HomeMy WebLinkAbout23- Public Works CITY OF SAN BERN[ IDINO - REQUEST V R COUNCIL ACTION
File No. 1.306
ROGER G. HARDGRAVE Approval of Contract Change Order
From: Subject: No. THREE - Interconnect & Modi-
Public Works fication of Traffic Signals -
Dept: Central Business District, per
Plan No. 8805 --
Date: 1-27-94 SUPERIOR SIGNAL SERVICE CORP.
Synopsis of Previous Council action:
June, 1992 - Allocation of $778 , 000, for completing the
interconnect and upgrading of traffic signals in CBD
approved in 1992/93 Federal-Aid Surface Transportation
Program.
09-08-92 -- Resolution NO. 92-372 adopted authorizing execution of
an Agreement with MGA for Professional Engineering
Design Services .
04-19-93 -- Allocation of $778 , 000 of Federal-Aid CMAQ funds ,
under Account No. 242-362-57306 , and plans approved,
and authorization granted to advertise for bids .
06-21-93 -- Resolution No. 93-212 adopted, awarding a contract to
Superior Signal Service Corp. for low bid price of
$695 , 878 .
Recommended motion:
That Change Order No. THREE to the contract with Superior Signal
Service, for the modification of Traffic Signals in the Central
Business District, be approved, to authorize the relocation of the
Traffic Signals and accessories to facilitate the proposed street
widening at the southwest corner of Rialto and "E" Sts. , at a cost
not to exceed $11 , 000 . 00; from $698 , 781 . 99 to $709 ,781 . 99 .
cc: Shauna Clark
Barbara Pachon
ignature
Contact person: Roger G. Hardgrave Phone: 5025
Supporting data attached: Staf f Report & CCO #3 Ward: 1
FUNDING REQUIREMENTS: Amount: $11 , 000 (Street Construction Fund)
Source: (Acct. No.) 242-362-57306
Acct. Description) Interconnect & Modify affic
Signals - CBD Finance:
Council Notes:
75-0262 Agenda Item No.
CITY OF SAN BERNP -VINO - REQUEST Ml COUNCIL ACTION
STAFF REPORT
The plans for interconnecting and modifying the traffic
signals in the Central Business District were prepared by a con-
sultant, pursuant to an Agreement approved on 9-8-92 .
Authorization was subsequently granted to initiate pro-
ceedings to direct the owner, of the parcel on the southwest
corner of Rialto Avenue and "E" Street, to widen Rialto Avenue to
match adjoining sections . This widening would entail reconstruc-
ting the curb return at Rialto Avenue and "E" Street at the new
curb alignment, and increasing the radius to comply with our
policies.
The plans for the traffic signal interconnect and modi-
fication direct the new signal equipment to be installed to match
the existing curb return. One traffic signal foundation has been
poured.
There are some existing pull boxes and conduit that will
have to be relocated to clear the new curb construction. It is
advisable for these facilities to be relocated by the traffic
signal contractor, since he is performing similar work. The
traffic signal contractor has agreed to perform this relocation,
abandon the foundation that was recently nour_ed, and construct a
new foundation on a time and materials basis at a cost not to
exceed $11 , 000.
The total estimated project cost included an amount of
$102 , 945 for contingencies, under Account No. 242-362-57306 ,
which can be used to finance the cost for this extra work.
Caltrans will need to concur with this extra work, since
100% of the project cost is being financed with Federal-Aid CMAQ
Funds. A request has been submitted to Caltrans for concurrence,
and a reply is expected within the next few days .
The owner of the parcel on the southwest corner did not
proceed to widen the south side of Rialto Avenue within the
specified time frame. Therefore, we are proceeding to have the
work done and place an assessment on the parcel to recover the
City' s cost. If the traffic signal relocation work is not done
under the current contract, it will have to be done under the
widening and assessed to the property owner.
We recommend that the relocation work be added to the
current contract.
1-27-94
5.0264
CONTRACT CHANGE ORDER NO. 3 REV NO. SUPPL. NO.
ROAD Traffic Signal Interconnect-Downtown SHEET 1 OF 1
FED NO. CMAQLG-5033 (006) CONTRACT NO. 8805
TO: SUPERIOR SIGNAL SERVICE CORPORATION
You are hereby directed to make the herein described changes from the plans and
specifications or do the following described work not included in the plans and
specifications on this contract. NOTE: This change order is not effective until
approved by the State Highway Engineer
Description of work to be done, estimate of quantities, and prices to be paid.
Segregate between additional work at contract price, agreed price and force
account. Unless otherwise stated, rates for rental of equipment cover only such
time as equipment is actually used and no allowance will be made for idle time.
The last percentage shown is not accumulated increase of decrease from the
original quantity in the Engineers Estimate.
EXTRA WORK AT FORCE ACCOUNT:
Remove and relocate the existing traffic signal poles, conduit, pull boxes and
street lighting conduit approximately 7-8 feet, to the ultimate street width at
the southwest corner of Rialto and "E" Streets, as directed by the Resident
Engineer, at a cost not to exceed $11, 000. 00.
ESTIMATED COST DECREASE $ INCREASE 8 11,000.00
By reason of this order the time of completion will be adjusted as follows:
1- working day
Submitted by: Resident Engineer, Date:
Approval Recommended: Date:
Approved: City Engineer Date:
We the undersigned contractor, have given careful consideration to the change
proposed and hereby agree, if this proposal is approved, that we will provide all
equipment, furnish all material, except as may otherwise be noted above, and
perform all services necessary for the work above specified, and will accept as
full payment therefor the prices shown above.
Accepted Date: Contractor:
By: Title:
If the contractor does not sign acceptance of this order, his attention is
directed to the requirements of the specifications as to proceeding with the work
and filing a written protest within the time therein specified.