File No. 3.14-25
CiTY' OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
From: ROGER G. HARDGRAVE Subject: APPROVAL OF CON'T'RACT CHANGE ORDERS NO. 1 &
2 -- INSTALLATION OF PHASE III, NORTHWEST
Dept: PUBLIC WORKS/ENGINEERING INTERCEPTOR SEWER, IN MEDICAL CENTER DRIVE
BETWEEN 8TH STREET & 16TH STREET, PER PLAN
Date: 2/21/96 ORIGINAL NO. 9187 — NORSTAR PLUMBING CO.
Synopsis of Previous Council action:
June, 1986 -- Allocation of $350,000 in 1986/87 Sewer Line Construction Fund Budget
approved.
June, 1988 -- Allocation of $327,400 in 1988/89 Sewer Line Construction Fund Budget
approved.
April 4, 1994 -- Resolution No. 94-83 adopted authorizing execution of an agreement with
CM Engineering for professional design services.
May 15, 1994 -- Plans approved and authorization granted to advertise for bids, and
transfer of $262,000 approved.
July 24, 1995 -- Resolution No. 95-265 adopted awarding a contract to Norstar Plumbing
Co. for the low bid price of $496,706.00.
Recommended motion: That Change Orders No. ONE and TWO to the contract with Norstar Plumbing
Company, for the installation of Phase III of the Northwest Intercepting Sewer, in accordance
with Plan No. 9187, be approved; to authorize the contractor to perform the necessary extra
work involved in relocation of an existing 24-inch storm drain, and the removal and replace-
ment of additional pavement south of Base Line Street; at an increase in the contract price
of $16,624.38, from $496,706.00 to $513,330.38.
Signature
cc: Shauna Clark
Contact person: ROGER G. HARDGRAVE Phone: 5025
Supporting data attached: Staff Report & CCO #1 & 2 Ward: 1, 3 & 6
FUNDING REQUIREMENTS: Amount: $16,624.38 (Sewer Line Construction Fund)
Source: (Acct. No.) 245-365-5504-1528
Acct. Description) Phase III, Nort est InterceDtor
Finance-
Council Notes:
?414gG
75-0262 Agenda Item No.
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
The contractor for Phase III of the Northwest Interceptor Sewer
encountered a 15X18-inch storm drain in the Base Line Street
Intersection that was not shown on the plans, or in our records.
This storm drain conveys water from the northwest corner to the
southeast corner of this intersection.
It was necessary to relocate about 100 feet of this storm drain, in
order to allow for construction of the interceptor sewer in
accordance with the plans and install a manhole for the storm
drain. This work was performed on a time and material basis, at a
total cost of $9, 739 . 01.
The trench for the interceptor sewer is located a short distance
from the west curb line of Medical Center Drive. A bus stop is
located on the west side of Medical Center Drive, south of Base
Line Street. After excavating the trench in this area for the
sewer, it was found that the intervening strip of pavement was
badly broken due to the loads imposed by the buses.
It was, therefore, necessary for the contractor to remove this
strip of broken pavement and replace as a part of the trench
restoration effort. This extra work was performed on a time and
material basis, at a total actual cost of $6, 885. 37 .
The total estimated project cost, based upon the actual low bid
price, included an amount of $55, 294 . 00 for contingencies, which
can be used to finance the cost of this extra work.
All costs incurred for these Change Orders will be charged to
Account No. 245-365-5504-1528 .
We recommend that Change Orders No. ONE and TWO be approved.
C I T Y O F S A N B E R N A R D I N O
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
Project: INSTALLATION OF PHASE 111 NORTHWEST INTERCEPTOR SEWER IN
MEDICAL CENTER DRIVE BETWEEN 8TH STREET AND 16TH STREET.
File No. : 3 . 14-25
Plan No. : 9187
Date: 1/19/96
CONTRACT CHANGE ORDER NO. TWO
TO: Norstar Plumbing Company
P.O. Box 9000-310
Alta Loma, CA 91701
Gentlemen:
You are hereby compensated for performing the extra work as
directed by the Resident Engineer, as follows:
Remove and relocate an existing storm drain that is in
conflict with the installation of the new sewer mainline, on
a time and material basis, at a total cost of $ 9, 739 . 01.
Total Extra Work Cost added to the Contract . . . . .$ 9,739.01
Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . .$ 503,591.37
Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 513,330.38
Additional time to complete Contract due to Change Order -O-Working
Days
CONTRACTOR CITY OF SAN BERNARDINO
Accepted Recommended
By: By:
ROGER G. HARDGRAVE DATE
Director of Public Works/City Engr
Title:
Date:
C I T Y O F S A N B E R N A R D I N O
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
Project: INSTALLATION OF PHASE 111 NORTHWEST INTERCEPTOR SEWER IN
MEDICAL CENTER DRIVE BETWEEN 8TH STREET AND 16TH STREET.
File No. : 3 . 14-25
Plan No. : 9187
Date: 1/19/96
CONTRACT CHANGE ORDER NO. ONE
TO: Norstar Plumbing Company
P.O. Box 9000-310
Alta Loma, CA 91701
Gentlemen:
You are hereby compensated for performing the extra work as
directed by the Resident Engineer, as follows:
Remove and replace the existing pavement on the southeast
corner of Baseline and Medical Center Drive, on a time and material
basis, at a total cost of $ 6, 885. 37 .
Total Extra Work Cost added to the Contract . . . . .$ 6,885.37
Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . .$ 496,706.00
Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 503,591.37
Additional time to complete Contract due to Change Order -O-Working
Days
CONTRACTOR CITY OF SAN BERNARDINO
Accepted Recommended
By: By:
ROGER G. HARDGRAVE DATE
Title: Director of Public Works/City Engr
Date: