Loading...
HomeMy WebLinkAbout15- Redevelopment Agency DEVELOPMENT DEPARTMENT OF THE CITY OF SAN BERNARDINO A..� REQUEST FOR COMMISSION/COUNCIL ACTION From: Roger G. Hardgrave, Dir. Subject: Approval of Contract of Public Works/City Engr. Change Order No. 4 - Expansion of Pioneer Cemetery, per Plan Date: 2-08-93 No. 8593 -- BOB BRITTON, INC. ----------------------------------------------------------------- Synopsis of Previous Commission/Council/Committee Action: June, 1988 - Allocation of $50, 383 approved in 1988/89 Budget under Account No. 244-364-57675, for acquisition of land for future expansion. ` 02-04-91 -- Allocation of $102 , 177 , from tax allocation bond proceeds, for acquisition of land and improvements, approved. 07-06-92 -- Plans for Phase I approved and authorization granted to advertise for bids . (Cont. on second page) ---------------------------------------------------------------- Recommended Motion: That Change Order No. Four to the contract with Bob Britton, Inc. for expansion of Pioneer Cemetery, Phase I, in accordance with Plan No. 8593 , be approved; to expand the scope of the contract to include the remaining frontage along 7th St. , at an estimated increase in the contract price of $92, 037 . 32; from $91 , 481 . 66 to $183, 518 . 98 . :�7 cc: K. Henderson S. Clark Roger H rdgrav , ' r. of P.W. /C.E. D. Ustation A. Ramos Tim ei aus, Agency Administrator ----------------------------------------------------------------- Contact Person: Roger Hardgrave Phone: 5025 Project Area: Central City Ward(s) : 1 Staff Report, Supporting Data Attached: CCO #4 Tax Allocation Bond FUNDING REQUIREMENTS: Amount: $ 92, 037 . 32 Source: Proceeds Budget Authority: ----------------------------------------------------------------- Commission/Council Notes: Agenda Item No. :_� File No. 6 . 26-3 Synopsis of Previous Commission/Council Action (Cont.) 10-05-92 -- Resolution No. 5345 adopted, awarding a contract to Bob Britton, Inc. for the low bid price of $85 , 000 . 20 , and approving Contract Change Order No. 1 . The transfer of $15, 817 from Acct. 244-000-30405 to Acct. 244-364-57675 , approved. 01-20-93 -- Supplemental funding, in the amount of $120 , 000 approved. 2-08-93 L, '.le No. 6. 26-3 DEPARTMENT OF PUBLIC WORKS STAFF REPORT Expansion of Pioneer Cemetery The expansion of Pioneer Cemetery was divided into two phases. A contract has been awarded to Bob Britton, Inc. , for Phase I, which is basically the northwest corner of Waterman Avenue and Seventh Street. There is a space of about 350 ' between Phase I and the original portion of Pioneer Cemetery. This section was not included in Phase I, due to the necessity to keep the Little League Baseball field in operation. However, this field is no longer a factor, since it has been taken out of service. Change Order No. 4 will enlarge the scope of our contract with Bob Britton, Inc. to include the remaining frontage along 7th Street. The total estimated cost of Contract Change Order No. 4 is $92, 037 . 32. This estimate is based upon the low bid unit prices, except for Rough Grading and Demolition of Existing Facilities, which have been negotiated with the Contractor. Supplemental funding, in the amount of $120 , 000, was provided at the Commission meeting of 1-20-93 to finance the cost for the extra work required to extend the improvements along the entire frontage of 7th Street. We recommend that Change Order No. 4 be approved. URGENCY CLAUSE: Approval of Change Order No. 4 is needed at the Commission meeting of 2-15-93 , in order to allow the Contractor to continue working and avoid the possibility of another move-in charge. I � C I T Y O F 8 A N B E R N A R D I N O DEPARTMENT OF PUBLIC WORKS ENGINEERING DIVISION Project: Pioneer Cemetery Expansion-Phase 1 File No. : 6.26-3 Plan No. : 8593 Date: 2/5/93 CONTRACT CHANGE ORDER NO. FOUR TO: BOB BRITTON, INC. 171 S. Waterman Avenue San Bernardino, CA 92408 Gentlemen: You are hereby authorized and directed to perform the following work on phase 11 of Pioneer Cemetery, at unit costs that were bid for phase 1, the work to be performed is as follows: 1) Rough Grading 1 L.S. $13 , 120.00 $13, 120. 00 2) Rolled curb & gutter 450 L.F. @ $ 7.60 $ 3,420.00 3) P.C.C. Header 352 L.F. @ $ 4. 50 $ 1,584.00 4) Conc. Blk/Wrought Iron Fencing 352 L.F.@ $ 32.00 $11,264.00 5) Irrigation System 71, 100 S.F.@ $ . 1826/S.F. $12,983 .59 6) Hydrospraying Lawn 71, 000 S.F. @ $ .2070/S.F. $14,718.53 7) 6' Chain Link fence 352 L.F.@ $ 11.60 $ 4, 083 .20 8) 12' Opening Double Gate 6' High 1 L.S. $ 824 . 00 $ 824 . 00 9) Rolling Gate 1 L.S. $ 1, 000.00 $ 1,000. 00 10) Demolition of Exist- ing Facilities 1 L.S. $29, 040. 00 $29,040.00 Estimated Total Extra Work Cost added to Contract $ 92 .037.32 Previous Contract Price . . . . . . . . . . . . . . . . . . . . . . . . . .$ 91,481.66 Amended Cost Price . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$ 183,518.98 Additional time to complete Contract due to Change Order 40 Working Days CONTRACTOR CITY OF SAN BERNARDINO Accepted Recommended By: By: ROGER G. HARDGRAVE DATE Director of Public Works/City Engr Title: Date: