HomeMy WebLinkAbout15- Development Department L — V E L O P H E N T D E P A R T M E N T
OF THE CITY OF SAN BERN ARDINO
REQUEST FOR COMKIISSIOP/COUNCIL ACTION
From: KENNETH J. HENDERSON Subject: COURT STRHBT SQUARE
Executive Director CONSTRUMON UPDATE
Date: February 26, 1993
--------------------------------------------------- ------------------
3Ynovsis of Previous Commission/Council/Committee Action(s)
On November 11, 1992, the Community Development Commission approved
the Court Street Square plans and budget, authorizing construction to
begin January, 1993.
--------------------------------
--------------------------------------------
Recommended Motion(s):
i
(Community Development Commission)
MOTION: That the Community Development Commission receive and
file the attached staff report regarding Court Street
Square construction progress.
I
Administrator KENNETH J.'HENDkRSON
Executive Director
-------------------------------------.
---------------
Contact Person(s): Ken Henderson/David J Norman Phone: 5081
Project Area(s): Central City Ward(s): One (1)
Supporting Data Attached: Staff Report
FUNDING REQUIREMENTS: Amount: I N/A Source: N/A
Budget Authority: N/A
--------------------------------------------------
Commission/Council Notes:
---------------------------------------------------COPRffSSION ME19TING AGENDA ----
KJH:DJN:mkc:2907J
Meeting Date: 3/08/1993
Agenda Item Number:
D o V E L O P H I N T D E P A R T M E N T
OF THE CITY OF SAN BERNARDINO
STAFF REPORT
Court Street Square Construction
Despite the rain, the contract with Bob Britton, Inc for construction
of the primary improvements for Court Street Square is progressing
toward completion. While there are increases for costs of removing
buried concrete and changes requested by City departments, the net
increase at this time is less than one percent (1X) of the contract
which is far below the normal ten to fifteen percent contingency
reserve. This is because other changes have reduced the cash costs of
the contract. As these changes must be made during the relatively
short time frame of the construction itself, they are being accumulated
and will be presented to the Commission at the conclusion of the work.
Most of the cost increases are already provided for in the terms of the
approved contract. Staff will be providing specific proposals for the
restrooms and kitchen facility for the site as well as with a proposal
for the planned ampitheater adjacent to the site.
SAVINGS REALIZED
Staff has realized cash savings of approximately $8,200 to date through
relatively minor changes. The nature of the existing surface membrane
on the Convention Center roof resulted in a recommendation for the
deletion of the two (2) street light type poles at the top of the
monumental stairs and replacing these with louvered step lights at each
of the two landings which netted a savings of approximately $1,800.
This change also resulted in a better integration of the upper plaza
with the Court Street Square. The proposed street light type poles
would have seemed out of place on the upper plaza level with its
railroad signal-type poles. Nearly $4,000 was saved from the current
budget with the use of existing sewer capacity credits which reduced
our cash outlay for sewer hook-up from $6,100 to $2,200. Approximately
$2,400 will be saved from the construction budget through Main Street's
decision to add a light bar inside the tent which substitutes permanent
stage lighting for temporary rented lights for performances. This
change eliminated four lighting poles in the middle of the tent,
thereby eliminating obstructions in the floor space and facilitating
more efficient floor layouts for different events.
---------------------------------------------------—--------------------
FJH:DJN:mkc:2907J COMMISSION MEETING AGENDA
Meeting Date: 3/08/1993
Agenda Item Number:
DEVELOPMENT DEPAkTMbdT STAFF npORT
Court Street Square Construction Update
February 26, 1993
Page Number -2-
ADDITIONAL COSTS INCURRED
Besides the rain, undisclosed site conditions which were expected but
whose quantities could not be determined prior to excavation, have
slowed progress only to a minimal degree. Although not costly in time,
the removal of buried concrete from the site has resulted in nearly
$5,000 in extra work. This extra work was provided for in the terms of
the contract but was not a part of the bid price and will be billed
seperately as the actual quantities and the nature of the work are
disclosed.
In addition to the excavation of those foundations, some change orders
have become necessary due to grading and site conditions and/or health
and safety issues. In order to properly drain the site, the Public
Works department recommended that the catch basin be moved to a new
location. This change resulted in an additional $2,600 to the contract
for a sidewalk cut and additional storm drain pipe under the sidewalk.
The handrailing on the monumental stairs was found by the Planning and
Building Services Department to be inadequate, causing a change in the
handrail-midrail design. Putting additional steel midrails in the
railing resulted in a $3,000 change to the contract.
Also, unearthed conditions on the east end of the site will result in
$500 of sandblasting and wall refinishing near the convention center
fire exit. Years ago, when the Court and "E" Street parking lot was
constructed, the wall was painted and finished only to the extent of
existing grade. When this grade was changed for our current
construction, the wall was found to be covered with tar and the
concrete left unfinished. The proposed sandblasting and refinishing
and repainting of this wall will be necessary for site aesthetics. In
addition, an increase in water meter service charges and an upgrade
from 3/4" to 1" water meters resulted in a $3,200 change to the current
budget.
The approximately $11,300 in increases to date have been offset by
approximately $8,200 of reductions to the budget resulting in a net
$3,100 in additional cost. As a percentage of total budget authority
(excluding the proposed kitchen and restroom discused below), current
changes have resulted in an increase of less than one percent (1%) of
budget authority at this time, far below the industry's standard
contingency of ten to fifteen percent.
-------------------------------------------- -
KJH:DJN:mkc:2907J COMMISSION MEETING AGENDA
Meeting Date: 3/08/1993c�
Agenda Item Number: ��J
DEVELOPMENT DEPARTHRat STAFF REPORT
Court Street Square Construction Update
February 26, 1993
Page Number -3-
---------------------------------------------------------—-------------------
RESTROOMS AND KITCHEN
Staff is working with Main Street and with the Planning and Building
Services Department on kitchen and restroom concepts which will best
balance current budget constraints with future life cycle, operation,
and maintenance costs. Providing a fully equipped kitchen has turned
out to be far beyond the budget and yet the options for reduced scale
equipment are severely limited by County Environmental Health Services
Department regulations. Staff is exploring several options for both
kitchen and restroom facilities and it is our intention to bring
forward design and cost criteria in the near future.
AMPHITHEATER
A seperate matter is the installation of an amphitheater improvement
which will tie the Court Street Square activity area to the Radisson
Hotel and Convention Center area. As originally envisioned, this
project involves changes to the entrance of the Radisson Hotel,
improvements to the street face of the Convention Center, the
installation of parallel parking and a pedestrian crossing in "E"
Street, and improvements for the Harris' courtyard area. Because some
parts of this program have proceeded slowly and have not coalesced, we
are shifting to a narrower scope of work.
Staff had earlier requested proposals from qualified engineers and
landscape architects for the design and construction phase of the
improvements. By limiting the issues to the amphitheater, it will be
possible to bring forward a recommendation on this component of the
short-term improvements described in the Downtown Plan. Staff expects
to make a specific recommendation on this in the near future.
Staff recommends adoption of the form motion.
K(EiNiE4 J. ERSON, Executive Director
Development Department
--------------------------
KJH:DJN:mkc:2907J COMMISSION MEETING AGENDA
Meeting Date: 3/08/1993
Agenda Item Number: ��