by any provisions of the documents for
construction and may be amended only by written instrument signed
by both Owner and Construction Manager.
1.3 DEFINITIONS
1.3. 1 The Project is the total construction to be managed under
this Agreement.
1.3.2 The Work is that part of the construction that a
particular Trade Contractor is to perform and such General
Condition Items that the Construction Manager performs with his own
forces.
1.3.3 General Condition Items as used herein shall be deemed to
mean provision of facilities or performance of work by the
Construction manager for items which do not lend themselves readily
to inclusion in one of the separate trade contracts. General
condition items may include miscellaneous minor construction work
when it is not feasible for the Owner to secure competitive bids or
proposals thereon. General Conditions may become part of Trade
Contractors work as provided elsewhere in the contract documents.
Exhibit A sets forth the general condition items within the scope
of this agreement.
[PDFacil.Agr]
February 18, 1994 2
ARTICLE 2
CONSTRUCTION MANAGER'S SERVICES
The Construction Manager will perform the following services
under this Agreement in each of the two phases described below.
2.1 DESIGN PHASE - It is acknowledged that Construction
Manager began providing services for the design phase on December
5, 1993 . Design phase ends at the award of trade contract (except
in demolition and grading) .
2 .1.1 CONSULTATION DURING PROJECT DEVELOPMENT. Schedule and
attend regular meetings with the Architect during the development
of design to advise on selection of materials, building systems and
equipment. Provide recommendations on construction feasibility,
availability of materials and labor, time requirements for
installation and construction, and factors related to cost
including costs of alternative designs or materials, preliminary
budgets, and possible economies.
2 .1.2 SCHEDULING. Develop a Project Schedule that coordinates
and integrates the Architect's design efforts and the Owner's
activities with construction schedules. Update the Project
Schedule incorporating a detailed schedule for all activities of
the project, including realistic activity sequences and durations,
allocation of labor and materials, processing of shop drawings and
samples, and delivery of products requiring long lead-time
procurement. Include the Owner's occupancy requirements showing
portions of the Project having occupancy priority.
2.1.3 PROJECT CONSTRUCTION BUDGET. Update and refine the
project budget estimate prepared by the Koll Company for Owner' s
approval as the development of the Drawings and Specifications
proceeds, and advise the Owner and the Architect if it appears that
the Project Construction Budget will not be met and make
recommendations for corrective action.
2 . 1.4 COORDINATION OF CONTRACT DOCUMENTS. Review the Drawings
and Specifications as they are being prepared, recommending
alternative solutions whenever design details affect construction
feasibility or schedules without, however, assuming any of the
Architect' s responsibilities for design.
2 . 1.5 CONSTRUCTION PLANNING. Recommend for purchase by the
Owner and expedite the procurement of long-lead items to ensure
their delivery by the required dates.
[PDFacil.Agr]
February 18, 1994 3
2 .1.5.1 Make recommendations to the Owner and the Architect
regarding the division of Work in the Drawings and Specifications
to facilitate the bidding and awarding of Trade Contracts, allowing
for phased construction taking into consideration such factors as
time of performance, availability of labor, overlapping trade
jurisdictions, and provisions for temporary facilities.
2.1.5.2 Review the Drawings and Specifications with the Architect
to eliminate areas of conflict and overlapping in the Work to be
performed by the various Trade Contractors. Develop bid
specifications and review and advise on all bid documents and
procedures.
2. 1.5.3 Develop Trade Contractor interest in the Project and as
working Drawings and Specifications are completed, assist the Owner
in taking competitive bids on the Work of the various Trade
Contractors. After analyzing the bids, recommend to the Owner that
such contracts be awarded.
2. 1.6 EQUAL EMPLOYMENT OPPORTUNITY. Determine applicable
requirements for equal employment opportunity programs for
inclusion in Project bidding documents, by coordinating with Owner
(City) personnel.
2 .2 CONSTRUCTION PHASE - The Construction phase begins at
awarding of trade contracts (other than demolition and rough
grading) .
2.2. 1 PROJECT CONTROL. Monitor the Work of the Trade
Contractors and coordinate the Work with the activities and
responsibilities of the Owner, Architect and Construction Manager
to complete the Project in accordance with the Owner's objectives
of cost, time and quality.
2.2.1.1 Maintain a competent full-time Superintendent at the
Project site to coordinate and provide general direction of the
Work and progress of the Trade Contractors on the Project.
2.2 . 1.2 Establish on-site organization and lines of authority in
order to carry out the overall plans of the Construction Team.
2.2. 1.3 Establish procedures for coordination among the Owner,
Architect, Trade Contractors and Construction Manager with respect
to all aspects of the Project and implement such procedures.
2 .2 . 1.4 Schedule and conduct progress meetings at which Trade
Contractors, Owner, Architect and Construction Manager can discuss
jointly such matters as procedures, progress, problems and
scheduling.
[PDFacil.Agr]
February 18, 1994 4
2 .2 .1.5 Provide regular monitoring of the Project Schedule as
construction progresses. Identify potential variances between
scheduled and probable completion dates. Review schedule for Work
not started or incomplete and recommend to the Owner and Trade
Contractors adjustments in the schedule to meet the probable
complete date. Provide summary reports of each monitoring and
document all changes in schedule.
2 .2.1. 6 Determine the adequacy of the Trade Contractors'
personnel and equipment and the availability of materials and
supplies to meet the schedule. Recommend courses of action to the
Owner when requirements of a Trade Contract are not being met.
2.2 .2 PROVISIONS OF FACILITIES. Provide all supervision,
labor, materials, construction equipment, tool and subcontract
items which are necessary for the completion of the General
Condition items which are set forth in Exhibit "A".
2.2.3 COST CONTROL. Develop and monitor an effective system of
Project cost control. Revise and refine the initially approved
Project Construction Budget, incorporate approved changes as they
occur, develop cash flow reports and forecasts as needed, and
identify variances between actual and budgeted or estimated costs
and advise the Owner and Architect whenever projected cost exceeds
budgets or estimates.
2.2 .3. 1 Maintain cost accounting records on authorized Work
performed under unit costs, actual costs for labor and materials,
or other basis requiring accounting records. Afford the Owner
access to these records and preserve them for a period of three (3)
years after final payment.
2.2 .4 CHANGE ORDER. Develop and implement a system for the
preparation, review and processing of Change Orders. Recommend
necessary or desirable changes to the Owner and the Architect,
receive requests for changes, assemble the required information and
documentation, submit recommendations to the Owner and the
Architect, and assist in negotiating Change Orders.
2.2.5 PAYMENTS TO TRADE CONTRACTORS. Develop and implement a
procedure for the review, approval, processing and payment of
applications by Trade Contractors for progress and final payments.
2 .2.6 PERMITS AND FEES. Assist the Owner and Architect in
obtaining all building permits and special permits for permanent
improvements, excluding any permits required to be obtained by the
various Trade Contractors, such as permits for inspection,
temporary facilities, etc. Assist in obtaining approvals from all
the authorities having jurisdiction.
[PDFacil.Agr]
February 18, 1994 5
2.2.7 OWNERIS CONSULTANTS. If required, assist the Owner in
selecting and retaining professional services of a surveyor,
testing laboratories and special consultants, and coordinate these
services.
2.2.8 REVIEW OF WORK AND SAFETY. Review the Work of Trade
Contractors for defects and deficiencies in the Work without
assuming any of the Architect' s legal responsibilities for design
and inspection. Review the safety programs of each of the Trade
Contractors and make appropriate recommendations. In making such
reviews, he shall not be required to make exhaustive or continuous
inspections to check quality of work, safety precautions and
programs in connection with the Project. The performance of such
services by the Construction Manager shall not relieve the Trade
Contractors of their responsibilities for performance of the work
and for the safety of persons and property, and for compliance with
all federal, state and local statutes, rules, regulations and
orders applicable to the conduct of the Work.
2.2.9 DOCUMENT INTERPRETATION. Refer all questions for
interpretation of the documents prepared by the Architect to the
Architect.
2 .2 . 10 SHOP DRAWINGS AND SAMPLES. In collaboration with the
Architect, establish and implement procedures for expediting the
processing and approval of shop drawings and samples.
2 .2. 11 REPORTS AND PROJECT SITE DOCUMENTS. Record the progress
of the Project. Submit written progress reports to the Owner and
the Architect including information on the Trade Contractors' Work,
and the percentage of completion. Keep a daily log available to
the Owner and the Architect.
2 .2 . 11. 1 Maintain at the Project site, on a current basis:
records of all necessary Contracts, Drawings, samples, purchases,
materials, equipment, maintenance and operating manuals and
instructions, and other construction related documents, including
all revisions. Obtain data from Trade Contractors and maintain a
current set of record Drawings, Specifications and operating
manuals. At the completion of the Project, deliver all such
records to the Owner.
2 .2.12 SUBSTANTIAL COMPLETION. Determine Substantial Completion
of Work or designated portions thereof and prepare for the
Architect a list of incomplete or unsatisfactory items and a
schedule for their completion.
2.2 .13 START-UP. With the Owner's maintenance personnel, direct
the check out of utilities, operations systems and equipment for
[PDFacil.Agr]
February 18, 1994 6
readiness and assist in their initial start-up and testing by the
Trade Contractors.
2.2 .14 FINAL COMPLETION. Determine final completion and provide
written notice to the Owner and Architect that the Work is ready
for final inspection. Secure and transmit to the Architect
required guarantees, affidavits, releases, bonds and waivers. Turn
over to the Owner all keys, manuals, record drawings and
maintenance stocks.
2 .2.15 WARRANTY. The Construction Manager shall collect and
deliver to the Owner any specific written warranties or guarantees
given by others, including all required Trade Contractor guarantees
and warranties.
2 .3 ADDITIONAL SERVICES
At the request of the Owner, the Construction Manager will provide
the following additional services upon written agreement between
the Owner and Construction Manager defining the extent of such
additional services and the amount and manner in which the
Construction Manager will be compensated for such additional
services.
2.3.1 Services related to investigation, appraisals or
valuations of existing conditions, facilities or equipment, or
verifying the accuracy of existing drawings or other Owner-
furnished information.
2 .3.2 Services related to Owner-furnished equipment, furniture
and furnishings which are not a part of the Work.
2.3.3 Services related to construction performed by the Owner.
2.3.4 Consultation on replacement of Work damaged by fire or
other cause during construction, and furnishing services for the
replacement of such Work.
2 .3.5 Services made necessary by the default of a Trade
Contractor.
2.3. 6 Preparing to serve or serving as an expert witness in
connection with any public hearing, arbitration proceeding, or
legal proceeding.
2 .3.7 Services related to Work performed by the Construction
Manager other than General Conditions items as set forth in Exhibit
nA".
2 .3.8 Inspections of and services related to the Project after
completion of the services under this Agreement.
[PDFacil.Agr]
February 18, 1994 7
2 .3.9 Providing any other service not otherwise included in
this Agreement.
ARTICLE 3
OWNER'S RESPONSIBILITIES
3.1 The Owner shall provide full information regarding the
requirements for the Project.
3.2 The Owner shall designate a representative who shall be
fully acquainted with the Project and has authority to approve
Project Construction Budgets, Changes in the Project, render
decisions promptly consistent with Project Schedule and furnish
information expeditiously.
3.3 The Owner shall retain an Architect for design and to
prepare construction documents for the Project. The Architect' s
services, duties and responsibilities are described in the
Agreement between the Owner and the Architect, a copy of which will
be furnished to the Construction Manger.
3.4 The Owner shall furnish for the site of the Project all
necessary surveys describing the physical characteristics, soil
reports and subsurface investigations, legal limitations, utility
locations, and a legal description.
3.5 The Owner shall secure and pay for necessary approvals,
easements, assessments and charges required for the construction,
use or occupancy of permanent structures or for permanent changes
in existing facilities.
3.6 The Owner shall furnish such legal services as may be
necessary for providing the items set forth in Paragraph 3 .5, and
such auditing services as he may require.
3.7 The Construction Manager will be furnished without charge
all copies of Drawings and Specifications reasonably necessary for
the execution of the Work.
3.8 The Owner shall provide the insurance for the Project as
provided in Paragraph 10. 4, and shall bear the cost of any bonds
required.
