HomeMy WebLinkAboutS2- Public Works CITY OF SAN EERV ALRDINO REQUEST F"OR COUNCIL ACTION
Fill No. 19.10
ROGER G. HARDCRr.�,'F Approval of Additional Expenditure
From: Subject: of $13 , 000 for Rubberized Cross-
Public Works ing Materials -- Rialto Avenue
Dept: Grade Crossing, West of Mt. Vernon
Date:
3-13-95 Avenue
Synopsis of Previous Council action:
June, 1994 -- Allocation of $105 , 000 , in 1994/95 Traffic Systems
Fee Budget, approved.
01-23-95 -- Expenditure of $30 , 000 approved, plans approved, and
authorization granted to advertise for bids .
DMIF . i, F'rrCEI
Recommended motion:
That the amount authorized for improvement of the Rialto Avenue
Grade crossing, west of Mt. Vernon Avenue, under Account No. 250-
670-57477 , be increased from $30 , 000 to $37 , 400 , to provide
sufficient funds to finance the additional payment of $13 ,000 to
Santa Fe Railway Co. for installation of rubberized crossing
materials in lieu of timber planks.
cc: Shauna Clark
Barbara Pachon
ignatu re
Contact person: -Roger G. Hardqrave Phone: 5025
Supporting data attached: Staf f Report Ward: 3
FUNDING REQUIREMENTS: Amount: $7400 (Traffic Systems Fee Fund)
3-7D - 5504- 1`I tt2
Source: (Acct. No.) 250-&' g ` 4-7:
(Acct. Description) Minor . Improvements �Various
Locations FinanceX-4: " �-
Council Notes: Not listed in CIP.
e
75.0262 Agenda Item No.
CITY OF SAN BERT iRDINO - REQUEST L JR COUNCIL ACTION
STAFF REPORT
Approval was given, at the Council meeting of 1-23-95 ,
for the expenditure of $30 , 000 to finance the improvement of the
Rialto Avenue grade crossing, west of Mt. Vernon Avenue. This
improvement was to consist of the railway tracks being lowered
0 . 5 feet by Santa Fe forces, and the adjoining asphalt concrete
pavement being removed and replaced to match the new grade by the
City ' s contractor.
A contract has been awarded by the City Administrator for
the low bid price of $20 , 940 .
Below is an estimate of the total project cost:
Construction Contract $ 20 , 940
Contingencies (15%) ± 3 , 460
TOTAL ESTIMATED PROJECT COST $ 24 ,400
Santa Fe has proposed that rubberized crossing material
be installed, in lieu of timber planks, due to the improved
riding quality. Rubberized crossing material normally costs
about $260 per linear foot. However, due to the large quantity
on hand for the Metrolink project, Bob Brendza has advised that
the material can be acquired for $160 per linear foot, which
equates to about $13 , 000 .
There is an available balance of $5 ,600 in the original
allocation of $30 ,000 . Supplemental funds in the amount of
$7 , 400 will be needed to fully finance the additional cost of in-
stalling rubberized crossing material.
We recommend that the approved expenditure for this
project be increased from $30 , 000 to $37 ,400 , in order to have
rubberized crossing material installed.
URGENCY CLAUSE:
Santa Fe is scheduled to lower the tracks on 3-20-95 . Therefore,
a decision on this additional expenditure must be confirmed on
this date.
3-13-95