HomeMy WebLinkAbout11- Facilities Management CITY OF SAN RERNARDINO - REQUEST FOR COUNCIL ACTION
From: James Sharer, Director Subject: Resolution authorizing the execution of a
contract with George Bryant Construction, Inc. for the
Dept: Facilities Management installation of an above ground fuel tank at Fire Station
I ri t r r 233, 2121 North Medical Center Drive in San
Date: March 1, 2000 R I O j " Y�L Bernardino.
Synopsis of Previous Council Action
April 19, 1999 —Approved allocation of$30,000 to CDBG Funds Project No. 99-0043
Recommended Motion:
Adopt Resolution.
James . Sharer
i
Contact person: James Sharer Phone: 384-5244
Supporting data attached: Staff Report, Bid Sheet Ward(s): 6
FUNDING REQUIREMENTS:
Amount: $28,755.60
Source: CDBG Program#99-0043
Finance
Council Notes:
Agenda Item No.
3/ao1 a000
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
SUBJECT
Resolution authorizing the execution of a contract with George Bryant Construction, Inc. for the installation of
an above ground fuel tank at Fire Station 233, 2121 North Medical Center Drive in San Bernardino.
BACKGROUND
On February 15, 1999, the Mayor and Common Council approved a project to install an above ground fuel tank
at Fire Station 233. Using CDBG funds. The City removed the in-ground fuel storage tank at this location in
December 1998,to comply with federal laws. This tank will allow the Fire Department to have fuel on the
northwest side of the City to replenish their fire apparatus on an ongoing basis.
The project consists of the installation of a 2000-gallon above ground concrete fuel tank. The project also
includes a fuel dispenser and all required peripheral items to make a complete installation in compliance with all
municipal, state and federal codes.
Requests for Bids were mailed to six vendors plus advertised in the newspaper and on the internet. Three bids for
the project were received on February 17, 2000. The bids ranged from $25,005.60 to $31,880, with George
Bryant Construction, Inc. being the lowest bidder. There were no local San Bernardino businesses identified that
could perform this work.
Vendor Location Bid Amonnt
George Bryant Construction Alta Loma, CA $25,005.60
Foss Environmental Long Beach, CA $29,204.00
Fleming Environmental Buena Park, CA $31,880.00
The estimated total project cost based on the low bid is as follows:
Construction Contract $25,005.60
Contingencies(15%) 3.750.0
Grand Total $28,755.60
FINANCIAL IMPACT
Funding for this project is provided in CDBG Projects No. 99-0043, in the total amount of$30,000. Therefore,
this project will be 100%reimbursable from the CDBG grant and will be accomplished at no cost to the City.
Invoices will be approved by Facilities Management and then given to EDA to pay from CDBG funds.
RECOMMENDATION
Adopt Resolution.
i
���iN
�IUII��P
o���_a��n��.� � ..
j COPY
1 Resolution No.
2 RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF SAN
3 BERNARDINO AUTHORIZING THE EXECUTION OF A CONTRACT WITH
GEORGE BRYANT CONSTRUCTION, INC., FOR THE INSTALLATION OF AN
4 ABOVE GROUND FUEL TANK AT FIRE STATION 233, 2121 NORTH MEDICAL
CENTER DRIVE IN SAN BERNARDINO.
5
6 BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE
7 CITY OF SAN BERNARDINO AS FOLLOWS:
8
9 SECTION 1. GEORGE BRYANT CONSTRUCTION, INC., is the lowest responsible
10 bidder for the Installation of an above ground fuel tank at Fire Station 233 per Plan No. F00-41.
11 A contract is awarded accordingly to said bidder in a total amount of S25,005.60. Such award shall
12 be effective only upon being fully executed by both parties. All other bids, therefore,are hereby
13
rejected. The Mayor is hereby authorized and directed to execute said contract on behalf of the
C 14
City; a copy of the contract is on file in the office of the City Clerk and incorporated herein by
15
16 reference as fully as though set forth at length.
17 SECTION 2. This contract and any amendment or modifications thereto shall not take
18 effect or become operative until fully signed and executed by the parties and no party shall be
19 obligated hereunder until the time of such full execution. No oral agreements,amendments,
20 modifications or waivers are intended or authorized and shall not be implied from any act or
21 course of conduct of an a
Y party.
22
23 SECTION 3. This resolution is rescinded if the parties to the contract fail to execute it
24 within sixty (60) days of the passage of this resolution.
25
26
27
V 28
�D .
3/Z ) rOC�
1 RESOLUTION OF THE MAYOR AND COMMON COUNCIL OF SAN
BERNARDINO AUTHORIZING THE EXECUTION OF A CONTRACT WITH
2
GEORGE BRYANT CONSTRUCTION, INC., FOR THE INSTALLATION OF AN
3 ABOVE GROUND FUEL TANK AT FIRE STATION 233, 2121 NORTH MEDICAL
CENTER DRIVE IN SAN BERNARDINO.
4
5
6 I HEREBY CERTIFY that the foregoing resolution was duly adopted by the Mayor and
7 Common Council of the City of San Bernardino at a meeting thereof, held on
8 the day of . 2000, by the following vote, to wit:
9
Council Members: Ayes NTvs Abstain Absent
10
ESTRADA
11
12 LIEN
13 MCGINNIS
14 SCIIINETZ
15 SUAREZ
16 ANDERSON _
17 MILLER _
18
19
20 City Clerk
21 The foregoing resolution is hereby approved this day of
2000.
