REQUEST FOR COMMISSION/COUNCIL ACTION
From: Roger G. Hardgrave, Dir. Subject: Contract Change Order No. 7
of Public Works/City Engr. Improvements to Mill Commun-
ity Center, per Plan No. 8890--
KIRKLEY DEVELOPMENT, INC.
Date: 09-28 -93
-----------------------------------------------------------------
.. Synopsis of Previous Commission/Council/Committee Action:
12-21-92 - Requests for CDBG financial assistance, in the amount of $2,268.520
as submitted by the Community Development Advisory Committee,
approved.
02-15-93 - Plans approved and authorization granted to advertise for bids.
04-05-93 - Resolution No. 93-103 adopted awarding a contract to Kirkley Develop-
ment for low bid price of $503,220.00.
06-07-93 - CCO #2 approved, for the re-roofing of Mill and Hernandez Community
Centers, at a total cost of $55,133.65.
09-07-93 - CCO #6 approved, for the remodelof existing restroom at Delmann
Heights Community Center, at a total cost of $56,960.00.
09-20-93 - Allocation of supplemental funds in the amount of $5,000.00 approved.
-----------------------------------------------------------------
Recommended Motion:
That Change Order No. 7 to the contract with Kirkley development, Inc:; for
Improvements to the Mill Community Center, in accordance with Plan No. 8890, be
approved; to authorize installment of a rubberized flooring system in the gym
area, at an increase in the contract price of $18,865,0,07 from $623,351.75 to
$642,216.75.
Roger G. H g ve, Dir. of P.W. /C.E.
cc: K Henderson
A. Ramos Timothy us, Agency Administrator
-----------------------------------------------------------------
Contact Person: Roger G. Hardgrave Phone: 5025
Project Area: N/A Ward(s)
Staff Report,
Supporting Data Attached: Contract Change Order No. 7
FUNDING REQUIREMENTS: Amount: # 18,865.00 Source:CDBG-93/94
Budget Authority: Acct. #806-5903
-----------------------------------------------------------------
Commission/Council Notes:
P
Agenda Item No. :
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
APPROVAL OF CONTRACT CHANGE ORDER NO. 7 --
IMPROVEMENTS TO MILL COMMUNITY CENTER
An amount of $14,760 was approved in the 1993/94 Community
Development Block Grant Program, under Account No. 806-5903 , to
finance the cost for installation of a new floor for the gym.
A contract has been awarded for general improvements to several
community centers, including Mill Community Center. In order to
expedite the installation of the new floor, the Contractor was
requested to provide a price quote.
The Contractor submitted a price quote of $18, 865 for the new
floor. A second quote was solicited from another Contractor for
comparison. This second quote was 25% higher than the one for
$18,865. We have reviewed this price quote and determined that it
is fair and reasonable, in view of current pricing trends.
The Department of Parks and Recreation would like for the new floor
to be installed by change order to the current contract, in order
to expedite completion of construction. Completion of all
construction activities will allow the normal recreation programs
to be resumed.
Supplemental funds in the amount of $5, 000 were allocated at the
Council Meeting of 9-20-93 , which increased the available funds to
$19,760.
We recommend that Change Order No. 7 be approved to authorize
installation of the new floor.
9-28-93
C I T Y O F S A N B E R N A R D 'I N O
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
Project: GENERAL IMPROVEMENTS-DELMANN HEIGHTS
File No. : 7.37-81
Plan No. : 8890 -
Date: 9/23/93
CONTRACT CHANGE ORDER NO. SEVEN
TO: KIRKLEY DEVELOPMENT, INC.
35242 Yucaipa Blvd.
Yucaipa, CA 92399
Gentlemen:
You are hereby authorized and directed to perform the following
work:
MILL CENTER
Install a ruberized flooring system (MCP) in the gym area at Mill
Community Center, as directed by the Resident Engineer, for a total
cost of $18,865. 00.
Total Extra Work Cost added to Contract . . . . . . . . .$ _ 18,865.00
Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . .$ 623,351.75
Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 642,216.75
Additional time to complete Contract due to Change Order 20-Working
Days
CONTRACTOR CITY OF SAN BERNARDINO
Accepted Recommended
By: By:
ROGER G. HARDGRAVE DATE
Title: Director of Public Works/City Engr
Date: