REQUEST FOR COMMISSION/COUNCIL ACTION
From: Roger G. Hardgrave, Dir. Subject: Approval of Plans &
of Public Works/City Engr. Authorizaton to Ad-
vertise for Bids -
Replacement of Rest-
Date: July 30 , 1996 room Buildings in
Meadowbrook Park &
Nunez Park, per Plan
No. 9521
------------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action:
June, 1995 -- Allocation of $143 , 200 (for Meadowbrook Park) and
$144 ,000 (for Nunez Park) , in 1995/96 CDBG Program
approved.
-----------------------------------------------------------------
Recommended Motion:
That the plans for the replacement of restroom buildings in
Meadowbrook Park and Nunez Park, in accordance with Plan No.
9521 , be approved; and the Director of Public Works/City Engineer
be authorized to advertise for bids.
cc : R. Winkler Roger G. Har - ave, Di r. of P.W. /C.E.
A. Ramos
Timothy Ste nh us, Agency Administrator
-----------------------------------------------------------------
Contact Person: Roger G. Hardgrave Phone: 5025
Project Area: N/A Ward(s) : 1 & 3
Supporting Data Attached: Staff Report
1995/96 CDBG
FUNDING REQUIREMENTS: Amount: $ 281 , 000 Source: Program
Accts #860-7002 &
Budget Authority: 860-5003
-----------------------------------------------------------------
Commission/Council Notes:
Agenda Item No. : 11
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Approval of Plans and
Authorization to Advertise for Bids
Replacement of Restroom Buildings
in Meadowbrook Park and Nunez Park
Plans for replacement of restroom buildings in Meadowbrook Park
and Nunez Park have been prepared, and the project is ready to be
advertised for bids . The project consists , in general , of
removing the existing restroom buildings, and constructing new
structures that are in compliance with current handicap
standards .
Below is an estimate of the total project cost:
Meadowbrook Nunez
Park Park Total
Construction Contract $ 122 , 250 $ 121 , 000 $ 243 , 250
Engineering & Inspec-
tion (W.O. #5011 & 5012) 12 , 100 12 , 100 24 , 200
Sub-Totals $ 134 , 350 $ 133 , 100 $ 267 , 450
Contingencies (50) ± 6 , 650 6 ,900 13 , 550
TOTAL ESTIMATED COST ----- $ 141 , 000 $ 140 , 000 $ 281 , 000
Funds have been allocated in the 1995/96 CDBG Program, as set
forth below, to finance the costs that will be incurred for these
projects .
Location Account No. Amount
Meadowbrook Park 860-7002 $ 143 , 200
Nunez Park 860-5003 144 , 000
Total Available Funds ------ $ 287 , 200
We recommend that the plans be approved and authorization granted
to advertise for bids .
7-30-96