HomeMy WebLinkAbout2015-028 I RESOLUTION NO. 2015-28
2 RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY OF SAN
BERNARDINO AUTHORIZING THE EXECUTION OF AMENDMENT NUMBER
3 TWO TO THE CONSULTANT SERVICES AGREEMENT WITH WILLDAN
4 ENGINEERING FOR PLAN REVIEW, INSPECTION, STORMWATER
MANAGEMENT, FIRE AND LIFE SAFETY PLAN REVIEW, BUILDING OFFICIAL,
5 AND COUNTER SERVICES.
6 BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE
CITY OF SAN BERNARDINO AS FOLLOWS:
7
8 SECTION 1. The City Manager is hereby authorized to execute Amendment Number
9 Two to the Agreement with Willdan Engineering, attached hereto as Exhibit "A" and
10
incorporated herein.
11
SECTION 2. The Director of Finance, or his designee, is hereby authorized to
12
increase Purchase Order No. 1316 in the amount of$180,000.
13
SECTION 3. The authorization to execute the above-referenced agreement is rescinded
14
15 if the agreement is not executed and returned to the Office of the City Clerk within sixty (60)
16 days following the effective date of this Resolution.
17
18
19
20
21
22
23
24
25
I RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF THE CITY OF SAN
BERNARDINO AUTHORIZING THE EXECUTION OF AMENDMENT NUMBER
2 TWO TO THE CONSULTANT SERVICES AGREEMENT WITH WILLDAN
ENGINEERING FOR PLAN REVIEW, INSPECTION, STORMWATER
3 MANAGEMENT, FIRE AND LIFE SAFETY PLAN REVIEW, BUILDING OFFICIAL,
4 AND COUNTER SERVICES.
5 I HEREBY CERTIFY that the foregoing Resolution was duly adopted by the Mayor and
6 Common Council of the City of San Bernardino at a joint regular meeting thereof, held on the
7 17th day of February, 2015, by the following vote, to wit:
8 Council Members: AYES NAYS ABSTAIN ABSENT
9 MARQUEZ X
10 BARRIOS X
11
VALDIVIA _ X
12
SHORETT X
13
NICKEL X
14
JOHNSON X
15
16 MULVIHILL X
17
George Hann ty Clerk
18 T� n
19 The foregoing resolution is hereby approved this day February, 2015.
1
20
21 R. Carey D is, Mayor
City of San Bernardino
22 Approved as to form:
Gary D. Saenz, City Attorney
23
24 By:
25
2015-28
AMENDMENT NUMBER TWO TO CONSULTANT SERVICES AGREEMENT WITH
WILLDAN ENGINEERING
THIS AMENDMENT NUMBER TWO TO CONSULTANT SERVICES AGREEMENT
WITH WILLDAN ENGINEERING ("Amendment") is made between Willdan Engineering
("Company") and the City of San Bernardino (The "City") on February 17, 2015.
WHEREAS,the parties wish to amend the Consultant Services Agreement that was entered into
on October 20, 2014 ("Agreement") to increase the total amount to cover the services requested
for Community Development Services;
NOW THEREFORE, in consideration of the foregoing and for other good and valuable
consideration the receipt and sufficiency of which are hereby acknowledged, the parties hereto
agree as follows:
1. This Amendment is made with respect to the following facts and purposes:
a. On October 20, 2014 the City and Company entered into an amended
agreement entitled "Plan Review, Inspection, Stormwater Management, Fire
and Life Safety Plan Review, Building Official, and Counter Services" with
minor language change between the City of San Bernardino Community
Development and Willdan Engineering for $355,600.
2. Section 2.1 Compensation of the Agreement is hereby amended to increase the total
Amount of the Agreement by $180,000.
3. Except for the changes specifically set forth herein, all other terms and conditions of
the Agreement shall remain in full force and effect.
IN WITNESS THEREOF,the parties hereto have caused this Amendment Number One to
be executed by and through their respective authorized officers, as of the date first above written.
CITY OF SAN BERNARDINO VENDOR
A Municipal Corporation Willdan Engineering
By: By:
Allen Parker, City Manager
APPROVED AS TO FORM:
Gary D. Saenz, City Attorney
2 ka�
2015-28
AMENDMENT NUMBER TWO TO CONSULTANT SERVICES AGREEMENT WITH
WILLDAN ENGINEERING
THIS AMENDMENT NUMBER TWO TO CONSULTANT SERVICES AGREEMENT
WITH WILLDAN ENGINEERING ("Amendment") is made between Willdan Engineering
("Company") and the City of San Bernardino (The "City") on February 17, 2015.
WHEREAS,the parties wish to amend the Consultant Services Agreement that was entered into
on October 20, 2014 ("Agreement")to increase the total amount to cover the services requested
for Community Development Services;
NOW THEREFORE, in consideration of the foregoing and for other good and valuable
consideration the receipt and sufficiency of which are hereby acknowledged,the parties hereto
agree as follows:
1. This Amendment is made with respect to the following facts and purposes:
a. On October 20, 2014 the City and Company entered into an amended
agreement entitled "Plan Review, Inspection, Stormwater Management, Fire
and Life Safety Plan Review, Building Official, and Counter Services" with
minor language change between the City of San Bernardino Community
Development and Willdan Engineering for $355,600.
2. Section 2.1 Compensation of the Agreement is hereby amended to increase the total
Amount of the Agreement by $180,000.
3. Except for the changes specifically set forth herein, all other terms and conditions of
the Agreement shall remain in full force and effect.
IN WITNESS THEREOF,the parties hereto have caused this Amendment Number One to
be executed by and through their respective authorized officers, as of the date first above written.
CITY OF SAN BERNARDINO VENDOR
A Municipal Corp tion Willdan Engineering.,
By: By:
Allen Parker, City Manager
APPROVED AS TO FORM:
Gary D. Saenz, City Attorney
t jLtA