22
23
24 Judith Valles, Mayor
City of San Bernardino
Approved as to form and
Legal content;
26 James F. Penman, City Attorney
27 BY:
28
C
CONTRACT
THIS AGREEMENT, made this 16th day of February
2000, by and between the City of San Bernardino, herein
called "Owner", acting herein through its Facilities
Manager, and George Bryant Construction, Inc.
STRIKE OUT (a corporation)
.. INAPPLICABLE G€D[3CX9{IFl4�f}14Fl6{79�{79UG)!C
TERMS
0
of Alta Loma , County of San Rer.na rd 'no
and State of —CAI i fn - hereinafter
called the "Contractor" .
WITNESSETH: That for and in consideration of the payments
and agreements hereinafter mentioned, to be made and
performed by the OWNER, the CONTRACTOR hereby agrees with
the OWNER to commence and complete the construction
described as :
ABOVE GROUND FUEL STORAGE TANK
AT
FIRE STATION #3
PER PROJECT NO. F00-41
Hereinafter called the project, for the sum of _Twenty-five
thousan-five dollars & sixt cents dollars
(525. 005. 60 ) and all extra work in connection
therewith, under the terms as stated in the General and
Special Conditions of the Contract; and at his (its or
their) own proper cost and expense to furnish all the
materials, supplies, machinery, equipment, tools,
superintendence, labor, insurance, and other accessories
and services necessary to complete the said project in
C-I
accordance with the conditions and prices state in the
Proposal, the General Conditions, Supplemental General '
Conditions and Special Conditions of the Contract, the
Plans which include all maps, plans, blueprints, and other
drawings and documents therefore, as prepared by the City ,
of San Bernardino, herein entitled the Facilities Manager„
and as enumerated in Article 2 of the Supplemental General
Conditions, all of which are made a part thereof and
collectively evidence and constitute the contract .
The Contractor hereby agrees to commence work under this
contract on or before a date to be specified in a written
"Notice to Proceed" of the Owner and to fully complete the
project within 90 working days thereafter. The Contractor
further agrees to pay, as liquidated damages, the sum of
$100 . 00 for each consecutive calendar day in finishing the
work in excess of the number of working days prescribed
above.
C-2
r
AGREEMENT: ABOVE GROMM FUEL STORAGE TANK AT FIRE
STATION Y3 e
IN WITNESS WHEREOF, the parties of these presents have
executed this contract in four (4) counterparts, each o' ,
which shall be deemed an original in the year and day first
above mentioned.
City of San Bernardino
(SEAL) (Owner)
ATTEST:
BY:
City Clerk Mayor
(SEAL).
George Bryant Construction, Inc.
Contractor
BY: Nisr
Secretary 0 ,rGEE.
O� ♦ Z
U C
L 7
Witness
9 yq2� °j
. i ST
Address and Zip Code
NOTE: Secretary of the Owner should attest . If Contractor
is a corporation, Secretary should attest.
Approved as to form and
Legal content:
JAMES F. PENMAN, City Attorney
By:
C-3
accordance with the conditions and prices stateod in the
Proposal, the General Conditions, Supplemental General
Conditions and Special Conditions of the Contract, the Plans
which include all maps, plans, blueprints ther drawings
and documents therefore, as prepared by ficials o the City
of San Bernardino, herein entitled the Faci i anager, and
so' ' enumerated in Article 2 of the Supplemental General
Conditions, all of which are made a part thereof and
collectively evidence and constitute the contract.
The Contractor hereby agrees to commence work under this
contract on or before a date to be specified in a written
"Notice to Proceed" of the Owner and to fully complete the
project within 9Q working days thereafter. The Contractor
further agrees to pay, as liquidated damages, the sum of
$100 .00 for each consecutive calendar day in finishing the
work in excess of the number of working days prescribed above,
C because pursuant to Civil Code Section 1671(d) , it would be
impracticable or extremely difficult to fix the amount of J
PAC, actual damages for a breach of this Agreement.
Fntrredinto Rer_ord at �2 r
v0evrms Mtg:
'tem _
Clay ClerkICOC Secy
City of San Bernardino
z Marc, Z01 4—aoo
Madif'd Ate. c-2
accordance with the conditions and prices stated in the
Proposal, the General Conditions, Supplemental General
Conditions and Special Conditions of the Contract, the Plans
which include all maps, plans, blueprints, and other drawings
and documents therefore, as prepared by officials of the City
of San Bernardino, herein entitled the Facilities Manager, and
as enumerated in Article 2 of the Supplemental General
Conditions, all of which are made a part thereof and
collectively evidence and constitute the contract.
The Contractor hereby agrees to commence work under this
contract on or before a date to be specified in a written
"Notice to Proceed" of the Owner and to fully complete the
project within 90 working days thereafter. The Contractor
further agrees to pay, as liquidated damages, the sum of
5100 . 00 for each consecutive calendar day in finishing the
work in excess of the number of working days prescribed above,
because pursuant to Civil Code Section 1671(d) , it would be
impracticable or extremely difficult to fix the amount of
actual damages for a breach of this Agreement.
C-2