HomeMy WebLinkAboutS4- Public Works CIT`9f OF SAN BERNARDINO REQUEST FOR COUNCIL ACTION
File No 7 . 30-10
From: ROGER G. HARDGRAVE Subject: Contract Change Order No. 2 -
Passenger Terminal Access Roads
Dept: Public Works ORIGINAL & Parking Facilities - San
Bernardino International Airport,
Date: 4-24-96
per Plan No. 9053 --
RIVERSIDE CONSTRUCTION
Synopsis of Previous Council action:
10-04-93 - Resolution No. 93-382 adopted authorizing the Mayor to
execute an application to the Economic Development Ad-
ministration for a grant.
03-21-94 - Resolution No. 94--68 adopted authorizing execution of
approval and award of grant.
04--03-95 - Resolution No. 95--92 adopted authorizing Mayor to execute
the amended grant application to EDA to finance road and
parking lot improvements .
10--02-95 - Plans approved and authority granted to advertise for bids .
01-22-96 - Resolution No. 96-41 adopted awarding contract for the low
bid price of $2 , 574 , 928 . 09 .
Recommended motion:
That Change Order No. 2 to the contract with Riverside Construction
for improvement of access roads and parking facilities for the
passenger terminal for the San Bernardino Trade Center & International
Airport, in accordance with Plan No. 9283 , be approved; to authorize
additional compensation to the Contractor for extra work and delays
incurred due to conflicts with utilities not shown on the plans and
credit for deletion of adjusting vaults to grade, at a net increase in
the contract price of $25 , 448 . 31 , from $2 , 579 , 828 . 09 to $2 , 605 , 276 . 40 .
cc: Jim Monger, SBIAA
Bill Bopf , IVDA -
Shauna Clark
Barbara Pachon Signature
Contact person: Gene R. Klatt Phone: 5125
Staff Report, Report
Supporting data attached: of Bids & Resolution Ward: 1
FUNDING REQUIREMENTS: Amount: $25 , 448 . 31 (EDA Grant & SBIAA)
Source: (Acct. No.) 242-362-5504-7038
Acct. Description) Access Roads & Parkin Lot -
S.B. International Airport Terminal Finance: ',
Council Notes:
75-0262 Agenda Item No.
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Page 1 of 2
The plans for improving the access roads and parking lot
to serve the passenger terminals, for the San Bernardino Trade
Center and International Airport, direct the installation of a
42-inch storm drain in Leland Norton Drive.
Upon commencing excavation for this storm drain, the
Contractor encountered numerous obstructions that were not
discovered during a record search by the Consulting Design Engi-
neer and were, therefore, not shown on the plans.
It was required for three water lines to be relocated, to
allow the new storm drain to be installed. Due to the many ob-
structions encountered, the Contractor was directed to dig a
pilot trench along Leland Norton Drive to locate utility
facilities crossing the street. These items of extra work were
done on a time and material basis, in accordance with Section 3
of the Standard Specifications, at an estimated cost of
$19 , 856 . 40 .
About 200 feet of the 42-inch storm drain had to be
removed and re-installed, due to the trench being flooded when a
valve for the irrigation system was inadvertently opened. The
storm drain alignment had to be adjusted at 3 locations where it
was in conflict with a concrete encased 33-KVA electrical duct.
These items of extra work were done on a time and materials
basis, at an estimated cost of $6 , 461 . 02 .
Portions of concrete encased 10-KVA electrical ducts had
to be removed at 7 locations , in order to allow the 42-inch storm
drain to be installed in accordance with the plans. Also, these
ducts had to be removed at 3 locations where they were in
conflict with the storm drain laterals . The Contractor' s forces
were delayed while these removals were being done. The items of
extra work were done on a time and materials basis , at an esti-
mated cost of $16 , 463 . 70 .
The Contractor' s forces were precluded from working
during the times that utility facilities in conflict were being
removed or relocated. This lost time is considered a right-of-
way delay in the Standard Specifications, and amounted to
$5 , 087 . 19 (which represents 1/2 of actual rental rates) .
About 300 feet of 6-inch conduit, service panel, and
electrical cables were installed, in order to provide service to
the pump station for the remediation effort, after the existing
vaults are abandoned. This extra work was done on a time and
material basis, at the agreed upon price of $17 , 580 . 00 .
The plans direct the Contractor to adjust 5 existing
electrical vaults to the new grade.
4-24-96
75-0264
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Page 2 of 2
Installation of the 300 feet of 6-inch conduit, as
described above, will allow these vaults to be abandoned.
Therefore, adjusting these vaults to grade can be deleted from
the contract, for an agreed upon credit of ($25 , 000 . 00) .
The plans direct the Contractor to adjust an estimated
amount of 5 existing telephone vaults to the new grade. It has
been determined that these vaults can be abandoned, which will
allow the adjusting to grade to be deleted from the contract, at
an agreed upon credit of $1 , 500 each, or ($7 ,500 . 00) .
One combined electrical/telephone vault can also be
abandoned, which will allow adjustment of this structure to the
new grade to be deleted from the contract, at an agreed upon
credit of ($7 , 500 . 00) .
Funds to finance the net additional costs authorized by
Change Order No. Two will be provided from the following sources :
Economic Development Administration Grant - 750
Inland Valley Development Agency - 250
All costs incurred will be charged to Account No. 242-
362-5504-7038 , and billed to the grant and IVDA. No City funds
will be used to finance any portion of the additional costs .
We recommend that Change Order No. Two be approved.
