CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
Date: June 10, 2009
Authorize the Director of
Development Services to execute
Contract Change Order No. One with
Cooley Construction, Inc. for Street
Improvements on Kendall Drive from
Bailey Court to Wagonwheel Road
(SS06-35), Per Project Plan no. 11428.
From: Valerie C. Ross, Director Subject:
Dept: Development Services
File Nos. 1.7584
MCC Date: July 6, 2009
Synopsis of Previous Council Action:
09-02-08 The Mayor and Common Council approved FY 2008-09 CIP budget.
10-20-08 The Mayor and Common Council adopted a Resolution awarding a contract to
Cooley Construction, Inc. for Street Improvements on Kendall Drive from Bailey
Court to Wagonwheel Road (SS06-35), Per Project Plan no. 11428.
Recommended Motion:
Authorize the Director of Development Services to execute Contract Change Order No. One
with Cooley Construction, Inc. for Street Improvements on Kendall Drive from Bailey Court
to Wagonwheel Road (SS06-35), Per Project Plan no. 11428.
~ 1/. 1<.Wv"
Valerie C. Ross
Contact Person: Robert Eisenbeisz, City Engineer
Phone: Ext. 5203
Supporting data attached: Staff Report & CCO No. One
Ward: 5
FUNDING REQUIREMENTS: Amount: $ 29,827.00
Source: (Ace!. Nos.)
126-369-5504-7584
Acct. Description:
Gas Tax Fund
Finance:
Council Notes:
Agenda Item No.J 4
1~fI-OIif
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT
Subject:
Authorize the Director of Development Services to execute Contract Change Order No. One with
Cooley Construction, Inc. for Street Improvements on Kendall Drive from Bailey Court to
Wagonwheel Road (SS06-35), Per Project Plan no. 11428.
Background:
This segment along Kendall Drive needed to be widened in order to provide additional capacity
and travel lane continuity. In order to provide a continuous accessible path of travel it was
necessary to acquire right-of-way and install a 4-foot wide sidewalk on the northerly portion of
Kendall Drive.
Change Order:
During construction of the project the contractor encountered the following conditions:
1. Two of the three fire hydrants would have to be relocated to accommodate an existing utility
pole. It was necessary to replace two of the three fire hydrants to a dry barrel type for safety,
because the relocation spot was directly under the high voltage power lines. Due to the fire
hydrant replacement the contractor needed to remove the old fire hydrant runs at the
mainline, and connect a new valve to the existing mainline to allow water to flow to the
relocated fire hydrants. The additional work was completed at a cost of $20,009.00.
2. The bid called for three fire hydrants to be replaced, two of the three fire hydrants needed to
be replaced with a dry barrel type for safety due to the high voltage power lines. Two of the
fire hydrants in the original bid were not used; as a result the City had a credit of $5,300.00.
3. During construction it was determined that eleven water meters needed to be replaced. The
original design plans only showed that seven water meters needed to be replaced. The
additional work was completed at a cost of $3,200.00.
4. During construction it was determined that five of the eXlstmg water meters included a
pressure-reducing valve (PRY) that was not previously known. It was necessary to relocate
the PRY behind the property line. The additional work was completed at a cost of $2,500.00.
5. During construction it was determined that the property located at 2548 W. Kendall Drive
had two services instead of one, which is typical, located off the back of the water meter. It
was necessary to relocate the additional I" service. The additional work was completed at a
cost of $600.00.
2
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT (Continued)
6. During construction it was determined that two Italian Cypress trees needed to be removed in
order to allow the new improvements to be constructed. The additional work was completed
at a cost of$I,IOO.OO.
7. During the brush clearing operations the contractor came across a sewer clean out and hose
bib were not previously known. It was necessary to relocate the sewer clean out and hose bib
to private property before construction could take place. The additional work was done at a
cost of $2, I 00.00.
8. After the brush clearing operations of the existing landscaping it was determined that 80
linear feet of existing chain link fence would have to be installed because the existing fence
was too deteriorated to relocate. In order to match the newly constructed chain link fence the
contractor was directed to remove the existing chain link gate and construct a new chain link
gate. The cost to remove and construct a new chain link fence with a gate was $2,510.00.
