HomeMy WebLinkAbout05- Public Works DEVELOPMENT DEPARTMENT OF THE
CITY OF SAN BERNARDINO
REQUEST FOR COMMISSION/COUNCIL ACTION
From: Roger G. Hardgrave, Dir. Subject: Approval of Plans &
of Public Works/City Engr. Authorization to Ad-
vertise for Bids --
Installation of Di-
Date: 8-24-93 agonal Parking on
"E" St. , from 2nd St.
to 6th St. , per Plan
No. 8985
-----------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action:
07-06-92 - San Bernardino Downtown Plan adopted.
07-08-93 - Redevelopment Committee recommended approval.
07-19-93 - Conceptual approval granted for installation of
diagonal parking on a temporary basis, and
authorization granted to have plans "prepared.
-----------------------------------------------------------------
Recommended Motion:
That the plans for installation of temporary improvements for
diagonal parking on "E" Street, from Second Street to Sixth
Street, in accordance with Plan No. 8985, be approved; and the
Director of Public Works/City Engineer be authorized to ad-
vertise for bids .
Rog r G. r grave, Dir. of P.W. /C.E.
cc: Ken Henderson � x'
Timothy Steinhaus, Agency Administrator
-----------------------------------------------------------------
Contact Person: Roger G. Hardgrave Phone: 5025
Project Area: Central City North Ward(s) : 1
Supporting Data Attached: Staff Report
Bond
FUNDING REQUIREMENTS: Amount: $ 25 , 300 Source: Proceeds
Budget Authority:
-----------------------------------------------------------------
Commission/Council Notes:
Agenda Item No. :
• DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Approval of Plans and
Authorization to Advertise for Bids
Diagonal Parking on "E" Street
from Second Street to Sixth Street
Plans for the installation of temporary improvements to provide
diagonal parking on "E" Street have been completed by the Engi-
neering Division and the project is ready to be advertised for
bids. These improvements are to serve as a six (6) month trial
period.
The plans provide, in general, that diagonal parking spaces be
delineated with paint, for the trial period. If it is decided to
make this arrangement permanent, curbed islands with landscaping
will be installed. These plans have been prepared in accordance
with the adopted San Bernardino Downtown Plan, prepared by
Project for Public Spaces (PPS) .
Below is an estimate of the total project cost:
Construction Contract $ 20 , 000
Engineering & Inspection (W.O. # ) 2, 000
Sub-Total $ 22 ,000
Contingencies (150) ± 3, 300
TOTAL ESTIMATED PROJECT COST $ 25,300
All costs incurred for this project will be financed from bond
proceeds.
Another contract will be needed for installation of landscaping,
as depicted in the San Bernardino Downtown Plan.
8-24-93