CITY OF SAN BER....HRDINO~EQUESTNf.JFtCOUNCIL ACTION
Dept: Public Works
l'28S StP ,~r(
Orr-.Subject: Authorization to Direct Extra
Services - Redesign of Entrance!
7 ,_~ Exit Ramps for 1-10 at Waterman
Avenue -- BOYLE ENGINEERING CORP.
From: ROGER G. HARDGRAVE 'zECJ, - j\D;~lf!.
Date: 9-27-89
Synopsis of Previous Council action:
Resolution No. 83-197 adopted approving the Tri-City
Redevelopment Plan and Final Environmental Impact Report.
Concept for modification of ramps approved.
Resolution No. 87-36 adopted, authorizing execution of a
revised Memorandum of Understanding with the California
Department of Transportation (Caltrans).
Authorization granted to issue Request for Proposals for
design engineering services.
Authorization to Execute Agreement for Professional
Engineering Services granted by Resolution 87-340.
Authorization to execute Cooperative Agreement with State
of California for construction of entrance/exit ramps at
1-10 at Hospitality Lane.
07-17 89 - Approval in principle to delete existing on-ramp. if
necessary.
06-20-83
08-06-84 -
02-02-87 -
02-02-87 -
09-21-87 -
05-17-89 -
Recommended motion:
That the Director of Public Works/City Engineer be authorized to
direct Boyle Engineering Corp. to provide extra services in connec-
tion with preparation of plans, specifications and estimate for
realignment of the ramp for Waterman Avenue, at Route 1-10, at an
estimated cost of $85,700.
cc: Marshall Julian
Jim Richardson
Steve Dukett
Andy Green
-a 4(JA~
Contact person:
Gene R. Klatt
Staff Report,
Letter
Phone:
5125
Supporting data attached:
Ward:
1
FUNDING REQUIREMENTS:
Amount: $85.700 (Est.)
Source: (Acct, No,)
242-362-57663
(Acct. Description) Waterman Av~nue at 1-10 Ramps
I. .,") ,-"_
Finance: \- "'v-"\',-c\.,-- 'J,-"':'--
Council Notes:
7 5-0262
Agenda I tern No. S - ~
CITY OF SAN BERN.....RDINO - REQUEST FvR COUNCIL ACTION
STAFF REPORT
Page 1 of 2
The agreement for professional services with Boyle
Engineering Corporation, as approved by the Mayor and Cornmon
Council on 9-21-87, provides for the performance of "extra
services" that exceed the original scope of the project, or are
additional in nature to the original concept of the project.
These extra services are to be performed only after written
authorization by the City and will be paid for in accordance with
the billing rates contained in the original agreement.
Upon submittal of the 95% complete project drawings and
specifications, Cal trans, during their review, voiced concerns
regarding design, concept, limits of the project and other
aspects of the design that had not been previously addressed in
the approved proj ect Report, or any of the previous design
reviews.
These concerns were: (1) the transition area between the
existing on-ramp and the 1-10/1-215 interchange, (2) median
protection, (3) sign bridges, (4) need to provide a High
Occupancy Vehicle lane on the new entrance ramp, (5) metering
requirements on the existing ramp, '(6) additional signing for the
existing freeway ramps, (7) need for irrigation and landscape
plans and (8) adequacy of data contained in the project report.
After much discussion and several meetings, it was determined
tha t design variances would be sought for some items, but design
changes would be required to comply with Caltrans' current
requirements and to secure their approval on the remaining items.
The indicated changes in the plans, specifications and
estimates, corning at the time of early complete documents, will
cause major rework of these documents. Redesign of the bridge,
grades, transitions, signals and other items are all new items of
work. The Engineer has submitted a letter (attached) detailing
the estimated cost of the various modifications in the drawings
and documents. At the time this letter was prepared, several
items were still being discussed with Caltrans and no resolution
was yet reached. It is not possible to give a fixed dollar
estimate at this point in time. However, staff is recommending
that the Director of Public Works/City Engineer be authorized to
give written direction to the Engineer to proceed with the
necessary changes as required by Cal trans, to meet with the
engineer and establish an accounting method agreeable to both to
track the extra work and to approve progress payments for the
extra work. The present estimate for the extra work is
$85,700.00, while the original contract amount was $199,994.00.
Cost incurred for preparation of the design documents is
to be paid by the Redevelopment Agency, under terms of the
cooperative agreement with Caltrans. The cost incurred for con-
tract administration will be the responsibility of Caltrans.
9-27-89
75-0264
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Page 2 of 2
Staff recommends approval of the authorization to direct extra
work.
URGENCY CLAUSE
It is essential that the Engineer be allowed to proceed with the
extra work so as to finish the project and allow the bidding
process to begin. The project is already several months behind
schedule and additional delays will likely impact development in
the Tri City area and traffic congestion in the City.
Attach.
75-0264
.... _' ...:... t ~. r"" .. \ ~ i": ~
, 1 ,,~:....,:: ',,"
~ i~?.,='.~
:A
I (
I
. :.., - ~ -;-: - - .
SOLlIe EnQlneerli!tiJ ttDtTiIc;.atlatf-
consultlnQ enqlneers arcnltects
::;wC", 306
7 :J50 South SU/lwest Lane
San Bernardino, California 92408
774 824-5580
FAX 714/ 884-1594
Mr. Gene Klatt
Assistant City Engineer
CITY OF SAN BERNARDINO
300 North D Street
San Bernardino, California 92418
September 12, 1989
1-10 On and Off Ramps at Carnegie
During our last project meeting on August 21, 1989, I committed to provide a revised
schedule for project submittal and the costs for additional services for the revisions
required by Caltrans in Bill Ojeda's letter of August 18, 1989. The purpose of this letter is
to provide the requested information. It is shown in tabular form below.
ITEM
COST
$77,200
PROJECTED SCHEDULE
REQUIREMENTS
2. Channel Improvements
(Associated with On
Ramp Bridge -- Refer
to Boyle letter of
10/5/88 and 6/26/89)
$ 8,458
* 14 weeks from written
authorization and
receipt of traffic
volumes for signal
design
* 14 weeks from written
authorization
1. Design and Plan Revisions
(Requested in letter of
8/18/89 -- Refer to
attached Table A)
3. Landscaping/Erosion
Control Plans and
Specifications
To be determined
after future meeting
To be determined
* The fourteen (14) weeks break down as follows:
o Written authorization to geometric submittal of On-Ramp -- 4 weeks.
o Review and acceptance of geometries -- 2 weeks.
o Completion of work -- 8 weeks.
O! :ll H't ~ i d:S 68
. - \ c~. ,.'1,; ~ _.~. .:;- .
.~. .": .J -;:, ~
,~ ... ...... .. --
'.~ ~,_';...1 -..~:: -;,..;
~1~~ ~,~: ~ '"~J~~ \\-':': ::-~ ,: ~.
Mr. Gene Klatt
Assistant City Engineer
September 12, 1989
Page 2
Therefore, in accordance with Section 3 of our Agreement for Professional Services, we
request written authorization for an increase to the Agreement in the amount of $85,658.
The costs for the Landscaping/Erosion Control Plans will be forwarded in a separate
request following the meeting to determine the required scope. Upon receipt of your
written authorization, we will proceed with the work in order to complete the project. We
would expect to deliver the entire project submittal in 14 weeks from written authorization.
If you have any questions regarding this matter, please notify me.
"BO~~~:TION
Ron B. McBryde, P.E.
Project Manager
xc: Bruce Mattern
Tiit Zimmermann
Bob Kershaw
Carl Anderson
Allen Randall
Fred Carlson
88-842-1 ()().() 1 /sj
waterman-lrevlse.doc
TABLE A
DESIGN AND PLAN REVISIONS
Estimated
Sheet No. Revision Required Cost
SC-1 Minor Changes to notes -- Reference notes for $220.00
new sheets, minor additional changes due to
scope change.
SC-2 Extend Work area -- Redraft area to be extended 220.00
for additional widening.
SC-3 Minor Changes -- Ramp station-line shift, minor re- 220.00
draft.
SC-4 Extend work area and modify detour -- Work area 1,000.00
change, lane line change. Redraft to remove
items from' extension area.
SC-5 New sheet showing Traffic control for Overhead 3,500.00
sign Modification. ,
CS-2 Tabulate additional signing for SC-5 -- Additional 550.00
signing and striping for traffic control for added
sheet, for overhead sign modification.
