A..� REQUEST FOR COMMISSION/COUNCIL ACTION
From: Roger G. Hardgrave, Dir. Subject: Approval of Contract
of Public Works/City Engr. Change Order No. 4 -
Expansion of Pioneer
Cemetery, per Plan
Date: 2-08-93 No. 8593 --
BOB BRITTON, INC.
-----------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action:
June, 1988 - Allocation of $50, 383 approved in 1988/89 Budget
under Account No. 244-364-57675, for acquisition of
land for future expansion. `
02-04-91 -- Allocation of $102 , 177 , from tax allocation bond
proceeds, for acquisition of land and improvements,
approved.
07-06-92 -- Plans for Phase I approved and authorization granted
to advertise for bids . (Cont. on second page)
----------------------------------------------------------------
Recommended Motion:
That Change Order No. Four to the contract with Bob Britton, Inc.
for expansion of Pioneer Cemetery, Phase I, in accordance with
Plan No. 8593 , be approved; to expand the scope of the contract
to include the remaining frontage along 7th St. , at an estimated
increase in the contract price of $92, 037 . 32; from $91 , 481 . 66 to
$183, 518 . 98 . :�7
cc: K. Henderson
S. Clark Roger H rdgrav , ' r. of P.W. /C.E.
D. Ustation
A. Ramos
Tim ei aus, Agency Administrator
-----------------------------------------------------------------
Contact Person: Roger Hardgrave Phone: 5025
Project Area: Central City Ward(s) : 1
Staff Report,
Supporting Data Attached: CCO #4
Tax Allocation Bond
FUNDING REQUIREMENTS: Amount: $ 92, 037 . 32 Source: Proceeds
Budget Authority:
-----------------------------------------------------------------
Commission/Council Notes:
Agenda Item No. :_�
File No. 6 . 26-3
Synopsis of Previous Commission/Council Action (Cont.)
10-05-92 -- Resolution No. 5345 adopted, awarding a contract to
Bob Britton, Inc. for the low bid price of
$85 , 000 . 20 , and approving Contract Change Order No.
1 . The transfer of $15, 817 from Acct. 244-000-30405
to Acct. 244-364-57675 , approved.
01-20-93 -- Supplemental funding, in the amount of $120 , 000
approved.
2-08-93
L,
'.le No. 6. 26-3
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Expansion of Pioneer Cemetery
The expansion of Pioneer Cemetery was divided into two phases. A
contract has been awarded to Bob Britton, Inc. , for Phase I,
which is basically the northwest corner of Waterman Avenue and
Seventh Street.
There is a space of about 350 ' between Phase I and the original
portion of Pioneer Cemetery. This section was not included in
Phase I, due to the necessity to keep the Little League Baseball
field in operation. However, this field is no longer a factor,
since it has been taken out of service.
Change Order No. 4 will enlarge the scope of our contract with
Bob Britton, Inc. to include the remaining frontage along 7th
Street. The total estimated cost of Contract Change Order No. 4
is $92, 037 . 32. This estimate is based upon the low bid unit
prices, except for Rough Grading and Demolition of Existing
Facilities, which have been negotiated with the Contractor.
Supplemental funding, in the amount of $120 , 000, was provided at
the Commission meeting of 1-20-93 to finance the cost for the
extra work required to extend the improvements along the entire
frontage of 7th Street.
We recommend that Change Order No. 4 be approved.
URGENCY CLAUSE:
Approval of Change Order No. 4 is needed at the Commission
meeting of 2-15-93 , in order to allow the Contractor to continue
working and avoid the possibility of another move-in charge.
I �
C I T Y O F 8 A N B E R N A R D I N O
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
Project: Pioneer Cemetery Expansion-Phase 1
File No. : 6.26-3
Plan No. : 8593
Date: 2/5/93
CONTRACT CHANGE ORDER NO. FOUR
TO: BOB BRITTON, INC.
171 S. Waterman Avenue
San Bernardino, CA 92408
Gentlemen:
You are hereby authorized and directed to perform the following
work on phase 11 of Pioneer Cemetery, at unit costs that were bid
for phase 1, the work to be performed is as follows:
1) Rough Grading 1 L.S. $13 , 120.00 $13, 120. 00
2) Rolled curb
& gutter 450 L.F. @ $ 7.60 $ 3,420.00
3) P.C.C. Header 352 L.F. @ $ 4. 50 $ 1,584.00
4) Conc. Blk/Wrought
Iron Fencing 352 L.F.@ $ 32.00 $11,264.00
5) Irrigation System 71, 100 S.F.@ $ . 1826/S.F. $12,983 .59
6) Hydrospraying Lawn 71, 000 S.F. @ $ .2070/S.F. $14,718.53
7) 6' Chain Link fence 352 L.F.@ $ 11.60 $ 4, 083 .20
8) 12' Opening Double
Gate 6' High 1 L.S. $ 824 . 00 $ 824 . 00
9) Rolling Gate 1 L.S. $ 1, 000.00 $ 1,000. 00
10) Demolition of Exist-
ing Facilities 1 L.S. $29, 040. 00 $29,040.00
Estimated Total Extra Work Cost added to Contract $ 92 .037.32
Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . . .$ 91,481.66
Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 183,518.98
Additional time to complete Contract due to Change Order 40 Working
Days
CONTRACTOR CITY OF SAN BERNARDINO
Accepted Recommended
By: By:
ROGER G. HARDGRAVE DATE
Director of Public Works/City Engr
Title:
Date: