HomeMy WebLinkAbout15- Public Works C IT Y OF SAN BERN[ -IDINO - REQUEST Fr 'I COUNCIL ACTION
File No. 1.397 & 4.42-32
ROGER G. HARDGRAVE Approval of Plans & Authorization
From: Subject: to Advertise for Bids - Modifica-
tion of Traffic Signals & Drain-
Dept: Public Works age Improvements at Kendall Dr. &
Little Mountain Dr. , per Plan
Date: 2-1-95 No. 9181
Synopsis of Previous Council action:
June, 1994 -- Allocation of $60 , 000 in 1994/95 Traffic Systems Fee
Budget and $25 , 000 in 1994/95 Storm Drain
Construction Fund Budget, approved.
2 FEE 9:, ',0. 3U
Recommended motion:
That the plans for modification of the traffic signals and drainage
facilities at Kendall Drive and Little Mountain Drive, in
accordance with Plan No. 9181 , be approved; and the Director of
Public Works/City Engineer be authorized to advertise for bids.
cc: Shauna Clark
Signature
Contact person: Roger G Hardgrave Phone: 5025
Supporting data attached: Staff Report _Ward: 5
(Storm Drain Const. & Traffic Systems
FUNDING REQUIREMENTS: Amount: $84 , 000 Fee Funds)
Source: (Acct No ) 248-368-57831 & 250-670-57397
(Acct Description) Kendall Dr /Little Mtn Dr. - Left
Turn Signals & Catch Basin Finance-
Council Notes:
75.0262 Agenda Item No.
CITY OF SAN BERN. .1DINO - REQUEST F..R COUNCIL ACTION
STAFF REPORT
Plans for modification of the traffic signals and
drainage improvements, at the intersection of Kendall Drive and
Little Mountain Drive, have been prepared by the Engineering
Division, and the project is ready to be advertised for bids.
This project consists, in general, of providing left turn phases
for Kendall Drive, installing a catch basin and curbed medians
(to preclude left turns into the frontage road adjacent to
Kendall Drive) .
Below is an estimate of the total project cost:
Traffic
Signals Drainage Total
Construction Contract $ 50 , 980 $ 20 , 176 $ 71 , 156
Engr. & Insp. (W.O. 1701 & 2 , 900 2 ,500 5 , 400
(1531)
Sub-Totals $ 53 , 880 $ 22,676 $ 76 ,556
Contingencies (10%) ± 5 , 120 2,324 7 ,444
TOTAL ESTIMATED PROJECT COST $ 59 , 000 $ 25,000 $ 84 ,000
The following listed funds have been allocated to finance
the costs that will be incurred for these improvements:
Account No. Amount
248-368-57831 $ 25 , 000
250-670-57397 60 , 000
TOTAL ALLOCATED FUNDS $ 85 , 000
We recommend that the plans be approved and authorization
granted to advertise for bids.
2-1-95