REQUEST FOR COMMISSION/COUNCIL ACTION
From: Roger G. Hardgrave, Dir. Subject: Approval of Plans &
of Public Works/City Engr. Authorization to Ad-
vertise for Bids - -
Installation of
Date: October 2 , 1997 Streetscape Improve-
ments on Base Line
Street, per Plan
No. 9733
-----------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action:
June, 1994 - Allocation of $218 , 915 , in 1994/95 CDBG Program,
approved.
10-21-96 - Allocation of $179 , 448 , in 1996/97 CDBG Program,
approved.
05-05-97 - Application for $262 , 000 , from 1997/98 CDBG Program,
denied.
----------------------------------------------------------------
Recommended Motion:
That the plans for installation of streetscape improvements on
Base Line Street, from "D" Street to Waterman Avenue, in
accordance with Plan No. 9733 , be approved; and the Director of
Public Works/City Engineer be authorized to a tine for bids .
CC. R. Winkler RogeirG. Her gra e, Dir. of P.W. /C.E.
N. Owens /
Timothy Ste7nhaus, Agency Administrator
-----------------------------------------------------------------
Contact Person: Roger G. Hardgrave Phone: 5025
Project Area: N/A Ward(s) : 2
Supporting Data Attached: Staff Report
1996/97 CDBG
FUNDING REQUIREMENTS: Amount: $ 178 ,000 Source: Program
Budget Authority: Acct. #80685
----------------------------------------- ----------------
Commission/Council Notes:
•
4
AdVAIL DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Approval of Plans and
Authorization to Advertise for Bids
for Streetscape Improvements
on Base Line Street
Plans for installation of streetscape improvements on Base Line
Street, from "D" Street to Waterman Avenue, have been completed
and the project is ready to be advertised for bids . The project
consists, in general , of installing an automated irrigation
system and trees.
A
Below is an estimate of the total project cost:
Construction Contract $ 134 ,500
Engineering & Inspection (W.O. #5031) 27 , 000
Sub-Total $ 161 , 500
Contingencies (100) ± 16 ,500
TOTAL ESTI14ATED PROJECT COST $ 178 ,000
All costs incurred for this project will be charged to the
$179 , 488 allocated in the 1996/97 CDBG Program, under Account No.
80685 .
We recommend that the plans be approved and authorization granted
to advertise for bids.
10-02-97