File No. 2. 126
Approval of Contract Change
From: ROGER G. HARDGRAVE Subject: Order No. 2 - Maintenance of
Landscaping in Assessment
Dept: Public Works District No. 976, per Plan No.
7034-B --
Date: 11-29-93 MENTONE TURF SUPPLY
Synopsis of Previous Council action:
08-19-86 -- Resolution No. 86-341 adopted establishing Assessment
District No. 976 .
01--05--87 --- Resolution No. 87-9 adopted expanding boundaries of
Assessment District No. 976 .
03--07--88 -- Resolution No. 88-67 adopted expanding boundaries of
Assessment District No. 976 .
06-06-88 - Resolution No. 88-179 adopted awarding a contract to
Cherokee Landscape Services for the low bid price of
$24 , 400. 00 .
06-19-89 -- Change Order No. 1 approved extending the contract for
one year, adjusting bid prices by 6 . 5% for inflation,
incorporating supplemental items of work, for an
increase in annual contract price to $29 , 977 . 00 .
Recommended motion:
That Change Order No. 2 to the contract with Mentone Turf Supply,
for the Maintenance of Landscaping in Assessment District No. 976 ,
in accordance with Plan No. 7034-B, be approved; to authorize the
Contractor to renovate the deteriorated landscaping material (lo-
cated at the southwest corner of Pine and Belmont Avenues) at an
increase in the contract price of $7 , 400 . 00 , from $48 ,619 . 00 to
$56 , 019 . 00 .
cc: Shauna Clark
LS4nA6re
Contact person: Roger G. Hardcfrave Phone: 5025
Supporting data attached: Staff Report & CCO #2 Ward: 5
FUNDING REQUIREMENTS: Amount: $7 , 400 . 00 (Assessment District No. 976)
Source: (Acct. No.) 254-650 & Jr�53925
Acct. Description) A.D. #976
Finance:
Council Notes: %_46 1,9Se a e- /41 re-..p a,✓ o���I �� P
75-0262 Aapnda Item Nn
File No. 2 . 126
SYNOPSIS OF PREVIOUS COUNCIL ACTION Cont.
06-04--90 -- Resolution No. 90--199 adopted awarding contract to
Executive Landscape Contractors, Inc . for the low bid
price of $25, 937 . 44 .
05-20-91 -- Contract Change Order No. 3 approved extending the
contract for one year, at no increase to the contract
unit price.
05-18-92 -- Change Order No. 4 approved to extend the contract for
one year, from 7-1-92 to 6-30-93 , and transfer of
$38 , 966 . 00 to A.D. #976 approved.
05-13-93 -- Resolution No. 93-143 adopted awarding a contract to
Mentone Turf for low bid price of $46 , 169 . 00 .
11-29-93
CITY OF SAN BERNCRDINO - REQUEST F `R COUNCIL ACTION
STAFF REPORT
One of the conditions of approval in 1986 for Tract No.
11844 was that the parkways along Pine Avenue and Belmont Avenue
be landscaped. Additional landscaping was installed at the
southwest corner of Pine Avenue and Belmont Avenue, due to the
remnant parcel created by the Bailey Creek Flood Control Channel.
Over the intervening 7 years, the condition of the ground
cover installed has deteriorated, due to aging of the plant
material and extra wear and tear from being on a corner.
In order to maintain the desired level of esthetics, it
was deemed necessary to remove and replace about 8 , 000 square
feet of ground cover. This operation entailed removing the
existing plant material , scarifying the soil , adding soil
amendments, modifying the irrigation system and reseeding the
area.
The landscape maintenance contractor has quoted a price of
$7 ,400. 00 for doing this extra work. We have reviewed this price
and determined that it is fair and reasonable for the amount of
extra work that was done.
The additional costs incurred for Change Order No. 2 will
be financed through assessments on the various parcels within
Assessment District No. 976 .
We recommend that Change Order No. Two, to the contract
with Mentone Turf for maintenance of the landscaping, be
approved.
11-29-93
75-0264
C I T Y O F S A N B E R N A R D I N O
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
Project: Maintenance of Landscaping - A.D. 976
File No. : 2 . 126
Plan No. : 7034-B
Date: 11/24/93
CONTRACT CHANGE ORDER NO. TWO
TO: MENTONE TURF SUPPLY
P.O. Box 592
Mentone, CA 92359
Gentlemen:
You are hereby authorized and directed to perform the following
work:
Remove the existing groundcover, located at the southwest corner of
Pine and Belmont Avenues, scarify the soil, add soil amendments,
modify the sprinkler system, and install seed for plant turf grass,
as directed by the Resident Engineer, at a total cost of $7,400. 00.
Total Extra Work Cost added to Contract . . . . . . . . .$ 7,400.00
Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . .$ 48,619.00
Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 56,019.00
Additional time to complete Contract due to Change Order -O-Working
Days
CONTRACTOR CITY OF SAN BERNARDINO
Accepted Recommended
By: By:
ROGER G. HARDGRAVE DATE
Director of Public Works/City Engr