HomeMy WebLinkAbout43- Public Works CITY OF SAN BERK .RDINO - REQUEST t )R COUNCIL ACTION
File No 1,289
Approval of Plans & Authorization
From: ROGER G. HARDGRAVE Subject: to Advertise for Bids - Pavement
Rehabilitation on Waterman Avenue,
Dept, Public Works from Barton Road to Redlands
Date: 2-24-93 Blvd. , per Plan No. 8869
Synopsis of Previous Council action:
�s 7 -,June, 1991 - Allocation of $110 , 000 in 1991/92 Storm Drain Con-
struction Fund Burlgr?t, under. Account No. 248-368-
57883 , approved.
June, 1992 - Allocation of '7400 , 000 in 1991/92 Street Construction
Fund Budget, under Account No. 242-362-57289 , and
$50 , 000 n Tr..ffic Systems Fee Fund, under Account No.
250-670••5789G , approved.
Recommended motion:
That the plans for rehabilitating pavement, installing storm drain
and traffic signal interconnect, in Waterman Avenue, from Barton
Road to Redlands Boulevard, in accordance with Plan No. 8869 , be
approved; and the Director of Public Works/City Engineer be
authorized to advertise for bids.
cc: Shauna Clark
Barbara Pachon
ig re
Contact person: Roger G. Hardqrave Phone: 5025
Supporting data attached: Staff Report Ward: 3
FUNDING REQUIREMENTS: Amount: $519 , 000
242-362-57289 ; 248-368-57883 ,
Source: (Acct. No.) & 250-670-57896
Acct. Description) Pavement Rehabilitation --
Waterman Avenue, Barton Rd. to Redlands Blvd. Finance:
Council Notes:
75-0262 Agenda Item No.
CITY OF SAN BERN. IDINO - REQUEST F R COUNCIL ACTION
STAFF REPORT
Plans for rehabilitating the pavement on Waterman Avenue,
from Barton Road to Redlands Boulevard, have been prepared by the
Engineering Division, and the project is ready to be advertised
for bids. The project consists, in general , of rehahilitating
the pavement, installing the master plan storm drain (between
Caroline Street and Redlands Boulevard) , and installing traffic
signal interconnect.
Below is an estimate of the total project cost:
Construction Contract -
Pavement Rehabilitation $258 , 390
Storm Drain 102 , 580
Traffic Signal Interconnect 50 , 000
$416, 670
Engineering & Inspection (W.O. #1988 &1502) 26 , 500
Relocate Water Line 8, 000
Sub-Total $451 , 170
Contingencies (15%) ± 67 , 830
TOTAL ESTIMATED PROJECT COST $519,000
Funds have been allocated as set forth below to finance
the costs that will be incurred for this project.
Account No. Amount
242-362-57289 $ 400 , 000
248-368-57883 110 , 000
250-670-57896 50, 000
TOTAL FUNDS AVAILABLE $ 560 , 000
We recommend that the plans be approved and authorization
granted to advertise or bids.
2-24-93
•0264