CS-3 No changes.
PD-1 Modify Striping -- Shoulder area being narrowed, 950.00
extensive striping changes, drafting.
PD-2 Modify Ramps -- Right turn lane being added, 550.00
ramp configuration changes.
PD-3 Modify Ramps -- Extensive changes require 1,400.00
extensive redraft - almost complete new sheet.
Estimated
Sheet No. Revision Required Cost
PD-4/5 Modify Quantities per change to PD-1,2 and 3 -- 550.00
Ramp configuration changes, additional lane lines
- quantities changed.
8-1 Ramp Widening -- Ramp being widened, need to 1,200.00
redraft, all data to outside of widening area.
8-2 Ramp Extension -- Widening extended, lane 550.00
changes and shift of data.
8-3 Minor Modifications -- Drafting to relocate signs 220.00
and additional signage.
8-4 Minor Modifications -- Overhead sign addition. 220.00
8-5 New sheet Detailing Overhead sign Extensions -- 3,500.00
addition of Overhead sign modifications.
E-1 Redesi~n Si~nal -- Approach widening change, 4,500.00
pole sc edu e change, affects conductor runs,
sign extensive redesign, redrafting.
Modify Background for Auxiliary Lane and Barrier
Extension.
New Work to light new signs replacing the 2 that
are being dismantled.
E-2 Widen Ramps -- Change affects conductor runs, 2,700.00
signs - redrafting.
Modify Exit and Entrance Ramp at Hospitality
Lane (Background change and conduit relocation)
Modify Entrance Ramp from Waterman Ave.
E-3 Modify Ramp -- Widening, Center line shift, 1,100.00
redrafting.
Modify Exit and Entrance Ramp at Hospitality
Lane (Background change and conduit relocation)
Estimated
Sheet No. Revision ReQuired Cost
L-1 MOd~ Auxiliary Lane -- Reduce shoulder width 2,900.00
from 0 feet to 8 feet along .WNINline, shift WNIN
line 2 feet northerly between stations 149 + 62.89
and 155 + 73.90 BC, extend type 50 barrier to
~ where the distance between WNIN line and
of connector ramp is 6 feet.
L-2 Modify Auxiliary Lane - Reduce Shoulder width 2,500.00
from 10 feet to 8 feet along .WNIN line.
L-3 Extend High Occupancy Vehicle lane - Widen 2,650.00
entrance ramp to accommodate Hi~h Occupancy
Vehicle lane and taper, modify profi e to
accommodate height requirement over creek due
to superelevation.
L-4 Extend High Occupancy Vehicle lane -- Add right 3,600.00
turn lane, widen entrance ramp to accommodate
High Occupancy Vehicle lane, modify profile, add
minimum 200 foot right turn pocket to exit ramp,
modify curb return.
.
0-1 Modify Drainage along "WNINline -- Determine 1,000.00
new Draina~e Inlet and outlet locations, pipe
profile, and ength.
0-2 Modify drainage along "WNI" line -- Determine new 3,200.00
Drainage Inlet and outlet locations, pipe profile
and length.
0-3 Modify Drainage along new Entrance Ramp -- 2,000.00
Determine new Drainage Inlet locations and piping
system configuration and profiles.
0-4 Modify Drainage along new Entrance and Exit 3,900.00
ramps -- Determine new Drainage Inlet locations
and piping system configuration and profiles.
0-7 Same as 0-3 and 0-4. 1,500.00
.--~'--
Sheet No.
58-542.1 ()()'()1 /SJ
waterman-revlse.doc
..~<'-
Rev,sion ReQuired
Overhead sign structures --
1. Determine if structure needs to be moved. If
not, cost would be minimal.
2. If Structure is moved, determine new length,
and if standard design can be used or engineering
is required.
3. If engineering is required, we will need Caltrans
Division of Structures approval.
San Timoteo Creek Bridge -- Redesign bridge to
accommodate added width for High Occupancy
Vehicle lane. Cost includes Revised Design, Plan
Check, Quantities, and revised Specifications.
Other Direct Expenses:
Computer
Reproduction
Project Management and attendance of project
meetings.
TOTAL
Estimated
Cost
11,000.00
11,000.00
6,000.000
300.00
2,500.00
~77.200.00