HomeMy WebLinkAboutR5- Public Works DEVELOPMENT DEPARTMENT OF THE
CITY OF SAN BERNARDINO
REQUEST FOR COMMISSION/COUNCIL ACTION
From: Roger G. Hardgrave, Dir. Subject: Approval of Plans &
of Public Works/City Engr. Authorization to Ad-
vertise for Bids --
Re-roof and Install
Date: September 26 , 1995 Window at Delmann
Heights Community
Center, per Plan No.
9354
Synopsis of Previous Commission/Council/Committee Action:
June, 1994 - Allocation of $38 , 000 , in 1994/95 Community Develop-
ment Block Grant Program, approved.
----------------------------------------------------------------
Recommended Motion:
That the plans for re-roofing and installing a window at the
Delmann Heights Community Center, in accordance with Plan No.
9354 , be approved; and the Director of Public Works/City Engi-
neer be authorized to advertise for bids.
Roger G;! H rdgrave, Dir. of .W. /C.E.
cc : B. Lindseth =�
A. Ramos
Timothy Steinhaus, Agency Administrator
-----------------------------------------------------------------
Contact Person: Roger G. Hardgrave Phone: 5025
Project Area: N/A Ward(s) : 6
Supporting Data Attached: Staff Report
1994/95 CDBG
FUNDING REQUIREMENTS: Amount: $ 22 , 000 Source: Program
Budget Authority: Account No. 806-4303
-----------------------------------------------------------------
Commission/Council Notes:
Agenda Item No. :
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Approval of Plans and
Authorization to Advertise for Bids
Re-roof and Install Window at
Delmann Heights Community Center
Plans have been prepared for re-roofing and installing a window
at the Delmann Heights Community Center, and the project is ready
to be advertised for bids. The project consists , in general, of
removing the existing rock and installing asphalt shingles; and
installing an additional window in the classroom.
Below is an estimate of the total project cost:
Construction Contract $ 16 , 200
Engineering & Inspection (W.O. #1304) 3 , 000
Sub-Total $ 19 , 200
Contingencies (150) ± 2 , 800
TOTAL ESTIMATED PROJECT COST $ 22 ,000
An amount of $38 , 000 has been allocated in the 1994/95 Community
Development Block Grant Program, under Account No. 806-4303 , to
finance the costs that will be incurred for this project.
We recommend that the plans be approved and authorization granted
to advertise for bids.
9-26-95