3.9 The services, information, surveys and reports required
by the above paragraphs shall be furnished with reasonable
promptness at the Owner's expense, and the Construction Manager
shall be entitled to rely upon the accuracy and completeness
thereof.
[PDFacil.Agr)
February 18, 1994 8
3. 10 If the Owner becomes aware of any fault or defect in the
Project or non-conformance with the Drawings and Specifications, he
shall give prompt written notice thereof to the Construction
Manager.
3.11 The Owner shall furnish reasonable evidence satisfactory
to the Construction Manager that sufficient funds are available and
committed for the entire cost of the Project. Unless such
reasonable evidence is furnished, the Construction Manager is not
required to commence any Work, or may, if such evidence is not
presented within a reasonable time, stop the Project upon fifteen
(15) days notice to the Owner.
3.12 The Owner shall communicate with the Trade Contractors
only through the Construction Manager.
3.13 Owner shall make provision within its trade contracts
giving authority to Construction Manager to direct, coordinate, and
determine the sequence of the work of Trade Contractors, and
requiring the Trade Contractor to provide to the Construction
Manager all documentation, deemed necessary by the Construction
Manager for the proper management and administration of the work,
required by this agreement, or the Trade Contract.
ARTICLE 4
TRADE CONTRACTS
4. 1 All portions of the Project other than General Condition
Items (set forth in Exhibit "A") shall be performed under Trade
Contracts including contracts for general construction work with
several construction trades. The Construction Manager shall
develop bid specifications and assist the Owner in requesting and
receiving bids from Trade Contractors and Trade Contracts will be
awarded by the Owner after the bids are reviewed by the Architect,
Construction Manager and Owner. Contracts will be awarded to the
lowest responsible bidder in accordance with Owner's policies and
procedures.
4.2 Trade Contracts will be between the Owner and the Trade
Contractors. The form of the Trade Contracts including the General
and Supplementary Conditions shall be developed jointly with the
Owner and Construction Manager. However, final decision for the
form of the Trade Contracts shall rest with the Owner.
[PDFacil.Agr]
February 18, 1994 9
ARTICLE 5
PROJECT SCHEDULE
5.1 The services to be provided under this Contract shall be
in general accordance with the following schedule:
a. Design phase 2 months;
b. Construction phase 9 months;
C. To the extent that the design phase exceeds 2
months or the date of Substantial Completion is
longer than nine months from the commencement of
construction phase, the Construction Manager is
entitled to additional compensation as set forth in
Subparagraphs 6.2 . 1 and 7. 1. 2 .
5.2 At the time work commences, a Date of Substantial
Completion of the Project shall also be established.
5.3 The Date of Substantial Completion of the Project or a
designated portion thereof is the date when construction is
sufficiently complete in accordance with the Drawings and
Specifications so the Owner can occupy or utilize the Project or
designated portion thereof for the use for which it is intended.
Warranties called for by this Agreement or by the Drawings and
Specifications shall commence on the Date of Substantial Completion
of the Project or designated portion thereof.
ARTICLE 6
CONSTRUCTION MANAGER'S FEE
6.1 In consideration of the performance of the Contract, the
Owner agrees to pay the Construction Manager in current funds as
compensation for his services a Construction Manager's Fee as set
forth in Subparagraphs 6. 1. 1 and 6. 1.2 .
6.1.1 For the performance of the Design services, a fee of
$25, 000. 00, which shall be paid monthly, in equal proportions,
based on the scheduled Design Phase time.
6.1.2 For work or services performed during the Construction
Phase, a fee of $155, 000 which shall be paid proportionately to the
ratio the monthly payment for the Cost of the Project bears to the
estimated cost. Any balance of this fee shall be paid at the time
of final payment.
6.2 Adjustments in Fee shall be made as follows:
[PDFacil.Agr]
February 18, 1994 10
6.2.1 The Construction Manager's Fee shall be adjusted by two
and one-half percent (2 1/2%) of the additional cost of the work
for increases in the scope of the Project. Therefore, in the event
that the aggregate Trade Contracts exceed $7,225, 000, the
Construction Manager shall receive as an adjustment to its fee, an
amount of two and one-half percent (2 .5%) of such excess.
6.3 Included in the Construction Manager' s Fee are the
following:
6.3.1 Salaries or other compensation of the Construction
Manager's employees at the principal office and branch offices,
except employees listed in Subparagraph 7.2 . 2 .
6.3.2 General operating expenses of the Construction Manager' s
principal and branch offices other than the field office.
6.3.3 Any part of the Construction Manager's capital expenses,
including interest on the Construction Manager' s capital employed
for the Project.
6.3.4 Overhead or general expenses of any kind, except as may
be expressly included in Article 7.
ARTICLE 7
REIMBURSABLE COSTS
7.1 The Owner agrees to pay the Construction Manager for the
reimbursable costs he incurs as defined in Paragraph 7 .2 . Such
payment shall be in addition to the Construction Manager's Fee
stipulated in Article 6.
7 . 1.1 Reimbursable costs shall only include costs for General
Conditions, as more fully described in Exhibit "A", Personnel Fee,
Insurance costs, or costs for work which has been added by Change
Order.
7 . 1.2 The aggregate amounts for all Reimbursable Costs shall
not exceed the following totals except as otherwise provided in
this Agreement:
a. Reimbursable Costs during the Design Phase shall not
exceed a maximum of $15, 000 except that such maximum
shall be adjusted by adding a maximum of $7,500 for each
month in excess of two (2) months for the Design Phase
(the Design Phase shall be deemed to have started on
December 5, 1993 for the purpose of said adjustment) .
[PDFacil.Agr]
February 18, 1994 1 1
b. Reimbursable Costs during the Construction Phase shall
not exceed a maximum of $175, 2000 except that such
maximum shall be adjusted by adding a maximum of $19,500
for each month in excess of nine (9) months for the
Construction Phase.
For the purposes of determing the above maximum amounts, partial
months shall be prorated based upon a 30 day month. Any
Reimbursable Costs in excess of the adjusted maximums described
above must be specifically authorized by written Change Order as
provided in Article 8.
7 .1.3 The cost items listed in Article 7.2 represent allowable
cost, and are not a representative listing of the items to be
provided by Construction Manager. Cost items provided by
Construction Manager are set forth in Exhibit "A". Any other items
for which costs are incurred are to be added by Change Order.
7 .2 REIMBURSABLE COST ITEMS
7.2 .1 Wages paid for labor in the direct employ of the
Construction Manager in the performance of General Condition Items
under applicable collective bargaining agreements, or under a '
salary or wage schedule agreed upon by the Owner and Construction
Manager, and including such welfare or other benefits, if any, as
may be payable with respect thereto.
7.2 .2 Salaries of the Construction Manager' s employees when
stationed at the field office, in whatever capacity employed,
employees engaged on the road in expediting the production or
transportation of materials and equipment, and employees in the
main or branch office performing the functions listed below:
Scheduling
Project Management/Administration
Document Preparation
Warehousing/Transportation
Expediting
Estimating/Plan Review/Budgeting
7.2 .3 Costs of all employee benefits and taxes for such items
as unemployment compensation and social security, insofar as such
cost is based on wages, salaries, or other remuneration paid to
employees of the Construction Manager referred to in Subparagraphs
7.2 . 1 and 7 .2 .2 .
7 .2.4 The proportion of reasonable transportation, traveling,
moving, and hotel expenses of the construction Manager or of his
officers or employees incurred in discharge of duties connected
with the Project.
[PDFacil.Agr]
February 18, 1994 12
7 .2.5 Cost including rental of all materials, supplies and
equipment required to perform General Condition Items, including
costs of transportation, storage and maintenance thereof.
7.2 .6 Cost of the premiums for all insurance which the
Construction Manager is required to procure by this Agreement or is
deemed necessary by the Construction Manager.
7.2.7 Sales, use, gross receipts or similar taxes related to
the Project imposed by any governmental authority, and for which
the Construction Manager is liable.
7 .2.8 Permit fees, licenses, tests, royalties, damages for
infringement of patents and costs of defending suits therefor, and
deposits lost for causes other than the Construction Manager' s
negligence. If royalties or losses and damages, including costs of
defense, are incurred which arise from a particular design,
process, or the product of a particular manufacturer or
manufacturers specified by the Owner or Architect/Engineer, and the
Construction Manager has no reason to believe there will be
infringement of patent rights, such royalties, losses and damages
shall be paid by the Owner.
7 .2 .9 Losses, expenses or damages to the extent not compensated
by insurance otherwise (including settlement made with the written
approval of the owner) .
7.2 .10 Minor expenses such as telegrams, long=distance telephone
calls, telephone service at the site, expressage, and similar petty
cash items in connection with the Project.
7.2 . 11 Cost of removal of all debris.
7.2. 12 Cost incurred due to an emergency affecting the safety of
persons and property.
7.2.13 Cost of data processing services required in the
performance of the services outlined in Article 2 .
7.2. 14 Legal costs reasonably and properly resulting from
prosecution of the Project for the Owner.
7.2 . 15 All costs directly incurred in the performance of the
Project and not included in the Construction Manager's Fee as set
forth in paragraph 6. 3 .
ARTICLE 8
CHANGES IN THE PROJECT
[PDFacil.Agr]
February 18, 1994 13
8.1 The Owner, without invalidating this Agreement, may order
Changes in the Project within the general scope of this Agreement
consisting of additions, deletions or other revisions. All such
Changes in the Project shall be authorized by Change Order.
8.2 A Change Order is written order to the Construction
Manager signed by the Owner or his authorized agent issued after
the execution of this Agreement, authorizing a change in the scope
of the Project or services to be provided.
PAYMENTS TO THE CONSTRUCTION MANAGER
9.1 The Construction Manager shall submit monthly to the
Owner a statement, sworn to, if required, showing in detail all
Reimbursable Costs incurred during the previous month, all amounts
due Trade Contractors, and the amount of the Construction Manager's
Fee due as provided in Article 6. Payment by the Owner to the
Construction Manager of his statement amount shall be made within
fifteen (15) days after it is received in writing.
9.2 Final payment constituting the unpaid balance of
Reimbursable Costs and the Construction Manager' s Fee shall be due
and payable when the Project is delivered to the Owner, ready for
beneficial occupancy, or when the Owner occupies the Project,
whichever event first occurs, provided that the project be then
substantially completed and this Agreement substantially performed.
9.3 If the Owner should fail to pay the Construction Manager
within ten (10) days after the time the payment of any amount
becomes due, then the Construction Manager may, upon seven (7)
additional days' written notice seek a hearing before the Owner' s
governing body (EDA Commission) to resolve the dispute. Should a
resolution not be reached, the disputed amount shall be placed in
an escrow account until such time the dispute is resolved, or upon
completion of the project, the Construction Manager may seek a
judicial remedy.
9.4 Payments due but unpaid shall bear interest at the rate
the Owner is paying on his construction loan or at the legal rate,
whichever is higher.
ARTICLE 10
INSURANCE, INDEMNITY AND WAIVER OF SUBROGATION
10.1 INDEMNITY
10. 1. 1 The Construction Manager agrees to indemnify and hold the
Owner harmless from all claims for bodily injury and property
[PDFacil.Agr]
February 18, 1994 14
damage (other than the work itself and other property insured under
Paragraph 10.4) that may arise from the Construction Manager' s
operations under this Agreement.
10.1.2 The Owner shall cause all Trade Contractors to agree to
indemnify the Owner and the Construction Manager and hold them
harmless from all claims for bodily injury and property damage
(other than property insured under Paragraph 10.4) that may arise
from that contractor's operations Such provisions shall be in a
form satisfactory to the Construction Manager.
10.2 CONSTRUCTION MANAGER'S LIABILITY INSURANCE
10.2.1 The Construction Manager shall purchase and name the
Redevelopment Agency for the city of San Bernardino as additional
insured under their Comprehensive General Liability Policy. Policy
Limits shall not be less than $1, 000, 000 per occurrence, $2, 000, 000
Aggregate, and shall include coverage for completed operations, and
premises operations including explosion, collapse, and underground
coverage, elevators, and blanket contractual.
10.2.2 Construction Manager shall also maintain Workers '
Compensation Insurance for all employees working on the project.
10.2.3 Construction Manager shall purchase Comprehensive Auto
Liability in the amount of $1, 000, 000 Combined Single Limits. A
Certificate of Insurance naming the Redevelopment Agency for the
City of San Bernardino shall be required.
10.2.4 All policies shall be written on an occurrence basis. If
a Claims Made policy is issued, the Construction Manager shall
present evidence to the Project Owner, a policy of insurance for a
period of five (5) years from completion of the project, naming the
Owner as an Additional Insured as their interests may appear.
10.3 OWNER'S LIABILITY INSURANCE
10.3.1 The Owner is self insured for the first $1, 000, 000 as
part of the City of San Bernardino's Liability Program, with Excess
Coverage to $25, 000, 000.
10.4 INSURANCE TO PROTECT PROJECT
10.4.1 The Owner has coverage for the project under the City of
San Bernardino's Master Property Policy, and can provide
Certificates of Insurance for the Construction Manager.
10.4.2 The Owner shall file a copy of all policies with the
Construction Manager before an exposure to loss may occur. Copies
of any subsequent endorsements will be furnished to the
Construction Manager. The Construction Manager will be given sixty
[PDFacil.Agr]
February 18, 1994 15
(60) days notice of cancellation, non-renewal, or new endorsements
restricting or reducing coverage. If the Owner does not intend to
purchase such insurance, he shall inform the Construction Manager
in writing prior to the commencement of the Work. The Construction
Manager may then effect insurance which will protect the interest
of himself, the Trade Contractors and their Trade Subcontractors in
the Project, the cost of which shall be reimbursable pursuant to
Articles 7 and 8. If the Construction Manager is damaged by
failure of the Owner to purchase or maintain such insurance or to
so notify the Construction Manager or if such insurance is
unavailable, the Owner shall bear all reasonable costs properly
attributable thereto.
10.5 PROPERTY INSURANCE LOSS ADJUSTMENT
10.5.1 Any insured loss shall be adjusted with the Owner and the
Construction Manager and made payable to the owner and Construction
Manager as trustees for the insureds, as their interests may
appear, subject to any applicable mortgagee clause.
10.5.2 Upon the occurrence of an insured loss, monies received
will be deposited in a separate account and the trustees shall make
distribution in accordance with the agreement of the parties in
interest, or in the absence of such agreement, in accordance with
an arbitration award pursuant to Article 14. If the trustees are
unable to agree on the settlement of the loss, such dispute shall
also be submitted to arbitration pursuant to Article 14.
ARTICLE 11
TERMINATION OF THE AGREEMENT AND OWNER'S
RIGHT TO PERFORM CONSTRUCTION MANAGER'S
OBLIGATIONS
11.1 TERMINATION BY THE CONSTRUCTION MANAGER
11.1.1 If the Project is stopped for a period of thirty (30)
days under an order of any court or other public authority having
jurisdiction, or as a result of an act of government, such as a
declaration of a national emergency making materials unavailable,
through no act or fault of the Construction Manager, then the
Construction Manager may, upon seven (7) days ' written notice to
the Owner and the Architect, terminate this Agreement and recover
from the Owner payment for all work executed, the Construction
Manger's Fee earned to date, and for any proven loss sustained upon
any materials, equipment, tools, construction equipment and
machinery, including reasonable profit and damages.
11.2 OWNER'S RIGHT TO PERFORM CONSTRUCTION MANAGER'S
OBLIGATIONS AND TERMINATION BY THE OWNER FOR CAUSE
[PDFacil.Agr]
February 18, 1994 16
11.2.1 If the Construction manager fails to perform any of his
obligations under this Agreement, the Owner may, after seven (7)
days' written notice during which period the Construction Manager
fails to perform such obligation, make good such deficiencies.
