HomeMy WebLinkAbout46-City Administrator
CITY OF' SAN BER~ ARDINO - REQUEST ...OR COUNCIL ACTION
From:
Marshall W. Julian
City Administrator
City Administrator
Subject:
Request for reconsideration of the
Agreement with 235 Investments, Inc
for 360 spaces in the 5-Level
Parking Structure (Ward 1).
Dept:
Date: September 11, 1989
Synopsis of Previous Council action:
Agreement terminated.
Recommended motion:
That the action of the Mayor and Council terminating the Agreement to
allocating 360 parking spaces in the 5-Level Parking Structure for use
by 235 Investments, Inc. be confirmed.
-or-
That the request for reconsideration of the termination of the Agreement
allocating 360 parking spaces in the 5-Level Structure for use by
235 Investments, Inc. be continued and that the matter be referred to the
for possible amendments to the eement, pursuant
to the discussion at this meeting.
Contact person:
Marshall W. Julian
Phone:
5122
Supporting data attached: Staff Report
Ward:
1
FUNDING REQUIREMENTS:
Amount:
Source: (Acct. No.)
(Acct. Description)
Finance:
Council Notes:
75-0262
Agenda Item No.
Jf6<
CITY OF SAN BEIt.4ARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
The original Agreement with 235 Investments, Inc. was
terminated by the Mayor and Common Council at the meeting of
August 21, 1989, as follows:
"That the City Administrator be directed to
terminate the agreement with 235 Investments, Inc.
pursuant to the terms of the agreement."
Mr. Lew, spokesman for 235 Investments, Inc., was present at
the meeting of August 21st, but did not offer any suggestions
for mitigating the situation. He states that he is now
prepared to discuss all issues and is requesting the Mayor
and Council to reconsider the termination.
Mr. Lew has subsequently explained that sections 14 and 15,
wherein he was required to submit "plans" of the two
pedestrian walkways, were included at his request for the
convenience of the tenants of the Thrifty Building. These
access-ways are necessary to make the building more
functional. The plans which were submitted were not
adequate: however, Mr. Lew apparently will be able to present
appropriate plans if the termination is rescinded.
FILED:235
75-0264
C I T Y 0 F
San Bernardino
PUBLIC WORKS DEPARTMENT
R 0 G ERG
H A R 0 G R A V E
DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
August 11, 1989
File No. 6.50
Mr. Donald Lew
235 Investments, inc.
235 Montgomery Street, Suite 972
San Francisco, CA 94104
RE: Parking Agreement
Five-Level Parking Structure
Dear Mr. Lew:
A Parking Agreement was entered into on 5-10-89, between 235 Invest-
ments, Inc., the Redevelopment Agency and City of San Bernardino. This
Agreement stipulates the terms and conditions under which 360 parking
spaces in the five-level parking structure are leased for the Thrifty
Building.
Quarterly payments, in the amount of $18,263.00, are to be paid to the
City in advance. Payment of this amount has been received as the first
quarter payment, and to serve as the required performance bond.
The second quarter under the terms of this Agreement commenced on
8-10-89. Payment for this quarter has not been received as of this
date.
Section 14 provides that the owner will submit plans, within 90 days,
for the construction of a pedestrian bridge and walkway. This facility
is to span the area between the westerly side of the second level of
the parking structure and the easterly side of the Thrifty Building.
No plans were submitted for this pedestrian bridge and walkway.
Section 15 provided that the owner will submit plans, within 90 days,
for cons truc tion of a covered pedes trian ramp. This ramp is to span
the area from the fifth level of the parking structure to the second
floor of the Thrifty Building. The plan submi t ted does not show a
connection to the second floor. The plans also indicate an at-grade
crosswalk on the service alley, with steps down to the first level of
the parking structure. This was never contemplated in the Agreement.
300 NORTH D STREET SAN BERNARDINO
C A ,~ I FOR N I A 9 2 4 1 8 0 0 0' 7 1 4 I 3 8 4 . 5 1 1 1
Mr. Donald Lew
Parking Agreement
August 10, 1989
File No. 6.50
Page -2-
Failure to submit the second quarter payment in advance, and plans, as
stipulated in Section 14 and 15 of the Agreement, within the time-limit
specified, constitutes grounds for a breach of this Agreement.
The City Administrator will be presenting a report on the discrepancies
to the Mayor and Council, at their meeting of 8-21-89. The report will
permit compliance, or finding that there is a default in complying with
the terms and provisions of the Agreement, and that cancellation is,
therefore, in order. You would be well advised to be present at this
Council meeting.
Please contact me at (714) 384-5025 if you have any questions.
Very truly yours,
ROGER G. HARDGRAVE
Director of Public Works/City Engineer
RGH/ckc
cc: /,Marshall Julian
/' Steve Dukett
Jim Penman
Wayne Overstreet