CITY OF SAN BERNMRDINO~QU~~; N;,J~l~~UNCIL ACTION
Date: 9-15-89
Approval of Change Order No.
Subject: Four, and Approval & Acceptance
of Work--Construction of Relief
Sewer 1n Mill Street East of
Lytle Creek Plan No. 7305
BONADIMAN-McCAIN, INC.
From: ROGER G. HARDGRAVE
Dept: Public Works/Engineering
Synopsis of Previous Council action:
09-23-86 -- Allocation of $266,200 in Account No. 245-365-57724
"Relief Sewer in Mill Street - East of Lytle Creek"
approved.
Findings of Health and Safety for Installation of
Sewer.
Approval of Plans and authorization to advertise for
bids for Construction of Relief Sewer in Mill.
Resolution No. 88-270 adopted authorizing execution of
pipeline Lease Agreement with AT & SF Railway Company.
Resolution No. 88-374 adopted awarding a contract fOL
the low bid price of $434,091.00. F~
..,JH.J.
09-08-87
07-05-88
07-18-88
09-19-88
(j:l
f',-.,
-0
::~)
rq
C)
6
I
i'...) ;..",.
I. i
..'j./"
~ ~II",
Recommended motion:
cc:
1. That Change Order No. Four to the contract with Bonadiman-
McMain, Inc., for the construction of a relief sewer in Mil! ~
Street, east of Lytle Creek, in accordance with Plan No. 7 :3:~ 5 tr1
be approved; at an increase in the contract price of $12,5b2.59,
from $436,998.48 to $449,561.07.
2. That the work performed, pursuant to Plan No. 7305, be approved
and accepted, and final payment be authorized at the expiration
of the lien period. /'7) . ..?< 1
~!~:~!~~:~~~~~n (Ph ~iI :;{7
~
Supporting data atta~hed:
Roger G. Hardqrave
Staff Report
CCO #4
Phone:
5025
Contact person:
Ward:
.3
Source: (Acct. No.)
_,d t S-I . '7 ;
.J " ) I
$3-..f,412.~O (CCO#4 -$12,562.59,
Retention $~,845.921
245-365-57724 & 20125
'_'1.:<::0,'7/
,;.-. #.~'..- O. , .--
FUNDING REQUIREMENTS:
Amount:
__~_~~(i_?.!_gl__~-Y t 1 e Creek
Finance:
Acct. Descri tioD Relief Sewer
Council Notes:
--~----------~--
Agenda I tern No.
c::2.8
75-0262
CITY OF SAN BERtt",RDINO - REQUEST "'~R COUNCIL ACTION
STAFF REPORT
During construction, an unknown underground waterline and
a sewer lateral were encountered during the pipe jacking
operation. The water line was repaired and protected for a cost
of $658.03. The bootleg sewer lateral flooded the Contractor's
operation resulting in the loss of one day's production, totaling
$6,114.56 in costs.
Addi tionally, the native material used for backfilling
the trench in Mill Street was deemed unsuitable, due to the
Contractor being unable to obtain specified compaction. Our soil
consultant was unable to determine the unsuitability prior to the
Contractor's efforts to obtain compaction. Al though the
Contractor sustained substantial additional costs, we have
determined that $ 5,790 was beyond his contractual obligation.
Change Order No. Four will authorize the Contractor to perform
these items of extra work, at a net increase in the contract cost
of $12,562.59.
The total project budget included an amount of $69,509
for contingencies, which can be used to finance the additional
costs for the change orders.
The work was satisfactorily completed as of 6-14-89. The
contract was awarded for the low bid price of $434,091.00.
Change Orders One through Four authorized a net increase in the
contract price of $15,470.07 to $449,561.07. The actual final
contract price is $ 451,030.68, due to some variations in the
actual final quantities from the estimated quantities.
We recommend that the work be approved and accepted, and
that final payment be authorized. Also, that Change Order No. 4
be approved.
9-15-89
75-0264
Projett: Sewer in Mill S ~et from Lytle
Creek Channel to Mt. Vernon Avenue
Ffle No.
9-11-89
3.14-8
Plan Ho.
7305
ENGINEERING DIVISION
DEPARTMENT OF PUBLIC WORKS
CITY OF SAN BERNARDINO. CALIFORNIA
CONTRACT. CHANGE ORDER NO. FOUR
-
To:
Bonadiman McCain, Inc.
280 S. Lena Road
San Bernardino, CA. ~2410
Gentlemen:
You are hereby authorized and directed to perform the following
extra work on a time and material basis:
1. Expose & protect existing water line interfering
within Bore pit Station 14+85! . . . . ., $ 658.03
2. Re-excavate Bore pit after encountering sewer
line at Station 11+90! ........... 6,114.56
3. Compact and excavate unsuitable backfill material
in Mill Street -- 500 ft. @ $11.28/ft. ....... 5,790.00
Total extra work cost added to contract .............................$ 12,562.59
P. S 436,998.48
Previous Contract rlce ................................... .... ......
Amended Cost Pri ce .................................................. S 449, 561 . 07
Additional time to complete contract due to change order .... ........ 6 Working Days
CONTRACTOR:
CITY OF SAN BERNARDINO:
Accepted
By:
Approved
By:
Roger G. Hardgrave
Director of Public Works/City
Date
Engr.
Date
Title: