ROGER G. HARDGRAVE Subject: Approval of Plans & Authorization
to Advertise for Bids -- Construe--
Public Works tion of Curb Cuts & Drainage In-
Dept: prover-ients on Del Rosa Drive at
1-10-96 Tippecanoe Avenue on. Norton A.F.B.
Date: per Plan Pio. 9432
Synopsis of Previous Council action:
10-04-93 - Resolution No. 93--382 adopted authorizing the Mayor to
execute a grant application to the Economic Development
Administration.
03-21-94 - Resolution No. 94--68 adapted authorizing execution of
approval and award of grant.
4)AIN AM
Recommended motion:
That the plans for installing curb cuts --:lor.g De-1. Rosa Drive ,
and drainage improvements adjacent to TJ-P 'e rnne Ax.=enue, on the
former Norton A.F.B. , in accordance with P l•ar? Ii(-). 9432 , be
approved; and the Director of Pubi is Work-s C7.1-ty - n.gine'nr be
authorized to advertise for bids .
cc : Bill Bopf, IVDA
Shauna Clark
Signature
Contact person: Roder G Hardgrave Phone: 5025
Supporting data attached: Staff Report Ward: 1
FUNDING REQUIREMENTS: Amount: $47 , 000 (Federal EDA Grant & IVDA)
Source:(Acct. No.) 242-362--5504--1993
(Acct. Description) Street Improvements - Tippecanoe
Ave. , "C" St. & Del Rosa Drive
-- Finance:
Council Notes:
75-0262 AnonrJo I+om AL, /�
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Plans for installation of curb cuts along Del Rosa Drive,
and drainage adjacent to Tippecanoe Avenue, on the former Norton
A.F.B. have been prepared pursuant to a letter from William L.
Bopf, Executive Director, dated 12-18-95 , and the project is
ready to be advertised for bids . The project consists , in
general , of removing existing curb and gutter in preparation of
installing a commercial driveway along Del Rosa Drive, and in-
stalling catch basins and storm drain laterals along interior
streets adjacent to Tippecanoe Avenue.
Below is an estimate of the total project cost,:
Construction Contract $ 36 ,545
Engineering & Inspection (W.O. #1993) 3 , 654
Sub-Total $ 40 , 199
Contingencies (15%) ± 6 , 801
TOTAL ESTIMATED PROJECT COST $ 47 , 000
All costs incurred will be charged to Account No. 242--
362-5504-199X� and billed to IVDA. Funding for this project will
be provided from the grant by the Federal Economic Development
Administration (75%) and the Inland Valley Development Agency
(25%) .
We recommend that the plans be approved and authorization
granted to advertise for bids .