HomeMy WebLinkAbout03- Development Department DEVELOPMENT DEPARTMENT OF THE CITY OF SAN BERNARDINO REQUEST FOR COMMISSION/COUNCIL ACTION From: Roger G. Hardgrave, Dir. Subject: Approval of Contract of Public Works/City Engr. Change Order No. 1 - In-Fill Street Im- Date: February 25, 1993 provements on Arteri- al & Collector Sts. , per Plan No. 8842 - BOB BRITTON, INC. ----------------------- --------------- Synopsis of Previous Commission/Council/Committee Action:-------- 05-20-91 -- Resolution 91-185 establishing procedures for a Land- scaping Development Program on selected major arterials adopted. 09-08-92 -- Allocation of $1 , 000, 000 . 00 from Tax Allocation Bond Proceeds approved. 12-07-92 -- Plans approved and authorization granted to advertise for bids. 01-20-93 -- Award of Contract to Bob Britton, Inc. , for the low bid price of $364 , 422 . 80. ---------------------------------------------- Recommended Motion: That Change Order No. 1 to the contract with Bob Britton, Inc. , for in-fill street improvements, in accordance with Plan No. 8842, be approved; to include street improvements and a pedestrian walkway ramp on Sierra Way, North of 44th Street, at an estimated increase in the contract pr' e of $21 , 764 . 00• $364, 186 . 80 to $386, 186 . 80 . R g a g , r. of .W. /C.E. cc: T. Steinhaus S. Clark ----------------------Timot inhaus, Agency Administrator --------------------------------- Contact Person: Gene R. Klatt Phone: 5125 Project Area: All Ward(s) : All Supporting Data Attached: Staff Report, CCO #1 Tax FUNDING REQUIREMENTS: Amount: $ 21 , 764 . 00 Source:—Proceeds Acct. # Budget Authority: 650-0140 ------------------------- --------------------------- ---------- Commission/Council Notes: Agenda Item No. : 3 DEPARTMENT OF PUBLIC WORKS STAFF REPORT In-Fill Street Improvements on Arterial & Collector Streets Plans were prepared several years ago for installation of sidewalk on Sierra Way (West side) , north of 44th Street. Other items of work, such as curb and gutter, in-fill paving, retaining wall and handrail, are required in connection with installation of sidewalk. In addition, a ramp must be provided to maintain access to Sierra Way for the pedestrian easement dedicated by the adjoining subdivision. These improvements were not constructed, due to insufficient funds and a lack of consensus among the residents of the adjoining tract over if pedestrian access should continue to be provided to Sierra Way. Installation of this section of sidewalk could be accomplished under the contract with Bob Britton, Inc. , for construction of in-fill street improvements. A price quote of $21 , 764. 00 has been submitted for installation of this sidewalk and appurtenant facilities . We have reviewed the price quote and found it to be in accordance with current pricing trends . We recommend that Change Order No. One be approved. A change order will be needed since installation of this sidewalk on Sierra Way entails some items of work not included in the contract bid items. 2-25-93 k5 C I T Y O F S A N B E R N A R D I N O DEPARTMENT OF PUBLIC WORKS ENGINEERING DIVISION Project: INSTALLATION OF IN-FILL STREET IMPROVEMENTS (SIERRA WAY-NORTH OF 44TH STREET, PLAN NO. 7753) File No. : 6.21-26 Plan No. : 8842/7753 Date: 2/25/93 CONTRACT CHANGE ORDER NO. ONE TO: BOB BRITTON, INC. 171 S. Waterman Ave. San Bernardino, CA 92408 Gentlemen: You are hereby authorized and directed to perform the following work on Sierra Way, North of 44th Street. The work to be done will be in accordance with Plan No. 7753, and is as follows: i Clearing and Grubbing . . . . . 1 Grading (165 C.Y. ) Final. . . .L.S. . $ 3,775. 00 1 „ . . . . . .$ 3, 645. 00 Retaining Wall. . . . . . $20. 00/L.F. . . . . . . . 107 . . . . . . $ 2, 140. 00 Sidewalk . . . . . . . . . . . $ 1.50/S.F. . . . . . . . 2, 300. • • • . $ 3,450. 00 Curb & Gutter $ 7. 50/L.F. . . . . . . . 180 . . . . . . $ 1, 350. 00 Asphalt Paving . . . . . $ 1.35/S.F. . . . . . . . 540 . . . . . . $ 729.00 Conc.Ramp/Ret. Wall $10. 00 1S.F. . . . . . . . 408 . . . . . . $ 4, 080.00 Handrail . . . $22 .50/L.F. . . . . . . . 102 . $ 2,295. 00 Handicap Ramp . . . . . . $300. 00/EA. . . . . . . . 1 . . . . . . $ 300. 00 $21, 764.00 Total Extra Work Cost added to Contract . . . . . . . . .$ 21, 764.00 Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . .$ 364.422.80 Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 386.186.80 Additional time to complete Contract due to Change Order -0-Workinc Days CONTRACTOR CITY OF SAN BERNARDINO Accepted Recommended By. By: ROGER G. HARDGRAVE DATE Title: Director of Public Works/City Engr Date: