HomeMy WebLinkAbout11- Development Department D b V E L 0 P ME N T DR P A R T ME NT
OF THE CITY OF SAN BERNARDINO
REQUEST FOR COMM SSION/COIINCIL ACTION
From: KENNETH J. HENDERSON Subject: MEDIAN LANDSCAPE
Executive Director IMPROVEMENTS OF WATERMAN
AVENUE FROM THE SANTA
ANA RIVER TO MILL STREET
Date: February 18, 1993
--------------------------------------
------------------
Synopsis of Previous Commission/Council/Committee Actions)
i At its meeting on February 18, 1993, the Redevelopment Committee
recommended to the Community Development Commission approval of median
landscape improvements not to exceed $163,000 to Waterman Avenue from
the Santa Ana River to Mill Street.
i -----------------------------------------------------------------------------
i Recommended Notion(s):
(Community Development Commission)
MOTION: That the Community Development Commission approve funding
not to exceed $163,000 for median landscape improvements
to Waterman Avenue from the Santa Ana River to Mill
Street and authorize the Chairman and Executive Director
to develop and execute agreements accordingly.
Administrator KENNETH J. HElDERSON
Executive Director
----—------------------------------
------------------
Contact Person(s): Kenneth Henderson/Doris A. Daniels Phone: 5081
Project Area(s): None Ward(s) : 1 and 3
Supporting Data Attached: Staff Report
FUNDING REQUIREMENTS: Amount: $163,000 Source: Bond Proceeds
Budget Authority: Previously Funded
--------------------------------------------------
Commission/Council Notes:
-------------------—----------------------------------------------------
KJH:DAD:lag:0442q COMMISSION MEETING AGENDA
Meeting Date: 03/08/1993
Agenda Item Number: _
D #1EL0PMENT D PAYT9ENT
OF THE CITY OF SAN BERNARDINO
STAFF REPORT
MEDIAN LANDSCAPE IMPROVEMENTS OF WATERMAN AVER[TE
FROM THE SANTA ANA RIVER TO MILL STREIT
At its meeting on February 18, 1993, the Redevelopment Committee reviewed
a proposal from the Director of the Public Works and recommended to the
Community Development Commission approval of median landscape
improvements not to exceed $163,000 to Waterman Avenue from the Santa Ana
River to Mill Street.
i
The landscape improvements are requested to accomplish the following:
To enhance Waterman Avenue which is a major entrance into the city
and a vital element in the re-use of Norton A.F.B. and
To complement the beautification efforts of undergrounding utilities
which the city has undertaken at a cost of approximately $6 Million.
The preliminary estimate of cost for installing an irrigation system and
landscaping in the existing curbed medians is as follows:
NO ITEM Qty Unit Unit Price Amount
1. River Rock 14,000 Sq. Ft. $ 3 $ 42,000
I
2. Irrigation System 1 L.S. $ 20,000 $ 20,000
3. Trees 70 Ea. $ 300 $ 21,000
i
4. Shrubs 500 Ea. $ 20 $ 10,000
5. Turf 48,000 Sq. Ft. $ .75 36,000
Sub-Total $ 129,000
Engineering & Insp. (10%)+/- 13}000
Sub-Total $ 142,000
Contingencies (15%) +/- 21,000
TOTAL PRELIMINARY ESTIMATED COSTS $ 163,000
-----------------------------------------------------------------
KJH:DAD:lag:0442q COMMISSION MEETING AGENDA
Meeting Date: 03/08/1993
Agenda Item Number: �_
DgVEWPMENT DBPAATK--r STAFF nPORT
MEDIAN LANDSCAPE IMF_ -1VEMENTS OF WATERMAN AVENUE
FROM THE SANTA ANA RIVER TO MILL STREET
February 18, 1993
Page Number -2-
----------------------------------------------------------
The river rock would be installed to provide an 18-inch buffer around the
periphery of the medians for safety of maintenance personnel. River rock
is recommended, since this theme has been established on Waterman Avenue
to the south.
Based on the information presented in this report, staff recommends
adoption of the form motion.
KE J. HEADERSON, Executive Director
Development Department
----------------------------------------------------------—-----------------
KJH:DAD:lag:0442q COMMISSION MEETING AGENDA
Fleeting Date: 03/08/1993
Agenda Item Number: �_
C I T Y O F S A N B E " M A R D I
INTEROFFICE MEMOt,tNDUM N 0
TO: TIM STEINHAUS, Agency Administrator
Economic Development Agency
FROM: ROGER G. HARDGRAVE, Director of Public Works/
City Engineer
SUBJECT: Landscaping Medians - Waterman Avenue, from
Santa Ana River to Mill Street
DATE: February 18, 1993
COPIES_-----File-No_-14_40_54-; - Reading File---
Various proposals have been made to establish an assessment
district to finance the installation of landscaping along this
section of Waterman Avenue. However, we were unsuccessful in
securing the property owner's concurrence.
Waterman Avenue is a major entrance into our city and a vital
element in the re-use of Norton A.F.B. The overhead utilities on
Waterman Avenue are being undergrounded, at a cost of
approximately $6 Million. Installation of landscaping would
complement the beautification efforts of undergrounding
utilities.
Therefore, it is requested that consideration be given to
allocating EDA funds to finance this landscaping.
Below is a preliminary estimate of cost for installing an irri-
gation system and landscaping in these existing curbed medians.
No Item Unit
Quantity Unit Price Amount
1. River Rock 14, 000 Sq.Ft. $ 3
2- Irrigation System $ 42, 000
1 L.S. $ 20,000 20,000
3. Trees 70 Ea.
$ 300 21,000
4- Shrubs 500 Ea.
$ 20 10,000
5. Turf
48, 000 Sq.Ft. $ 0.75 36,000
Sub-Total $ 129, 000
Engineering & Insp. (10$) ± 13,000
Sub-Total $ 142,000
Contingencies (15%) t 21,000
TOTAL PRELIMINARY ESTIMATED COST $ 163,000
I(
' TIM STEINHAUS
Landscaping - -aterman Avenue
February 18, 1993
Page - 2 -
The river rock would be installed to provide an 18-inch buffer
around the periphery of the medians for safety of maintenance
personnel. River rock is recommended, since this theme has been
established on Waterman Avenue to the south.
Please advise if you need any additional information to support
Pthi equest.
OGER G. HARDGRAVE
Director of Public Works/City Engineer
RGH:rs