HomeMy WebLinkAbout21-Public Works
. .
CITY OF SAN BERN~_.IDINO -
From:
ROGER G. HARDGRAVE
REQUEST F,- ~ COUNCIL ACTION
File No. 6.44-5
Authorization to Execute Standard
Subject: Form Agreement - City of laDa Linda
- Development of East Valley Sub
Area Traffic Model
Dept:
Public Works
Date: 7-21-94
Synopsis of Previous Council action:
June, 1992 - Allocation of $150,000.00 approved in 1992/93 Budget
from the 1/2 cent Sales Tax Fund.
02-15-93 Authorization granted to issue Request for Proposals
in connection with the development of a Traffic
Forecasting Model.
09-06-93 Resolution No. 93-354 adopted entering into Agreement
for Professional Design Services - JHK.
03-21-94 Establishment of one additional position of
Engineering Assistant III approved.
04-04-94 Approval in principle of agreement with adjacent
cities.
06-20-94 Resolution No. 94-143 adopted establishing fee
schedule.
Recommended motion:
Adopt resolution.
cc: Shauna Clark
Jim Penman
a~
Signature -
Contact person:
Gene R. Klatt
&taff Report, Agreement
and Resolution
Phone:
5125
Supponing data attached:
Ward:
All"
FUNDING REQUIREMENTS:
Amount: $235,820 (!(: Sales Tax - Local Funds)
Source: (Acct. No.)
129-309-57731 f
, .
Forecastirtq Model
(Acct. DescriPtion) Congestion Management Traffic
Finance:~r/'~
/
Council Notes:
75-0262
Agenda Item No~
, CITY OF SAN BERN~~, IDINO - REQUEST F\ }I COUNCIL ACTION
STAFF REPORT
The City has entered into an agreement with JHK &
Associates to develop a Traffic Forecast Model for the City. In
doing the initial work, it was determined that the model, as a
basic requirement, must extend beyond the boundaries of the com-
muni ty. Al though not in great detail, it must look at the
surrounding communities and their traffic and land use data.
After investigation and contact with the adjacent
communi ties, it was determined that the cost of. ~xpanding the
model (by adding sufficient detail to the other "areas) would
produce a regional model and could be done at less cost than each
city preparing its own model. In turn, each adjacent city, in-
cluding Redlands, Highland, Grand Terrace, Colton, Lorna Linda and
Rialto, was contacted to see if there was interest in a joint
effort. All of the listed cities have expressed interest in a
joint effort. It is realized that a model that addresses all of
the concerns of the region, would speed the development process
and eliminate many points of conflict.
The result is the attached agreement which has been
reviewed and approved by all of the agencies, the City Attorney's
office, MIS and the Administrator's Office. In general, it sets
forth the operations, cost sharing, responsibilities, and duties
of each city. It received concept approval by the Mayor and
Common Council April 4, 1994.
The City of Lorna LInda has executed the agreement and it
is now ready to be approved by the City of San Bernardino.
We recommend that the agreement be approved.
"
7-21-94
75-0264
1
RESOLUTION NO.
2 RESOLUTION OF THE CITY OF SAN BERNARDINO AUTHORIZING THE
EXECUTION OF AN AGREEMENT WITH THE CITY OF LOMA LINDA RELATING TO
3 THE DEVELOPMENT, OPERATION AND MAINTENANCE OF THE EAST VALLEY SUB
AREA TRAFFIC MODEL.
4
BE IT RESOLVED BY THE MAYOR AND COMMON COUNCIL OF THE
5 CITY OF SAN BERNARDINO AS FOLLOWS:
6
SECTION 1. The Mayor of the City of San Bernardino is
7 hereby authorized and directed to execute on behalf of said City,
8 an agreement with the City of Lorna Linda for the development,
9 operation and maintenance of the East Valley Sub Area Traffic
10 Model, a copy of which agreement is attached hereto marked
11 Exhibit "A" and incorporated herein by reference as fully as
12 though set forth at length.
13 SECTION 2. The agreement shall not take effect until
14 fully signed and executed by both parties. The City shall not be
15 obligated hereunder unless and until the agreement is fully
16 executed and no oral agreement relating thereto shall be implied
17
18
19
20
21
22
or authorized.
SECTION 3.
The authorization to execute the above-
referenced agreement is rescinded if the parties to the agreement
fail to execute it within sixty (90) days of the passage of this
resolution.
"
/ / / /
23 / / / /
24 / / / /
25 / / / /
26 / / / /
27 / / / /
28 / / / /
7-21-94
RESO: EXECUTING AGREEMENT WITH CITY OF LOMA LINDA RELATING
TO THE \ST VALLEY SUB AREA TRAFFJ MODEL.
1 I HEREBY CERTIFY that the foregoing resolution was duly
2 adopted by the Mayor and Common Council of the City of San
3 Bernardino at a meeting thereof, held on the
4 day of , 1994, by the following vote, to-wit:
5 Council Members:
6 NEGRETE
7 CURLIN
8 HERNANDEZ
9 OBERHELMAN
10 DEVLIN
11 POPE-LUDLAM
12 MILLER
ABSTAIN
AYES
NAYS
ABSENT
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Rachel Clark, City Clerk
The foregoing resolution is hereby approved this
day of
, 1994.
Tom Minor, Mayor
Ci ty of San Bernardino
Approved as to form
and legal content:
James F. Penman
City Attor-ney
"
- 2 -
4-12-94
AGREEMENT
THIS AGREEMENT, made and entered into this ___ day of ,
1994, by and between the city of Lema Linda, a municipal
corporation of the State of California, hereinafter, referred to as
"Lema Linda" and the city of San Bernardino, a municipal
corporation of the State of California, hereinafter, referred to as
"San Bernardino".
WITNESSETH
WHEREAS, a transportation forecast model is needed by local
agenc~es in order to comply with provisions of the Congestion
Management Plan, apply for Federal-Aid Funds, and update
Circulation Elements of their general plans; and
WHEREAS, the proposed model needs to look beyond the boundaries of
each specific jurisdiction; and
WHEREAS, San Bernardino has entered into an Agreement with JHK and
Associates to develop a traffic model; and
WHEREAS, San Bernardino is willing to develop a larger model with
greater detail within "Lema Linda" provided "Lema Linda" pays
associated additional costs, as well as provides required data for
accurate model development; and
WHEREAS, Colton, Grand Terrace, Highland, Lema Linda, Redlands and
Rialto in the East Valley Sub Area have expressed an interest in
having San Bernardino extend the limits of the model to include
their incorporated areas in order to achieve cost savings through
economy of scale and consolidation of effort; and
WHEREAS, identical agreements may be entered into between San
Bernardino and each of the listed cities; and
WHEREAS, the development of a consistent model for the East Valley
Sub Area insures consistency and reduces development costs for all
participants; and
WHEREAS, San Bernardino has obtained a price quote from JH~ and
Associates for extending the limits of the model to include these
additional areas, in an amount of $235,820.00; and
WHEREAS, the traffic model will necessarily be developed in
accordance with the Southern California Associated Government's
(SCAG) Comprehensive Transportation Model for the County of San
Bernardino; and
-
WHEREAS, the traffic model developed pursuant to this Agreement
shall 1>e referred to as the "East Valley Sub Area Model"; and
Page 1
WHEREAS,
specify,
is to be
Lama Linda and San Bernardino do mutually desire to
herein, the terms and conditions under which said project
completed, financed, and maintained; and
WHEREAS, development of the expanded model is proposed for the
1994/95 fiscal year.
NOW, THEREFORE, IT IS MUTUALLY AGREED AS FOLLOWS:
SECTION ONE - SAN BERNARDINO SHALL --
MODEL DEVELOPMENT PERIOD
1.01 Perform necessary contract negotiations and administer the
contract with the selected development firm for creation of
said model.
1.02 Amend Agreement with JHK and Associates to include the other
cities in the East Valley Sub Area with the cost for the
expanded model distributed among the participating agencies as
set forth on Attachment A.
