HomeMy WebLinkAbout06- Public Works CITY OF SAN BERN/ ZDINO - REQUEST F( ; COUNCIL ACTION
File No. 4.42-26
Approval of Plans & Authorization
From: ROGER G. HARDGRAVE Subject: to Advertise for Bids - Installa-
tion of Storm Drain and Paving on
Dept: - Public Works Pepper Avenue, from Rialto Avenue
to East Rialto Channel, per Plan
Date: 4-01-94 No. 9086
Synopsis of Previous Council action:
June, 1993 - Allocation of $176 , 000 in 1993/94 Storm Drain
Construction Fund Budget, under Account No. 248-368-
57850, approved.
Recommended motion:
1 . That the transfer of $27,000 from Account No. 129-309-57826,
"Waterman Avenue, from Sixth St. to Ninth St. " to Account No.
129-309-57853, "Pepper Avenue Widening, from Rialto Avenue to
East Rialto Channel, " be approved.
2 . That the plans for installation of a storm drain and paving on
Pepper Avenue, from Rialto Avenue to East Rialto Channel, be
approved; and the Director of Public Works/City E eer be
authorized to advertise for bids.
cc: Shauna Clark Sl-gdafure
Contact person: Roger G. Hardgrave Phone: 5025
Supporting data attached: Staff Report Ward: 3
FUNDING REQUIREMENTS: Amount: $184 ,000 } Cent Sales Tax - Local Funds
Storm Drain Construction Funds
Source: (Acct. No.) 129-309-57853 & 248-368-57850
Acct. Description) Pepper -Avenue Widening and Storm
Drain, from Rialto Avenue to East Rialto Channel
Finance
Council Notes:
75.D262 Agenda Item No
CITY OF SAN BERN! ;DING - REQUEST P I COUNCIL ACTION
STAFF REPORT
Plans for the installation of a storm drain and
additional paving on Pepper Avenue, from Rialto Avenue to East
Rialto Flood Control, have been prepared and the project is ready
to be advertised for bids . The project will consist, in general ,
of installing a 36-inch storm drain and 12 feet of additional
paving, to provide the second southbound traffic lane.
Below is an estimate of the total project cost:
Construction Contract
Storm drain $ 98, 584
Pavement Widening 41, 810
$ 140, 394
Engineering & Inspection (W.O. 1515) 20 ,000
Sub-Total $ 160, 394
Contingencies (158) ± 23, 606
TOTAL ESTIMATED PROJECT COST $ 184,000
An amount of $176, 000 was allocated in the 1993/94 Storm
Drain Construction Fund Budget, under Account No. 248-368-57850 ,
to finance the costs that will be incurred for installation of
the storm drain. It is recommended that the transfer of $27,000 ,
from Account No. 129-309-57826, "Waterman Avenue, Sixth Street to
Ninth Street, " to Account No. 129-309-57853, "Pepper Avenue
Widening, from Rialto Avenue to East Rialto Channel, be approved.
We recommend that the plans be approved and authorization
granted to advertise for bids.
4-01-94
)5-0264