11.2.2 If the Construction Manager is adjudged a bankrupt, or if
he makes a general assignment for the benefit of his creditors, or
if a receiver is appointed on account of his insolvency, or
persistently disregards laws, ordinances, rules, regulations or
orders of any public authority having jurisdiction, or otherwise is
guilty of a substantial violation of a provision of the Agreement,
then the Owner may, without prejudice to any right or remedy and
after giving the Construction Manager and his surety, if any, seven
(7) days' notice, during which period Construction Manager fails to
cure the violation, terminate the employment of the Construction
Manager and take possession of the site and of all materials,
equipment, tools, construction equipment and machinery thereon
owned by the Construction Manager and may finish the Project by
whatever method he may deem expedient. In such case, the
Construction manager shall not be entitled to receive any further
payment until the Project is finished nor shall he be relieved from
his obligation assumed under Article 6.
11.3 TERMINATION BY OWNER WITHOUT CAUSE
11.3.1 If the Owner terminates this Agreement other than
pursuant to Subparagraph 11.2 .2 or Subparagraph 11. 3 . 211 he shall
reimburse the Construction Manager for any unpaid Reimbursable cost
of the Project due him under Article 7, plus (1) the unpaid balance
of the Fee computed upon the Reimbursable Costs and payments due
Trade Contractors to the date of termination at the rate of the
percentage named in Subparagraph 6.2 . 1 or (2) if the Construction
Manager's Fee be stated as a fixed sum, such an amount as will
increase the payment on account of his fee to a sum which bears the
same ratio to the said fixed sum as the Reimbursable Costs and
payments due Trade Contractors at the time of termination bears to
a reasonable estimated Project Construction Budget when completed.
The Owner shall also pay to the Construction Manager fair
compensation, either by purchase or rental at the election of the
Owner, for any equipment retained. In case of such termination of
the Agreement the Owner shall further assume and become liable for
obligations, commitments and unsettled claims that the Construction
Manager has previously undertaken or incurred in good faith in
connection with said Project. The Construction Manager shall, as
a condition of receiving the payments referred to in this Article
11, execute and deliver all such papers and take all such steps,
including the legal assignment of his contractual rights, as the
Owner may require for the purpose of fully vesting in him the
[PDFacil.Agr]
February 18, 1994 17
rights and benefits of the Construction Manager under such
obligations or commitments.
11.3.2 After the completion of the Design Phase, if the final
cost estimates make the Project no longer feasible from the
standpoint of the Owner, the Owner may terminate this Agreement and
pay the Construction Manager his Fee in accordance with
Subparagraph 6. 1. 1 plus any costs incurred pursuant to Article 7.
ARTICLE 12
ASSIGNMENT AND GOVERNING LAW
12.1 Neither the Owner nor the Construction Manager shall
assign his interest in this Agreement without the written consent
of the other except as to the assignment of proceeds.
12.2 This Agreement shall be governed by the law of the place
where the Project is located.
ARTICLE 13
ARBITRATION
13.1 The Owner or the Construction Manager may agree to
arbitrate any claims, disputes, or other matters in question
arising out of or relating to this agreement. Such arbitration
shall not be final or binding unless so agreed to in writing by the
parties.
This Agreement executed the day and year first written above.
Approved as to legal OWNER:
form and content:
The Redevelopment Agency
of the City of San Bernardino
By:
Agency Counsel
By:
Executive Director
Approved as to program:
CONSTRUCTION MANAGER:
By: Millie and Severson, Incorporated
Deputy Director
By:
President
[PDFacil.Agr]
February 18, 1994 18
EXHIBIT "All
GENERAL CONDITIONS ITEMS TO BE
PROVIDED BY CONSTRUCTION MANAGER
1. Included in the General Conditions Cost to be provided under
the agreement are:
a. Storm control (exclusive of erosion control plan work) ;
b. Telephone and facsimile;
C. Office supplies;
d. General hauling;
e. Safety;
f. Dust Control-general;
g. Storage shed.
2 . Excluded are:
a. Plans/Document reproduction;
b. Temporary power facilities in electrical;
C. Permits and Bond;
d. Continuous Clean-up
e. Disposal, haul away, and dump fees;
f. Dust/Erosion Control Plan by (earthwork subcontractor) ;
g. Facilities for Agency personnel;
h. Temporary water meter (to be provided by Trade Plumber) ;
i. Layout/Survey/Inspection/Testing;
j . Cost of weekly power usage;
k. Temporary water;
1. Site fencing.
[PDFacil.Agr]
February 18, 1994 19