9. Due to the new chain link gate the City had a credit of $740.00. The bid documents originally
required the contractor to relocate the chain link gate.
10. In order to make a smooth transition between Bailey Court and Pine A venue it was necessary
to add additional striping. The additional work was completed at a cost of$I,480.00.
II. In order to acquire the necessary right-of-way located at 2532 Kendall Drive an agreement
was made to plant four pine trees at this location. The trees were planted at an additional cost
of $1 ,368.00.
Financial Impact:
The revised estimated project costs are as follows:
TOTAL
Original Contract Amount $421,865.20
Contract Change Order No. One $29,827.00
Reimbursement by SBMWD ($8,604.50)
Total Project Cost $443,087.70
This change order represents a net increase of 7.07% of the original contract amount. There are
sufficient funds in the project account to cover this change order.
3
CITY OF SAN BERNARDINO - REQUEST FOR COUNCIL ACTION
STAFF REPORT (Continued)
Recommendation:
Authorize the Director of Development Services to execute Contract Change Order No. One with
Cooley Construction, Inc. for Street Improvements on Kendall Drive from Bailey Court to
Wagonwheel Road (SS06-35), Per Project Plan no. 11428.
Attachments:
Change Order No. One
4
DEVELOPMENT SERVICES DEPARTMENT
300 North "D" Street. San Bernardino. CA 92418-0001
Planning & Building 909.384.5057 . Fax: 909.384.5080
Public WorkslEngineering 909.384.5111. Fax: 909.384.5155
www.sbcity.org
'"
CONTRACT CHANGE ORDER NO. ONE
FILE NO. 1.7584
W.O. NO. 7584
DATE: JULY 6, 2009
PROJECT: STREET IMPROVEMENTS ON KENDALL DRIVE FROM BAILEY
COURT TO WAGONWHEEL ROAD (SS06-35), PER PROJECT PLAN
NO. 11428.
TO: COOLEY CONSTRUCTION, INC.
P.O. BOX 401810
HESPERIA, CA 92340
GENTLEMEN:
You are hereby compensated for performing the additional work as follows:
ITEM NO: DESCRIPTION OF CHANGE COST
1-1 Install 3 New Fire Hydrants (3 @ $4,025) $ 12,075.00
1-2 Abandon 2 Fire Hydrants at Flange (2 @ $747) $ 1,494.00
1-3 Hot-Tap Mainline (2 @ $3,220) $ 6,440.00
1-4 Eliminate 2 of 3 Hydrants in Bid Item No. 14 (2@ $2,650/ea) $ 15..1110.1111)
1-5 Increase Bid Item No. IS (4 @ $800) $ 3,200.00
1-6 Relocate Pressure Reducing Valve (5 @ $500) $ 2,500.00
1-7 Relocate I" Water Service $ 600.00
1-8 Remove 2 Italian Cypress Trees (2 @ $550) $ 1,100.00
1-9 Relocate Sewer Clean Out and Hose Bib $ 2,100.00
Increase Bid Item No. 21 - Remove & Construct New Chain-Link .
1-10 Fence (80 U. @ $32/per U. $ 2,560.00
1-11 Increase Bid Item No. 22 - Remove Existing Chain-Link Gate & $ 950.00
Construct New gate (1 @ $950/ea)
1-12 Decrease Bid Item No. 20 - Relocate Existing Chain-Link Gate (1 $ 1~.jO.1I01
ia) $740/ea)
1-13 Additional Striping $ 1,480.00
CHANGE ORDER NO. ONE - COOLEY CONSTRUCTION. INC.
STREET IMPROVEMENTS ON KENDALL DR FROM BAILEY CT TO w AGONWHEEL RD (SS06-35). PER PROJECT PLAN NO.
11428.
1-14 I Plant Elderica Pine Trees (4 @ $342/ea) $ 1,368.00
TOTAL COST CCO #1 $ 29,827.00
JUSTIFICATION:
Install 3 New Fire Hvdrants (3 @) $4,025)
During construction, it was determined that 2 fire hydrant runs would have to be
relocated & all 3 fire hydrants would have to be replaced. The plans required the
Item 1-1 existing fire hydrants to be relocated behind the new curb & gutter. It was determined
No. that this would place 2 of the hydrants too close to the existing utility pole and they
would then become inoperable. It was necessary to replace all 3 fire hydrants to a dry
barrel type for safety. as the relocation placed the hydrant directly under the high
volta"e power lines.
Abandon 2 Fire Hvdrants at Flange (2 @) $747)
1-2 Item No. I-I required the contractor to relocate 2 fire hydrant runs; therefore. the
contractor was required to remove the old runs at the mainline and blind flange the
connection.
Hot -Tap Mainline (2 @) $3,220)
1-3 Item No. I-I required the contractor to hot-tap a new valve to the mainline for the
relocated fire hydrant run.
1-4 Eliminate 2 of 3 Hydrants in Bid Item No. 14 (2@) $2,650/ea)
The contractor provided a credit for contract bid Item No. 14.
Increase Bid Item No. 15 (4 @) $800)
1-5 The project plans required 7 water meters to be relocated. In the field, it was
determined to be II meters in need of relocation.
Relocate Pressnre Reducing Valve (5 @) $500)
1-7 During construction, it was determined that 5 of the existing water meters included a
pressure-reducing valve (PRV). It was necessary to relocate the PRY behind property
line.
Remove 2 Italian Cypress Trees (2 @) $550)
1-8 2 additional Italian Cypress trees were removed to allow the new improvements to be
constructed.
Relocate Sewer Clean Out and Hose Bib
1-9 During clear and grub operations, a sewer clean-out and hose bib were discovered. It
was necessary to relocate the sewer clean-out and hose bib to private property.
Increase Bid Item No. 21 Remove & Construct New Chain-Link Fence (80 I.f.
@) $32/per I.f.
1-10 After the contractor completed the clearing and grubbing of existing landscaping, it
was determined that 80 !.f. of existing chain-link fence was too deteriorated to
relocate; therefore, the contractor was reauired to replace the chain-link fence.
Increase Bid Item No. 22 - Remove Existing Chain-Link Gate & Construct New
1-11 gate (1 @) $950/ea)
A new gate was provided to match new chain-link fencing at one location.
Decrease Bid Item No. 20 - Relocate Existing Chain-Link Gate (1 (a) $740/ea)
1-12 Credit for not relocating one existing chain-link gate. A new gate was provided per
Item No. 1-13, below.
o
CHANGE ORDER NO. ONE - COOLEY CONSTRUCTION. INC.
STREET IMPROVEMENTS ON KENDALL DR FROM BAILEY CT TO W AGONWHEEL RD (SS06-35). PER PROJECT PLAN NO.
11428.
Additional Striping
1-13 It was necessary to add additional striping between Bailey Ct and Pine Ave to create a
smooth transition into the stri in for the Kendall Ave ro' ect.
Plant Elderica Pine Trees (4 (fj) $342/ea)
1-14 Planted 4 Elderica Pine trees for 2532 W. Kendall Dr, per Agreement made by real
ro ert .
SUMMARY OF CONTRACT COSTS
The estimated revised contract cost is as follows:
Original Bid Amount. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..... $ 421,865.20
Contract Change Order No. One............................ ....$ 29.827.00
Revised Construction Contract cost. . . . . . . . . . . . . . . . . . . . . . . . . . .....$ 451,692.20
Reimbursement by SBMWD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 8,604.50
Additional time to complete Contract due to this Change Order ................... 10 Working Days
This change order represents 7.07 % of the original contract amount.
COOLEY CONSTRUCTION, INC.
CONTRACTOR
Accepted
By:
CITY OF SAN BERNARDINO
DEVELOPMENT SERVICES
Approved
By:
VALERIE C. ROSS
Director of Development Services
Title:
Date:
Date:
Approved
By:
CHARLES McNEELY
City Manager
Date:
[tern No.
July 6, 2009
.,