CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
From: ROGER G . HARDGRAVE :L7 _jl�gW?c ,;Approval of Contract Change Order
No . ONE & Approval & Acceptance
Dept: Public Works/Engineering - ,_, of Work --Installation of Fill -in
' Sidewalk on Mt . Vernon Avenue ,
Date: 1-21-88 from Union Street to 21st Street ,
per Plan 7214--GOSNEY CONSTRUCTION
Synopsis of Previous Council action: /7-Y " V
June , 1986 --- Allocation of $21 ,600 approved in 1986/87
CDBG Program.
3-23-87 --- Plans approved and authorization granted to
advertise for bids .
11-16-87 -- Resolution 87-408 adopted , awarding contract to
Gosney Construction for the low bid price of
$17 ,500 .00 .
Recommended motion:
1 . That Change Order No . One to the contract with Gosney
Construction for installation of sidewalk along Mt .
Vernon Avenue per Plan No . 7214 , be approved ; authorizing
the Contractor to remove & replace 196 sq . ft . of existing
sidewalk for a net increase in the contract price of
$980 .00 , from $17 ,500 . 00 to $18 ,480 . 00 .
2 . That the work be approved & accepted and that final
payment be authorized at the expiration f the lien period .
cc : Ray Schweitzer
Warren Knudson -
Ken Henderson
'Signature
Contact person: Roger G . H a r d g r a v e Phone: 5025
Supporting data attached: Staff Report , C C O No . One Ward: 1
FUNDING REQUIREMENTS: Amount: $1 ,848 (Retention )
Source: (Acct. No.) 121-544-57564
_(Acct. Description)_ Sidewalks , Mt . Vernon Avenue -
Union to 21st Street
—. - _.__ ---- - - - - - - --- __._ -- ---- --- Finance:
Council Notes:
75-0262 Agenda Item No. Ly
CA OF SAN- RNARD1 - REOUE*T FOR COUNCIL AC) iON
STAFF REPORT
This contract covers the fill - in of parkway areas along
Mt . Vernon Avenue . During construction , it was determined that
portions of the existing sidewalk had deteriorated and would not
align with the new construction .
Change Order No . One will authorize the Contractor to re-
move and replace 196 sq . ft . of existing concrete sidewalk for
the unit price of $5 . 00/sq . ft . , for an increase in the contract
price of $980 .00 , from $17 , 500 .00 to $18 ,480 . 00 . This project
includes $2 ,800 .00 in contingencies , which can be used to finance
this extra work . We recommend that Change Order No . One be
approved .
All work under this contract was satisfactorily completed
as of 1-20-88 . The project was awarded for the low bid price of
$17 , 500 . 00 . Change Order No . One will increase the contract
price by $980 . 00 .
The actual final contract price is $18 ,480 . 00 , due to
Change Order No . One .
We recommend that the work be approved and accepted and
that final payment be authorized at the expiration of the lien
period .
1-21-88
Date: 1-4-88
^roject: SIDEWALK FILL-IN ALONG MT. VERNON DR.
Pian No. 7214 File No. 7.3727
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO, CALIFORNIA
CONTRACT CHANGE ORDER NO. _0L
(Change necessitated because of field conditions)
T0:
GOSNEY CONSTRUCTION
P.O. BOX 831
BLOOMINGTON, CA 92316
Gentlemen:
YOU ARE HEREBY AUTHORIZED AND DIRECTED TO REMOVE AND REPLACE EXISTING
CONCRETE SIDEWALK AS DIRECTED BY THE ENGINEER, (APPROXIMATELY 200 SQ. FT. )
FOR THE UNIT PRQE OF $5.00 PER SO. FT.
Total extra work cost added to contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 1 ,000.00 (EST)
Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 17 �nn_nn
Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .518.500.00 (FST)
Additional time to complete contract due to change order . . . . . . . . . . . . TO BE DETERMINED
CONTRACTOR: CITY OF SAN BERNARDINO:
By:
By:
ROGER G. HAVDGRAVE
r Ti tip c2z,4 Director of Public Works/City Engr.
Accepted Date: - y- � _ Approved Date: