REQUEST FOR COMMISSION/COUNCIL ACTION
From: Roger G. Hardgrave, Dir. Subject: Approval of Contract
of Public Works/City Engr. Change Order No. 1,
Construction of Curb
& Gutter, Sidewalk &
Date: 10-10 -95 Other Facilities at
Various Locations
per Plan. No . 9151 --
GOSNEY CONSTRUCTION
-----------------------
Synopsis of Previous Commission/Council/Committee Action:
June, 1995 -- Allocation of $265 , 721 . 00 , in 1994/95 CDBG Program;
approved.
08-01-94 — Plans approved and authorization granted to
advertise for bids .
09-19-94 -- Resolution No. 94-284 adopted awarding a contract
for the low bid price of $160 , 000 . 00 .
------------ ------------
Recommended Motion:
1. That the Mavor and Common Council increase the CDBG allocation_ to
,- include $6 , 952 . 01 in 1995/96 contingency,
AND
2 . That Change Order No. One to the contract with Gosney Backhoe &
Equipment, for installation of curb and gutter, sidewalk and
other concrete construction, in accordance with Plan No. 9151 , be
approved, to extend the term of the contract from 1-1-96 to 6-30-
96 , and increase the contract price by $160 , 000 . 00 , from
$160 ,000 . 00 to $320 , 000 . 00 .
cc: R. Winkler Roger G. r—dgra-ve,- Dir. of P.W. /C.E.
B. Pachon
J. Howell Timothy Std' haus , Agency Administrator
-------------------------------------------------------------------
Contact Person: Mike Grubbs Phone: 5179
Project Area: N/A _ Ward(s) : All
Staff Report,
Supporting Data Attached: & CCO #1 _
1994/95 & 1995/96 CDBG
FUNDING REQUIREMENTS: Amount: $ 160 , 000 . 00 Source: Program
Accts. #100-80683 &
Budget Authority: 001-406-5505
-------------------------------------
Commission/Council Notes:
Agenda Item No n
0
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Approval of Contract Change Order No.
One -- Construction of Curb & Gutter
at Various Locations
An amount of $265 , 721 . 00 was provided in the 1994/95 Community
Development Block Grant Program for construction of curb and
gutter, sidewalk and other concrete construction at various
locations. Removal of damaged sections of those improvements is
accomplished by personnel from the Department of Public Services,
with construction of replacement facilities done by the
Contractor.
At the Council meeting of 9-19-95 , a contract was awarded to
Gosney Construction for the low bid price of $160 , 000 . 00 . This
contract will terminate on 1-1-96 .
Additional locations have been identified by the Department of
Public Services where the existing curbs and gutters, and side-
walk, are damaged and need to be replaced. The Contractor has
agreed, by letter dated 9-22-95 , to extend the contract from 1-1-
96 to 6-30-96 , at the same unit prices .
An amendment to Memorandum of Understanding, CDBG funded 7 ro 'ect
P ,
has been entered into. This amendment increases the amount of
authorized CDBG funds by $100 , 647 . 99 .
In addition, an amount of $52 , 400 . 00 has been allocated under
Account No. 001-406-5505 , "Professional/Contractual Services, "
for repair of curb and gutter, and sidewalk. The Department of
Public Services would like to apply these funds to finance a
portion of the contract with Gosney Construction. Applying these
funds to the contract will allow work to be done outside of areas
that are eligible for CDBG funds.
Available funds to finance the additional costs to be incurred
pursuant to Change Order No. One are as follows:
Amendment to M.O.U. $ 100 , 647 . 99
1995/96 CDBG Contingency 6 , 952 . 01
Account No. 001-406-5504 52 , 400 . 00
TOTAL AVAILABLE FUNDS -------- $ 160 , 000 . 00
We recommend the term of this contract be extended and the
contract price increased by $160 , 000 . 00 .
10-10-95
CITY _d SAN BERNARDINO, CALIFORh,A
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
_oject• Construction of Curb & Gutter, 7 . 37-94
Sidewalk and Other Concrete File No.
Construction @ Various Locations Plan No. 9151 Date• 10-10-95
CONTRACT CHANGE ORDER NO. ONE
To: GOSNEY CONSTRUCTION
P. O. Box 381
Bloomington, CA 92316
Gentlemen:
You are hereby authorized and directed to perform the following extra
work on the above-referenced contract:
The terms of the contract are hereby amended as set forth below:
1 . The term of the contract is extended from 1-1-96 to 6-30-96 ,
at no change in the contract unit prices.
2 . The contract price is increased by $160 ,000 . 00 .
Total extra work cost added to contract. . . . . . . . . . . . . . . . . . $ 160 ,000 . 00
Previous Contract Price. . . . . . . . . $_ 160 , 000 . 00
. . . . . . . . . . . . . . . . . .
Amended Cost Price. . . . . . . . . . . . $ 320 , 000 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . .
Additional time to complete contract due to change order ll * - 130 WORKING
CONTRACTOR DAYS CITY OF SAN BERNARDINO