1.03 Act as Lead Agency in securing Environmental Review approval,
prepare all required reports, agreements, coordinate
activities of the consultant, advise "Lama Linda " of the
needed data, hold task force meetings with involved agencies
on progress and model development.
1.04 Prepare a working model, consistent with County Transportation
model as determined by SANBAG and acceptable to SCAG.
1.05 Arrange for collection of data necessary for the development
of the model.
1.06 Submit a model run for review and comment to "Lama Linda"
prior to final submittal to SANBAG and include "Lama Linda" in
the developmental meetings leading to the final model.
1.07 Submit quarterly bills to "Loma Linda" for their proportionate
share of the costs received by San Bernardino from the
Consultant for development of the East Valley Sub Area Model.
1.08 Submit a model run for "Loma Linda" of their street network
upon completion of project.
1.09 Obtain the necessary computer equipment, programs, and support
materials necessary to operate and maintain the model.
1.10 Accept responsibility for all costs of the project, including
prel;iminary model development, equipment acquisition,
staffing, applicable overhead charges, and any other costs
Page 2
directly attributable to project, except for the share to be
borne by "Loma Linda" as provided, hereinafter.
1.11 Submit an accounting to "Loma Linda" of all costs charged to
the project along with a statement for "Loma Linda's" share of
the cost.
MAINTENANCE OF MODEL AND ON-GOING MODELLING EFFORTS
1.12 Upon completion of the project, assume maintenance of the
model constructed within the area under jurisdiction of San
Bernardino and maintenance of the model with the jurisdiction
of "Lama Linda" to the extent that update information and
changes are submitted by "Loma Linda" as required in a timely
manner.
1.13 Prepare a cost accounting (hourly rate) that includes the
actual costs necessary for staff, benefits, and overhead for
updating the model, making requested model runs so "Lama
Linda" may request as many such runs as required to adequately
address development impacts within their jurisdiction and be
billed accordingly. The hourly rate shall be established and
adjusted annually based on increases in the services provided,
mandated salary increases, and other such factors but only
after review of data by parties to the agreement. The hourly
rate is set at $45.00 per hour for the first year of the
agreement.
1.14 Provide adequate staffing so the model remains current and
model runs can be made in a reasonable amount of time from the
request, provided "Lama Linda" makes update information
available as required. The City of San Bernardino will
maintain a log of requests, provide estimated time for
completion at time of request, commit to processing first in
first out, and provide overtime or priority service when staff
is available for such serivce and only upon payment of
increased fees.
1.15 Maintain a detailed record of any proposed changes to the
approved model, and secure "Lama Linda's" approval prior to
authorizing any major changes, thereof (major updates).
Maintain 10gs of requested model runs, agency that requested
and data supplied for model run. '
SECTION TWO - "Lama Linda" SHALL --
2.01 Assist San Bernardino in accomplishing the required data
collection for development of the model and correct input of
land use types and transportation networks.
-
2.02 Accept responsibility for the share of the project costs for
the enlargement of the model to include the city of "Lama
Page 3
Linda" and reimburse San Bernardino within 30 days after
receipt of an itemized statement of cost. "Loma Linda's"
share is estimated to be $8,673.00, but in no event shall
"Lema Linda's" total obligation under this agreement exceed
the actual cost of enlarging the model as determined by the
final contract change order issued to the selected consultant
and reviewed by "Loma Linda" provided that "Lema Linda" may,
at its sole discretion, in writing, authorize a greater amount
for additional work as desired.
2.03 Execute this agreement in a timely manner, but in no case
later than June 1, 1994, such that the project may'proceed and
be completed within the 1994/95 fiscal year with an
anticipated completion date of November, 1994.
2.04 Make those arrangements that may be necessary for the
collection of data on land use, transportation network, and
traffic counts as may be necessary for accurate model
development and/or maintenance.
2.05 Accept responsibility for the regular update information that
is required to maintain an accurate model and notify the City
of San Bernardino of major changes in land use, development
and/or traffic count data necessary for the development and
maintenance of the model.