4-24-96
FEDERAL PROJECT NO. 07-49-02680.01
CONTRACT CHANGE ORDER
CHANGE ORDER NO. 2
DATE: 4/17f96
Agreement Date: 2/12f96
NAME OF PROJECT: PASSENGER TERMINAL ACCESS ROADS AND PARKING
FACILITIES; SAN BERNARDINO INTERNATIONAL AIRPORT
OWNER: CITY OF SAN BERNARDINO
CONTRACTOR: RIVERSIDE CONSTRUCTION
The following extra work is to be performed, as directed by the
Resident Engineer, and the following changes are hereby made to the
CONTRACT DOCUMENTS:
(1) Relocation of 3-existing 12-inch water mainlines in conflict
with the new 42-inch storm drain, and excavating a pilot
trench for locating unmarked utility lines on Harry Sheppard
and Leland Norton prior to the installation of the new 12-inch
water mainline, on a time and material basis, at a total cost
of $ 19,856.40.
(2) Pull out and relay 42-inch storm drain pipe that was misaligned
due to irrigation water flooding the trench, and perform work
to realign the pipeline at three locations where a conflict
with an existing 33 KVA concrete duct prevented the
installation of the storm drain as indicated on the plans, on
a time and material basis, at a total cost of $ 6,461.02 .
(3) Removal of 7-existing 10 KVA and telephone concrete encased
ducts in direct conflict with the new 42-inch storm drain, and
3-existing 10 KVA concrete encasement in conflict with the
installation of the storm drain laterals, and lost production
time in the initial excavation of the storm drain mainline and
lateral trenches, on a time and material basis, at a total cost
of $ 16,463 .70 .
Page 1
Contract Change Order No. 2
07-49-02680 .01
(4) Right-of Way Delay due to work stoppage during remediate of
the utility conflicts in the installation of the 42-inch storm
drain mainline, at a total cost of $ 5,087 . 19 .
(5) Install approximately 300-lineal feet of 6-inch conduit,
service panel, electrical cable and tie into the SCE Vault
located on Del Rosa Avenue, at the agreed price of $ 17,580.00.
(6) Delete the adjusting to grade of an estimated 5-Electrical
vaults per Contract Bid Item No. 25, at $ 5,000.00 each, for a
total credit of <$ 25,000.00>.
(7) Delete the adjusting to grade of an estimated 5-Telephone
vaults per Contract Bid Item No. 24, at $ 1,500.00 each, for a
total credit of <$ 7,500.00.>
(6) Delete the adjusting to grade of an estimated 1-Combined
Electrical and Telephone vault per Contract Bid Item No. 83, at
$ 7,500 .00 each, for a total credit of <$ 7,500 .00>.
JUSTIFICATION:
During the installation of the new storm drain system,
numerous obstructions were discovered that resulted in a delay
in the installation of the new storm drain system, these
included concrete encased electrical and telephone ducts,
existing water mainlines, as well as misc. utilities that were
in direct conflict with the installation of the new storm
drain system. Some such as the 33 RVA electrical transmission
ducts could not be moved so the storm drain pipe had to be
removed and relayed in order to clear the line, water lines had
to be either caped off or adjusted to clear the storm drain,
additionally, on three occasions the storm drain pipe needed to
be removed and reinstalled due to the flooding of the trench
that occurred as a result of caretaker personnels unauthorized
opening up water gate valves on three occasions which flooded
the trench and resulted in sections of the storm drain pipe
being removed and reinstalled.
Since it was obvious that there were many potential
obstructions that affected the installation of the storm
drain system, it was decided that a pilot trench would be dug
prior to the installation of the new water mainline. As a
Page 2
Contract Change Order No. 2
07-49-02680.01
result, 30 obstructions were discovered in direct conflict at
the location and elevation where the new waterline was to be
installed, however, since this condition was known on the
onset, the contractor was able to make the adjustments to the
elevation of the new waterline prior to the installation,
avoiding all of the obstructions. What would have been a
costly delay and resulted in additional work and extra costs
was prevented, and the only additional costs incurred were for
the excavation of the pilot trench.
There was an additional cost of the installation of a
service to the existing pump and treat plant on Rialto Avenue,
installation an electrical service to this location will enable
the abandonment of many of the existing electrical and
telephone vaults.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $ 2 ,574,928.09
CURRENT CONTRACT PRICE adjusted
by previous change Order: $ 2 ,579,828.09
The CONTRACT PRICE due to this CHANGE ORDER will be increased by:
Change Order will be increased by
an estimated- $ 25,448.31
The NEW ESTIMATED CONTRACT PRICE including this CHANGE ORDER will
be $ 2 ,605,276.40
CHANGE TO CONTRACT TIME: 14 Calendar Days
The CONTRACT TIME will be (increased) by NONE calendar days.
The date for completion of all work will be 7/20196
Page 3
Contract Change Order No. 2
07-49-02680.01
Approvals Required:
To be effective, this Order must be approved by the Federal agency
if it changes the scope or objective of the PROJECT, or as may
otherwise be required by the SUPPLEMENTAL GENERAL CONDITIONS.
Accepted by:
Riverside Construction Date
Requested by:
Steven Enna, Construction Engineer Date
Recommended by:
Jim Monger Date
San Bernardino International Airport Authority
Recommended by:
William Bopf Date
Inland Valley Development Agency
Recommended by:
Roger G. Hardgrave Date
Director of Public Works/City Engineer
Economic Development Administration
Approved by:
Date
Page 4