HomeMy WebLinkAbout13- Public Works CITY OF SAN BERN' -NDINO - REQUEST FC 7 COUNCIL ACTION
File Iv.,. 1.856
Award of Contract - Construction
From: ROGER G. HARDGRAVE Subject: of Street Improvements in Pepper
Avenue (West Side) , South of Mill
Dept: Public Works Street, per Plan No. 9176 --
RVC ROADWAY CONSTRUCTION, INC.
Date: 12-13-94
Synopsis of Previous Council action:
June, 1994 - Allocation of $150 , 000 , in 1994/95 Gas Tax Budget,
approved.
11-07-94 -- Plans approved and authorization granted to advertise
D,aie' . " 4!CF,; for bids . Transfer of $15 , 000 also approved.
GEC 9L
Recommended motion:
Adopt resolution.
cc: Shauna Clark
Jim Penman
Signature
Contact person: Roger G Hardqrave Phone: 5025
Staff Report, Report of
Supporting data attached: Bids & Resolution Ward: 3
FUNDING REQUIREMENTS: Amount: $151 , 000 (Gas Tax Fund)
Source: (Acct No ) 126-356-57856
Acct. Description) Improvement of Pepper Avenue
(West Side) Finance:
Council Notes:
75-0262 Agenda Item No.
CITY OF SAN BERM .4DINO - REQUEST F%M COUNCIL ACTION
STAFF REPORT
Bids for the improvement of Pepper Avenue (west side) ,
south of Mill Street, were opened at 2 : 00 p.m. , Tuesday, 12-13-
94 .
A total of 14 bids were received, ranging from
$134 , 717 . 86 to $196 , 593 . 01 . The low bid of $134 , 717 . 86 is 9 . 6%
under the Engineer' s Estimate of $149 , 040 . 00 .
Below is an estimate of the total project cost, based
upon the actual low bid price:
Construction Contract $ 134 , 717 . 86
Engineering & Inspection (W.O. #1405) 8 , 500 . 00
Sub-Total $ 143 , 217 . 86
Contingencies (5%) ± 7 , 782 . 14
TOTAL ESTIMATED PROJECT COST $ 151,000.00
An amount of $165 , 000 has been allocated, under Account
No. 126-356-57856 , to finance the cost that will be incurred for
this project.
We recommend that a contract be awarded to the low
bidder.