HomeMy WebLinkAbout13- Public Works CITY OF SAN BERNI 'IDINO REQUEST F( Z COUNCIL ACTION
File No. 6 . 44-2
From: ROGER G. HARDGRAVE Subject: Adopted of Amended 1993/94 Capital
Improvement Program - Measure
Dept: Public Works "I" 1/2-Cent Local Funds
Date: 10-2-95
iynopsis of Previous Council action:
06-07-93 - Resolution No. 93-184 , adopting the 1993/94rleasure "I"
Five--Year Plan. approved.
iecommended motion:
Adopt resolution.
cc: Shauna Clark,
Jim Penrian
Barbara Pachon
ature
:ontact person:_ Roger G Hardgrave Phone: 5025
Staff Report, Anended
,upporting data attached: 1993/94 Plan & Resolution Ward: Al
'UNDING REQUIREMENTS: Amount: N/A
Source: (Acct. No.)
(Acct. Description)
Finance:
ouncil Notes: e'S
-02e2 Aqenda Item Nn �3
CITY OF SAN BERN 1DINO - REQUEST F�.A COUNCIL ACTION
STAFF REPORT
In November of 1989 , voters approved Measure "I, "
authorizing San Bernardino Associated Governments, acting as the
Transportation Authority, to impose a one-half of one percent
retail transactions and use tax applicable throughout the county.
This tax can only be used for transportation improvement and
traffic management programs authorized in the expenditure plans
set forth in Ordinance No. 89-1 of the authority.
The referenced ordinance requires each local agency to
expend funds based on a 5-year Capital Improvement Program and
twenty-year transportation plan adopted by resolution for these
funds. Additionally, it is mandatory that each agency update the
plan and program each year.
The Independent Auditor' s Report found that some
expenditures were made in the 1993/94 Fiscal Year for projects
not listed in the Five-Year Plan for Measure "I" Funds . It was
recommended by the auditor that the plan be updated to reflect
actual expenditures .
An amended 1993/94 Plan has been prepared to accomplish
this recordation.
We recommend that the amended 1993/94 Plan be approved.
10-2-95
-0264
10-02-95
CITY OF SAN BERNARDINO
SECOND AMENDMENT
MEASURE "I" FIVE-YEAR PLAN 1993/94
COST
YEAR STREET & LIMITS IMPROVEMENTS ESTIMATE
1993/94 City-wide Street Resurfacing $ 673 , 400
Pepper/Linden Avenue Second of Three 103 , 600
N10 Kendall Dr. Payments for Acqui-
sition of R-O-W
Del Rosa Drive, Widen to 4 Lanes 63 , 000
6th Street to (Local Match to
Base Line Street Federal-Aid project)
Hospitality Lane @ Construct Right Turn 21 , 000
Waterman Avenue Lane (Local Match to
Federal-Aid Project)
Foothill Dr. @ Little Construct Box Culvert 49 , 000
Sand Creek (Local Match to
Federal-Aid Project)
Waterman Avenue, Curbs & Gutters 75 , 249
6th Street to 9th St.
University Parkway, Curbs & Gutters 139 , 140
College Avenue to
Kendall Drive
Redlands Blvd. , Hunts Rehabilitate Pave- 258 , 412
Ln. to Waterman Ave. ment
Kendall Drive, Widen 130 , 184
@ Devil ' s Canyon
Channel
40th Street, Acquire Right-of-Way 63 , 021
Third Ave. to Acre Ln.
Various Locations Minor Improvements 76 , 000
17th Street, West of Curb & Gutter 2 , 876
Arrowhead Avenue
City-Wide Congestion Management 18 , 733
Model
EXHIBIT "A"
Page 2
COST
YEAR STREET & LIMITS IMPROVEMENTS ESTIMATE
1993/94 Tippecanoe Avenue, Widen $ 31 , 560
I-10 to Hardt St.
South "E" Street Widen Bridge 4 ,540
Bridge, at Santa Ana
River
Ninth Street, @ Cross Gutter 3 , 007
Wilson Street
Mill Street, @ Curb & Gutter 1 ,540
Pepper Avenue
TOTAL 1993/94 PROGRAM $ 1 , 714 , 262
Contact:
Roger G. Hardgrave
Director of Public Works/City Engineer
(909) 384-5025