2.06 Agree with the adopted cost accounting methods and charges to
be levied for model maintenance and model runs as requested by
"Loma Linda" in that they reflect the actual hourly wages and
benefits and overhead experienced by the City of San
Bernardino for providing said service. Accept that changes in
such charges shall occur as salaries are adjusted, benefit
costs increase, and other such changes occur within the
bargaining units within the City.
2.07 Agree to make no secondary sales of model information or
output that extend beyond the legal boundaries of the city of
"Lema Linda".
2.08 Agree to a uniform pricing schedule for model output or model
runs that is to be provided to all third parties (private
sector developers or consultants). Such rate shaJ.l be
determined at annual meetings of all participants to the
agreement and shall be established by majority vote of
participants in attendence at the annual meeting. General
Plan updates or information used exclusively by the City shall
be at the hourly rates established in Section 1.14.
Information used for encouraging development within the city
and delivered to third party interests shall be at a rate of
$90.00 and shall be established such that cost recovery for
model development and maintenance is included.
Page 4
2.09 Provide written instructions and acceptable data as approved
by "Loma Linda" in cases where "Loma Linda" directs that the
third party consultant deal directly with San Bernardino for
model information. Signed authorization forms will permit San
Bernardino to perform requested model runs using approved
input data and will be billed at the rate listed in 2.08.
2.10 Agree to negotiate an appropriate cost sharing method with all
model users in the event one or more of the model users
requests an upgrade or update of fixed assets (computer or
other hardware) prior to the projected useful life of the
equipment. .
SECTION THREE - BE IT FURTHER AGREED BY THE PARTIES HERETO --
3.01 That no part to the agreement, nor officer, nor employees,
thereof, shall be responsible for any damage or liability
occurring by reason of anything done or in connection with any
work, authority or jurisdiction delegated to the parties under
this Agreement. It is also understood and agreed that
pursuant to Government Code Section 895.4, each party shall
fully indemnify and hold all other parties harmless from any
liability for injury (as defined by Government Code section
810.8) occurring by reason of anything done or omitted to be
done under or in connection with any work, authority, or
jurisdiction delegated under this Agreement.
3.02 By combined funding, the cities are able to construct a larger
sized model than is planned by any of the cities and, thereby,
create additional capacity for analysis and a consistent
application of the modeling effort.
SECTION FOUR - TERMINATION --
4.01 Either party may terminate this agreement upon 30 day written
notice.
4.02 The City that is withdrawing from the agreement is entitled to
only a current model run (hard copy output or magnetic data
output) for that portion of the model contained within the
legal boundaries of their city. Data contained in the entire
model wilL.be subject to a negotiated price and availabl~ty of
supporting software. Negotiations shall consider overall cost
for model development, equipment, and support services.
4.03 After termination, the withdrawing City may request model runs
and data, but only as defined as a third party and subject to
the hourly charges established for third party requests.
4.04 Failure to provide necessary data for updates as required or
failure to provide them in a timely manner will result in that
portion of the model being inaccurate. Repeated failure to
Page 5
supply data or make efforts at model maintenance may result in
a request to terminate this agreement.
4.05 Should the city of San Bernardino terminate this agreement, a
copy of the full model at the time of termination shall be
provided to the local traffic agency (SANBAG) for use by the
participants. The supporting software, hardware, and other
such items will remain the property of the city of San
Bernardino.
THIS AGREEMENT shall inure to the benefit of and be ~inding upon
the successors and assigns of the parties involved.
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
IIII
"
Page 6
AGREEMENT: EAST VA~~EY SUB AREA TRAFFIC MODEL'
IN WITNESS WHEREOF, the parties hereto have caused this Agreement
to be executed by their respective officials thereunto duly
authorized.
ATTEST
By:
City Clerk
Approved as to form and
Legal content:
James F. Penman
City Attorney
CITY OF "Loma Linda"
~~~:-..~
Robert Christman, Mayor
City of "Loma Linda"
CITY OF SAN BERNARDINO
By
Tom Minor, Mayor
City of San Bernardino
, ,
Page 7
-=-
~