HomeMy WebLinkAbout14- Redevelopment Agency DEVELOPMENT DEPARTMENT OF THE
CITY OF SAN BERNARDINO
REQUEST FOR COMMISSION/COUNCIL ACTION
From: Roger G. Hardgrave, Dir. Subject: Approval of Plans &
of Public Works/City Engr. Authorization to Ad-
vertise for Bids -
Main Street Revitali-
Date: 2-09-93 zation Program -Phase
II , per Plan No. 8812
-----------------------------------------------------------------
Synopsis of Previous Commission/Council/Committee Action:
07-06-92 - Director of Public Works/City Engineer directed to
prepare appropriate documents for Phase II improve-
ments, of the Main Street Revitalization Program, in
accordance with Plan No. 8484 , and to advertise for
bids.
-----------------------------------------------------------------
Recommended Motion:
That the plans for construction of improvements under the Main
Street Revitalization Program - Phase II , in accordance with Plan
No. 8812 , be approved, and the Director of P lic Works/City
Engineer be authorized to ad tine for bid .
R r G. H11 rdg e, Dir. of P.W. /C.E.
cc: K. Henderson
Timothy St inha6us, Agency Administrator
-----------------------------------------------------------------
Contact Person: Roger G. Hardgrave Phone: 5025
Project Area: CCN - Main Street Ward(s) : 1
Supporting Data Attached: Staff Report
CNN Bond
FUNDING REQUIREMENTS: Amount: $ 1 , 198 , 000 Source: Issue
Budget Authority: 650-0105 �;;�,�� j
Commission/Council Notes:
Agenda Item No. : j '
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
Main Street Improvements - Phase II
Authorization was granted at the Commission meeting of 7-6-92 for
contract documents to be prepared for Phase II of the Main Street
Revitalization Program. Phase II consists, in general, of
installing streetscape improvements on "D" Street, from Second
Street to Sixth Street, Court Street, from "E" Street to
Arrowhead Avenue, and Third Street, from "D" Street to Arrowhead
Avenue.
Below is an estimate of the total project cost.
Construction Contract $ 1 ,076 , 002
Engineering & Inspection (W.O. #1928) 36, 100
1-inch Water Meter Fees (3) 17, 955
Sub-Total $ 1 , 130,057
Contingencies (6%) ± 67 , 943
TOTAL ESTIMATED PROJECT COST $ 1,198,000
An amount of $1 , 205 , 000 is available, under Account No. 650-0105
to finance the costs incurred for Phase II of the Main Street
Revitalization Program.
We recommend that the plans be approved and authorization granted
to advertise for bids.