HomeMy WebLinkAbout11- Public Works CITY OF SAN BERN RDINO - REQUEST F'-)R COUNCIL ACTION
File No. 1. 895
ROGER G. HARDGRAVE Approval of Contract Change Order
From: Subject: No. ONE - Rehabilitation of Pave-
Public Works/En ineerin ment on Arrowhead Avenue, from
Dept: g g Mill St. to 3rd St. , per Plan
12--09--93 No. 8815 --
Date: MATICH CORPORATION
Synopsis of Previous Council action:
July, 1991 - Allocation of $500, 000 . 00 in 1991/92 Street Construc-
tion Fund budget approved.
02-16-91 - Transfer of $500, 000 . 00 to Street Resurfacing -
Various locations approved and $500 , 000 allocated from
Subordinate Tax Allocation Bond Issue of 1991 .
U2-17--92 - Resolution No. 92--55 adopted authorizing execution of
an agreement with L.A. Wainscott for professional
services .
02--15--93 - Resolution No. 93-43 adopted authorizing execution of
Program Supplement No. 77 .
04-19-93 - Plans approved and authorization granted to advertise
for bids . (Cont. on second page. )
Recommended motion:
That Change Order No. ONE to the contract with Matich Corporation,
for rehabilitation of Arrowhead Avenue , from Mill St. to 3rd St.
be approved; to authorize the Contractor to place 3-inch rock
additional asphalt grindings and geo-grid (as recommended by the
Soils Engineer . to stabilize the subgrade between Cluster Ave. and
Valley St. , at an estimated increase to the contract price of
$15 , 500 . 00; from $626 , 413 . 00 to $641 . 913 . 00 .
cc: Shauna Clark e 9
Signature
Contact person: Gene R fl�tt Phone: 5125
Supporting data attached: Staff Report, CCO #1 Ward: 1
FUNDING REQUIREMENTS: Amount: $15, 500 . 00 (Street Construction Fund)
Source: (Acct. No.) 242--362-57895
Acct. Description) Arrowhead Ave ue Reha_bi4itation,
Mill St. to Third St. Finance:
Council Notes:
75-0262 Ananria Itam Nn //
PUBLIC WORKS
File No. 1 . 895
SYNOPSIS OF PREVIOUS COUNCIL ACTION Continued:
08-02--93 -- Resolution No. 93-289 adopted awarding a contract to the
Matich Corporation for the lowest responsible bid of
$626 , 413 . 00 .
12-09--93
CITY OF SAN BERN,' IDINO - REQUEST F'R COUNCIL ACTION
STAFF REPORT
Removal of the existing pavement section revealed that
the underlying soil was unsuitable to serve as subgrade for the
new asphalt concrete to be placed.
Normal practice would be to remove the unsuitable
material and impact backfill soil that meets the specifications .
However, this method was not practical , due to the shallowness of
'the utilities . Removal of the unsuitable material would have en-
tailed relocating the sewer, water, geothermal , gas and telephone
lines .
The Soils Engineer was, therefore, requested to provide a
recommendation to stabilize the unsuitable material in place. A
recommendation was made that 3-inch rock be spread over the un-
suitable material , and compacted with a steel-wheel vibratory
roller. Asphalt chippings were then to be applied to a depth of
3 inches , and a geo-grid fabric placed over the chippings .
The above items of work are necessary to prevent
premature failure of the pavement section, with the attendant
extra maintenance costs being incurred by the Cite.
The Contractor has been directed to proceed with the
extra work involved in stahilizincT the unsuitable material , in
order to avoid extensive delay claims by the Contractor. This
extra work is being done on a time and material basis , as
provided in Section 4-103 , "changes" in the State of California
Standard Specifications.
The total estimated project cost included an amount of
$106 , 587 for contingencies, which can be used to finance the
additional cost for this change order.
Federal-Aid Surface Transportation Funds (STP) have been
approved to finance approximately 88% of the total project cost,
including any required extra work. Caltrans oversees Federal-Aid
funded projects to insure compliance with all applicable federal
requirements . Their representative has reviewed this extra work,
and determined that it is eligible for Federal-Aid funds.
Since the Contractor is entitled, by terms of the
contract, to be compensated for work required in the construction
of the project, we recommend that Change Order No. 1 be approved.
12-09-93
75-0264
i
0
CITY OF SAN BERNARDINO
Memorandum
Date: 12/6/93
File No. 1. 385
To: Roy King, Local Assistance
From: Mike Grubbs Contingency Balance
CCO No. 1 Rev No. Sup No. (Inc This Change)
$ 91,087 .00
$ 15,500.00 INCREASE
THIS CHANGE ORDER PROVIDES for the additional work required in the
placement of amendments in unsuitable soils and additional asphalt
grindings and geo-grid prior to the paving of Arrowhead Avenue.
During the grading operation on Arrowhead Avenue, unsuitable
material was discovered in an area between Cluster Avenue and
Valley Street. The soil was analyzed and found to be unsuitable
subgrade material, the Soils Engineer recommended that this soil be
amended and 3-inch rock be placed to stabilize the subgrade, and
then 3-inches of asphalt grindings and geo-grid be placed to
stabilize the subgrade.
The parameters of the unsuitable soil were found to be 18-feet wide
from station 26+00 to station 28+00 on the east side of the
roadway, and 24-feet wide from 23+50 to 27+50 on the west side of
the roadway.
The contractor was directed to perform the work on a time and
material basis, with the total cost to be determined when the work
is completed. This change order provides compensation for the extra
work at an estimated cost of $15,500.00.
C.C.O. DISCUSSED WITH:
Construction Engineer: Roy King
Bridge Engineer:
FHWA Rep. YES NO
Name:
ESTIMATE OF COST
THIS JOB TOTAL TO DATE
Item $ $
Force Account $ 15, 500. 00 $ 15, 000. 00
Agreed Price $ $
Adjustment $ $
Total $ 15,500.00 $ 15, 000. 00
Federal Segregation:
Federal No. $
Dist Prior Approval By: Date:
H.Q. Issue & Approval By: Date:
Suppl. Funds Provided: $
RESIDENT ENGINEER
0
CONTRACT CHANGE ORDER NO. 1 REV NO. SUPPL. NO.
ROAD PAVEMENT REHABILITATION-ARROWHEAD AVE SHEET 1 OF 1
FED NO. DBL-5033 (005) CONTRACT NO. 8815
TO: MATICH CORPORATION
You are hereby directed to make the herein described changes from the plans and
specifications or do the following described work not included in the plans and
specifications on this contract. NOTE: This change order is not effective until
approved by the State Highway Engineer
Description of work to be done, estimate of quantities, and prices to be paid.
Segregate between additional work at contract price, agreed price and force
account. Unless otherwise stated, rates for rental of equipment cover only such
time as equipment is actually used and no allowance will be made for idle time.
The last percentage shown is not accumulated increase of decrease from the
original quantity in the Engineers Estimate.
EXTRA WORK AT FORCE ACCOUNT:
Place 3-inch rock into the existing soil to stabilize the subgrade, 3-inches of
asphalt grindings and geo-grid to stabilize the subgrade on Arrowhead Avenue
between Cluster Avenue and Valley Street, as directed by the Resident Engineer,
at a total estimated cost of $15,500.00.
ESTIMATED COST DECREASE $ INCREASE $ 15,500.00
By reason of this order the time of completion will be adjusted as follows:
10 - working days
Submitted by: Resident Engineer, Date:
Approval Recommended: Date:
Approved: City Engineer Date:
We the undersigned contractor, have given careful consideration to the change
proposed and hereby agree, if this proposal is approved, that we will provide all
equipment, furnish all material, except as may otherwise be noted above, and
perform all services necessary for the work above specified, and will accept as
full payment therefor the prices shown above.
Accepted Date: Contractor:
By: Title:
If the contractor does not sign acceptance of this order, his attention is
directed to the requirements of the specifications as to proceeding with the work